Mdn Real Estate L.L.C ام دي ان للعقارات ش.ذ.م.م 13 projects in the DLD register: 13 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
13
in the DLD register
Completed
13
2,521 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 13Completed 13
- Median time from start to completion: 36 months (13 completed projects).
- 2,521 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 12 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Mdn Real Estate L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Mudon Al Ranim 32444 · Al Hebiah Sixth · Mudon | Completed | 100% | Sep 2025 Completed | 242 | 141 |
| Mudon Al Ranim 62648 · Al Hebiah Sixth · Mudon | Completed | 100% | Jul 2026 Completed | 242 | 109 |
| Mudon Al Ranim 12399 · Al Hebiah Sixth · Mudon | Completed | 100% | Oct 2025 Completed | 224 | 102 |
| Mudon Al Ranim 52638 · Al Hebiah Sixth · Mudon | Completed | 100% | Jul 2026 Completed | 182 | 96 |
| Mudon Phase 3 _ Neighbourhood I- Arabella1659 · Al Hebiah Sixth · Mudon | Completed | 100% | Sep 2018 Completed | 663 | 93 |
| Mudon Al Ranim 22419 · Al Hebiah Sixth · Mudon | Completed | 100% | Dec 2025 Completed | 176 | 89 |
| Mudon Al Ranim 42549 · Al Hebiah Sixth · Mudon | Completed | 100% | Jan 2026 Completed | 134 | 89 |
| Arabella 31877 · Al Hebiah Sixth · Mudon | Completed | 100% | Jul 2020 Completed | — | 66 |
| Mudon Al Ranim 72699 · Al Hebiah Sixth · Mudon | Completed | 100% | Sep 2026 Completed | 248 | 63 |
| Mudon Views1874 · Al Hebiah Sixth · Mudon | Completed | 100% | Feb 2020 Completed | 181 | 58 |
| Mudon Al Ranim 82701 · Al Hebiah Sixth · Mudon | Completed | 100% | Sep 2026 Completed | 228 | 57 |
| Arabella 2 - Townhouses At Mudon1714 · Al Hebiah Sixth · Mudon | Completed | 100% | May 2020 Completed | — | 55 |
| Mudon-Phase 21521 · Al Hebiah Sixth · Mudon | Completed | 100% | Feb 2016 Completed | 1 | 44 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.