DLD master projectAl Thanyah Fifth
DMCC Master Community 17 of 69 phases not yet completed · 10,225 units · 4,453 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
DMCC Master Community has 69 projects in the Dubai Land Department projects register as of 1 November 2026: 17 not yet completed, with 10,225 units and villas. By DLD status: Under construction 15 · Conditionally activating 2 · Completed 52. Under construction and past the DLD end date: 7.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 68 of the 69 phases: those with a map pin. Pins mark approximate locations.
Al Thanyah Fifth (DM community)Jabal Ali First (DM community)
Phases (69)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Diamondz By Danube | Under construction | 18.5% | — | — | 1,225 | 637 | +1.5% |
| Seven City Jlt | Conditionally activating | 28.4% | Nov 2025 11 months past it | 11 months past it | 2,666 | 325 | — |
| Saba 4 | Under construction | 30.4% | Jun 2027 7 months to go | 7 months to go | 547 | 251 | +1.4% |
| Me Do Re 2 | Under construction | 97.8% | Dec 2025 10 months past it | 10 months past it | 407 | 237 | — |
| MBL Signature | Under construction | 60.1% | Mar 2027 4 months to go | 4 months to go | 463 | 230 | +6.6% |
| Mercer House | Under construction | 18.1% | Jul 2027 8 months to go | 8 months to go | 610 | 215 | +8.8% |
| Verde by Sobha | Under construction | 85% | Jun 2027 7 months to go | 7 months to go | 610 | 187 | +2.2% |
| MBL Royal | Completed | 100% | Mar 2025 | — | 333 | 141 | +8.4% |
| Uh West By Ellington | Under construction | 83.7% | Mar 2026 7 months past it | 7 months past it | 381 | 127 | +12.9% |
| Signature Lifestyle Residences | Under construction | 8.1% | Dec 2028 25 months to go | 25 months to go | 187 | 115 | +16.2% |
| Uh East By Ellington | Under construction | 62.8% | Mar 2026 7 months past it | 7 months past it | 381 | 102 | +8.5% |
| Orra The Embankment | Completed | 100% | Jan 2026 | — | 464 | 97 | — |
| Gold Crest VIEWS2 | Completed | 100% | Feb 2010 | — | 492 | 90 | — |
| New Dubai GATE2 | Completed | 100% | Oct 2018 | — | 453 | 85 | — |
| Concorde Tower | Completed | 100% | Apr 2008 | — | 502 | 83 | — |
| Lake View | Completed | 100% | Feb 2009 | — | 546 | 80 | — |
| Lake City Tower | Completed | 100% | Sep 2008 | — | 443 | 77 | — |
| Mbl Residence | Completed | 100% | Mar 2021 | — | 487 | 77 | — |
| Lake Terrace | Completed | 100% | May 2008 | — | 573 | 76 | — |
| Saba Tower 3 | Completed | 100% | Jan 2008 | — | 361 | 73 | — |
| Hilton Residences Dubai Jumeirah Lakes Towers | Under construction | 63% | — | — | 401 | 72 | — |
| Armada Towers | Completed | 100% | Jan 2010 | — | 1,156 | 72 | — |
| Saba Tower 2 | Completed | 100% | Mar 2008 | — | 377 | 69 | — |
| New Dubai GATE1 | Completed | 100% | Mar 2010 | — | 621 | 66 | — |
| Viewz 2 By Danube | Under construction | 65% | Jun 2026 4 months past it | 4 months past it | 564 | 64 | +2% |
| Lake Shore Tower | Completed | 100% | Aug 2009 | — | 418 | 61 | — |
| Viewz 1 By Danube | Under construction | 66.5% | Jun 2026 4 months past it | 4 months past it | 564 | 58 | -0.3% |
| Global Lake View | Completed | 100% | Jan 2010 | — | 342 | 58 | — |
| Me Do Re | Completed | 100% | Jan 2024 | — | 394 | 55 | +6.5% |
| Dubai Arch Tower | Completed | 100% | May 2009 | — | 404 | 54 | — |
| Lakeside Residence | Completed | 100% | Dec 2012 | — | 358 | 46 | — |
| Laguna Tower | Completed | 100% | Aug 2012 | — | 485 | 44 | — |
| Banyan Tree Residences Hillside Dubai | Completed | 100% | May 2020 | — | 236 | 42 | — |
| Gold Crest Executive | Completed | 100% | Sep 2009 | — | 574 | 39 | — |
| The Wind Tower I | Under construction | 74.6% | Jun 2023 40 months past it | 40 months past it | 515 | 38 | — |
| V3 | Completed | 100% | Nov 2009 | — | 331 | 38 | — |
| Palladium | Completed | 100% | Nov 2007 | — | 320 | 36 | — |
| Indigo Tower | Completed | 100% | Feb 2008 | — | 348 | 36 | — |
| Bonnington Tower Hotel & Residence Dubai | Completed | 100% | May 2009 | — | 273 | 34 | — |
| Madina Tower | Completed | 100% | Nov 2007 | — | 205 | 33 | — |
| Dubai Star | Completed | 100% | Dec 2015 | — | 556 | 32 | — |
| Alshera Tower | Completed | 100% | Jan 2008 | — | 253 | 32 | — |
| Al Seef Ii | Completed | 100% | Nov 2008 | — | 229 | 27 | — |
| The Wind Tower Ii | Under construction | 84.5% | Jun 2023 40 months past it | 40 months past it | 411 | 19 | — |
| J&G Plexs | Completed | 100% | Apr 2006 | — | 1,182 | 13 | — |
| The Residences | Completed | 100% | Jul 2019 | — | 82 | 10 | — |
| ME DO RE Business | Under construction | 24.5% | Sep 2029 34 months to go | 34 months to go | 293 | 0 | — |
| Project 459, Al Thanyah Fifth | Conditionally activating | 0% | Dec 2026 1 month to go | 1 month to go | 0 | 0 | — |
| Jumeirah Business Centre 5 | Completed | 100% | Jan 2010 | — | 295 | 0 | — |
| Jumeirah Business Centre2 | Completed | 100% | Jan 2010 | — | 293 | 0 | — |
| Jumeirah Business Centre3 | Completed | 100% | May 2010 | — | 244 | 0 | — |
| Jumeirah Business Centre1 | Completed | 100% | Jan 2011 | — | 336 | 0 | — |
| Reef Tower | Completed | 100% | Feb 2009 | — | 121 | 0 | — |
| Inigo Icon | Completed | 100% | Apr 2009 | — | 246 | 0 | — |
| Swiss Tower | Completed | 100% | Oct 2010 | — | 177 | 0 | — |
| The Dome Tower | Completed | 100% | Feb 2013 | — | 275 | 0 | — |
| Saba Tower 1 | Completed | 100% | Oct 2006 | — | 188 | 0 | — |
| Jumeirah Business Centre 4 | Completed | 100% | May 2010 | — | 248 | 0 | — |
| Platinum Tower | Completed | 100% | Dec 2012 | — | 453 | 0 | — |
| Tiffany Towers | Completed | 100% | Jun 2009 | — | 304 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
17 phases| DLD end year | Projects | Units |
|---|---|---|
| 2023 | 2 | 926 |
| 2025 | 2 | 3,073 |
| 2026 | 5 | 1,890 |
| 2027 | 4 | 2,230 |
| 2028 | 1 | 187 |
| 2029 | 1 | 293 |
| No end date | 2 | 1,626 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on DMCC Master Community
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology