DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

ME DO RE Properties DMCC مي دو ري بروبيرتيز م.د.م.س DLD developer no. 1379 · Registered with DLD on 13 October 2021 · Licence DMCC-351526 2 projects in the DLD register: 1 completed, 1 under construction, 0 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
2
in the DLD register
Completed
1
394 units delivered
Not yet completed
1
293 units in the pipeline
Past DLD end date
0 / 1
under construction with an end date

Delivery record

Projects: 2
Completed 1Under construction 1
  • 394 units and villas in completed projects; 293 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 0 of 1 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by ME DO RE Properties DMCC Most registered sales in the last 24 months first

Projects by ME DO RE Properties DMCC
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Me Do Re2505 · Al Thanyah Fifth · DMCC Master Community Completed 100% Jan 2024 Completed 394 55
ME DO RE Business3409 · Al Thanyah Fifth · DMCC Master Community Under construction 24.5% Sep 2029 34 mo to go 293 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 1, all pinned

ME DO RE Business · Under construction, 0–25% builtME DO RE Business · Under construction, 0–25% builtMakani
Under construction, 0–25% built

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.