DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 3409Under construction293 units

ME DO RE Business مي دو ري بزنس Al Thanyah Fifth · DMCC Master Community by ME DO RE Properties DMCCAll phases of DMCC Master Community 24.5% built (DLD register as of 1 November 2026) DLD end date Sep 2029 34 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
24.5%
DLD register, 1 November 2026
Period elapsed
25%
Nov 2025 → Sep 2029
Latest sales
—
Fewer than 5 recent sales
Developer
2 projects
1 completed · 394 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built and period elapsed

1 November 2026
Built
24.5%Elapsed
25%

Two separate measures: one is DLD's % built, the other is time on the calendar.

Latest DLD register reading: 24.5% built on 1 November 2026 (register readings: 2). Latest DLD inspection: 24.5% built on 21 November 2024 (inspections: 1).
Every DLD inspection and every change in the register %, newest first
Date % built Source
21 November 2024 24.5% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.

Our completion calculation

Pace since the last two DLD readings: —

Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Changes in the DLD register

1 Nov 2026Construction completed: 24.5% → 24.5%.

Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

Building permits

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Buildings
1
1 on construction permits
Permit status
Open
438614
Issued
7 November 2024
Consultant · contractor
ARCHITECTURE & PLANING GROUP L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
No stage listed1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
3409
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Dubai Municipality
Master project
DMCC Master Community
DLD area
Al Thanyah Fifth
Units · villas
293 · 0
Start → DLD end
Nov 2025 → Sep 2029

Description in the DLD register: Commercial Tower Development located at Jumeirah Lakes Towers. The building is designed as 4B+1UB+G+39Floor+1 Mech Floor+ Roof+ Upper Roof Commercial Tower located on Plot No. H1 3930899, the building formed in a concrete structure, currently built until the eleventh floor, internal blocks with and an external curtain wall glazing system. The units will be handed over as core and shell construction.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Rents in DLD area Al Thanyah Fifth

New Ejari rent contracts for apartments across DLD area Al Thanyah Fifth, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 58,000 1,004 -3.3%
1 BR AED 82,000 2,305 -3.5%
2 BR AED 120,000 1,149 -4%
3 BR AED 165,000 270 -2.9%
4 BR AED 250,000 20 +8.7%
5 BR AED 490,000 9 —

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.76 AED/sqft a year
DMCC Master Community: median of 32 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Looking for a unit in this or similar projects?

Tell us what you are looking for in ME DO RE Business or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).

Automated estimate, not a valuation

Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Resale asking prices against the original price

Fewer than 5 resale offers with an original price are tracked for this project.

Across all Dubai off-plan resale offers we track: -3.9% (1,105 offers).

Median asking premium by share of the price already paid (number of offers); shown from 5 offers
Paid to the developer This project All Dubai
0–30% paid—0% (9)
30–50% paid—-5% (51)
50–70% paid—-1.5% (65)
70% paid or more—-3.5% (45)

Asking prices of off-plan resale offers we track, compared with each offer's original price, with the 4% DLD fee removed on both sides. A negative value means asking below the original price. Only aggregates of at least 5 offers are shown; no individual offer, seller or agent is.

Thinking of selling your unit?

Thinking of reselling your unit in ME DO RE Business? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Sep 2029); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Sep 2029
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in ME DO RE Business? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationAl Thanyah Fifth · Dubai Municipality community

Edelweiss Market · 70 mSunrise Supermarket JLT · 130 mKP Mart · 260 mDMCC Metro Station · 600 mJumeirah Lakes Towers Park · 620 mJumeirah Lakes Towers · 710 mPark · 710 mDubai Marina Mall · 800 mPark · 860 mDubai Marina Mall · 900 mDAMAC Properties Metro Station · 1.2 kmEmirates International School - Meadows · 1.3 kmLux Aeterna Clinic · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Metro and tram Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationDMCC Metro Station · Red Metro line · 600 m
Tram stopJumeirah Lakes Towers · Tram line · 710 m
MallDubai Marina Mall · 900 m
SupermarketEdelweiss Market · 70 m
HospitalLux Aeterna Clinic · 1.4 km
SchoolEmirates International School - Meadows · 1.3 km
ParkJumeirah Lakes Towers Park · 620 m
BeachMarina Beach Dubai · 1.8 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 26, with 18,346 units and villas.

2023: 9262025: 3,0732026: 2,3052027: 2,2302028: 1,6492029: 1,4122030: 2,9562031: 2,169No end date: 1,626

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Thanyah Fifth: 22

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Eltiera Views 0% Dec 2029 2,591 647
Serenia District - West 2.8% Dec 2028 2,441 378
Eltiera Heights 3% Dec 2028 2,530 303
Serenia District - East 1.1% Jun 2030 2,592 124
Signature Lifestyle Residences 8.1% Dec 2028 3,171 115

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Thanyah Fifth

Developer in DLD data ME DO RE Properties DMCC · DLD developer no. 1379

Projects registered
2
1 completed · 1 under construction · 0 not started
Units delivered
394
293 in the pipeline
Past the DLD end date
0
of 1 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in DMCC Master Community

DLD lists 68 projects in the master project DMCC Master Community.

The Wind Tower IUnder construction · 74.6% · Jun 2023
The Wind Tower IiUnder construction · 84.5% · Jun 2023
Me Do Re 2Under construction · 97.8% · Dec 2025
Uh West By EllingtonUnder construction · 83.7% · Mar 2026
Uh East By EllingtonUnder construction · 62.8% · Mar 2026
Viewz 1 By DanubeUnder construction · 66.5% · Jun 2026
Viewz 2 By DanubeUnder construction · 65% · Jun 2026
MBL SignatureUnder construction · 60.1% · Mar 2027
Saba 4Under construction · 30.4% · Jun 2027
Verde by SobhaUnder construction · 85% · Jun 2027
Mercer HouseUnder construction · 18.1% · Jul 2027
Signature Lifestyle ResidencesUnder construction · 8.1% · Dec 2028

Questions about ME DO RE Business

When is ME DO RE Business's handover?

DLD lists an end date of Sep 2029 (register of 1 November 2026); the SPA sets the handover terms.

Is ME DO RE Business past its DLD end date?

No. Its DLD end date is Sep 2029, 34 months after the register of 1 November 2026.

How far along is ME DO RE Business?

24.5% built in the DLD register of 1 November 2026.

Who is the developer of ME DO RE Business?

ME DO RE Properties DMCC, as registered with DLD.

What is the DLD project number of ME DO RE Business?

3409.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error