DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers in 2025 222 projects registered to end in 2025 · 145 completed · 62 under construction DLD projects register as of 1 November 2026 · sales to 5 November 2026

222 projects in the Dubai Land Department projects register have an end date in 2025. As of 1 November 2026, 145 are completed, 62 are under construction and 14 have not started. 62 of those under construction are past their DLD end date. These are the DLD end dates registered for each project, not handover forecasts.

Registered to end in 2025
222
projects · 18,225 units not yet completed
Completed
145
marked completed by DLD
Under construction
62
0 with the end date to come
Not started
14
Not yet active on the DLD register
Under construction, past end date
62
of 62 under construction

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end dates by month

222 projects

Columns link to their monthly pages. Source: DLD projects register, export of 1 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Not yet completed (77)77 projects with a 2025 DLD end date, by sales over 24 months

77 projects with a 2025 DLD end date, by sales over 24 months
ProjectArea Built DLD end dateTo DLD end date Units
Azizi GrandAl Hebiah Fourth 82.1% 2 Feb 2025 20 mo past 411
Azizi Riviera ReveAl Merkadh 76.6% 5 Feb 2025 20 mo past 455
Project 3201, Al Barsha South FourthAl Barsha South Fourth 24.7% 28 Feb 2025 — —
South Bay 1Madinat Al Mataar 93.7% 10 Mar 2025 19 mo past 251
Project 3296, Al Thanyah FifthAl Thanyah Fifth 30% 15 Mar 2025 — —
Kiwi Yard ResidencesWarsan Fourth 54.7% 30 Mar 2025 — 78
Living Legends Phase 5Wadi Al Safa 3 48.9% 31 Mar 2025 19 mo past 920
Enaya ResidencesAl Barsha South Fifth 39% 31 Mar 2025 19 mo past 61
Elysian MansionsAl Hebiah Fourth 95% 31 Mar 2025 19 mo past —
7 Park Central By MeteoraAl Barsha South Fourth 90.2% 30 Apr 2025 18 mo past 121
The Heart of Europe 2World Islands 93.4% 30 Apr 2025 18 mo past 1,383
Flamingo Lux ResidenceNad Al Shiba First 47% 5 May 2025 — 53
One CanalAl Wasl 87.7% 30 May 2025 17 mo past 43
Project 3692, Warsan FourthWarsan Fourth 75% 30 May 2025 — —
Cavalli CoutureAl Wasl 19.7% 31 May 2025 17 mo past 95
Vincitore VolareAl Barshaa South Third 63.4% 1 Jun 2025 17 mo past 415
Damac Lagoons - PortofinoAl Hebiah Fifth 97.1% 29 Jun 2025 16 mo past —
Tria By DeyaarNadd Hessa 94.1% 30 Jun 2025 16 mo past 717
Luxury Family Residence IIIBusiness Bay 50.6% 30 Jun 2025 16 mo past 72
Zaya Zuha IslandWorld Islands 81.1% 30 Jun 2025 16 mo past 28
California VillageWadi Al Safa 4 95.1% 15 Jul 2025 15 mo past 212
Project 3333, Al Barsha South FourthAl Barsha South Fourth 41.3% 25 Jul 2025 — —
Damac Lagoons - Nice 1Al Hebiah Fifth 93.7% 29 Jul 2025 15 mo past —
Damac Lagoons - Nice 2Al Hebiah Fifth 83.9% 29 Jul 2025 15 mo past —
Chic TowerBusiness Bay 84% 30 Jul 2025 15 mo past 467
Ocean StarMadinat Dubai Almelaheyah 30.5% 31 Jul 2025 15 mo past 155
Damac Hills (2) - FarmhousesMadinat Hind 4 83% 28 Aug 2025 14 mo past —
Equiti TowerWarsan Fourth 70.2% 30 Aug 2025 14 mo past 88
Sunset Grove HomesAl Barsha South Fourth 27.8% 18 Sep 2025 — 8
Damac Lagoons - Venice (1)Al Hebiah Fifth 74.4% 29 Sep 2025 13 mo past —
Cavalli Casa TowerAl Safouh Second 85.1% 30 Sep 2025 13 mo past 441
The PortmanAl Barsha South Fourth 78.7% 30 Sep 2025 13 mo past 167
Project 3532, Al MerkadhAl Merkadh 0% 30 Sep 2025 — —
Elano By ORO24Al Barshaa South Third 70% 1 Oct 2025 13 mo past 339
The HarmonyMadinat Al Mataar 97.8% 6 Oct 2025 12 mo past 113
Project 3369, Al Barsha South FourthAl Barsha South Fourth 37% 15 Oct 2025 — —
Azizi Venice 5Madinat Al Mataar 63.5% 30 Oct 2025 12 mo past 484
Orbit Residences by Jewel 2Warsan Fourth 80.1% 30 Oct 2025 — 147
API- Barsha Residential TowerAl Barsha First 92.6% 31 Oct 2025 12 mo past 335
The Community Motor CityAl Hebiah First 95.1% 31 Oct 2025 12 mo past 433
Serenity Lakes 2Al Barsha South Fourth 50.5% 5 Nov 2025 11 mo past 268
One By NineNad Al Shiba First 50.3% 8 Nov 2025 11 mo past 46
Seven City JltAl Thanyah Fifth 28.4% 24 Nov 2025 — 2,666
The Stella ResidencesJabal Ali First 71.1% 1 Dec 2025 11 mo past 236
Levanto By ORO24Al Barsha South Fourth 66% 8 Dec 2025 10 mo past 579
Equiti GardenJabal Ali First 87% 13 Dec 2025 10 mo past 133
The RingsJumeirah Second 35.1% 25 Dec 2025 10 mo past 13
Sky Suites by Peace HomesAl Barsha South Fourth 55.5% 25 Dec 2025 10 mo past 239
Azizi Venice 2Madinat Al Mataar 57.2% 30 Dec 2025 10 mo past 526
Azizi Venice 4Madinat Al Mataar 62.2% 30 Dec 2025 10 mo past 389
Damac CityAl Wasl 72.8% 30 Dec 2025 10 mo past 511
Azizi Venice 3Madinat Al Mataar 76% 30 Dec 2025 10 mo past 352
Azizi Venice 1Madinat Al Mataar 67.4% 30 Dec 2025 10 mo past 143
Gardens 2Al Barshaa South Third 68.5% 30 Dec 2025 10 mo past 223
Paradise HillsAl Hebiah Fifth 84.1% 30 Dec 2025 10 mo past 178
Damac Lagoons - IbizaAl Hebiah Fifth 78.9% 31 Dec 2025 10 mo past —
Me Do Re 2Al Thanyah Fifth 97.8% 31 Dec 2025 10 mo past 407
Damac Lagoons - MykonosAl Hebiah Fifth 81.1% 31 Dec 2025 10 mo past —
Ashton Park Residences The SecondAl Barsha South Fourth 70.1% 31 Dec 2025 10 mo past 194
Damac Lagoons - MarbellaAl Hebiah Fifth 87.3% 31 Dec 2025 10 mo past —
Damac Lagoons - Monte CarloAl Hebiah Fifth 86.4% 31 Dec 2025 10 mo past —
Maimoon GardensAl Barsha South Fourth 78% 31 Dec 2025 10 mo past 722
Bugatti Residences by BinghattiBusiness Bay 65.6% 31 Dec 2025 10 mo past 187
Elitz By DanubeAl Barsha South Fourth 91.8% 31 Dec 2025 10 mo past 592
Q Gardens LoftsAl Barsha South Fourth 90.7% 31 Dec 2025 10 mo past 194
Verdana ResidenceDubai Investment Park First 96.1% 31 Dec 2025 10 mo past 224
99 Park PlaceAl Barsha South Fourth 90% 31 Dec 2025 10 mo past 102
The Maiden ResidenceWarsan Fourth 73% 31 Dec 2025 10 mo past 71
Verdana (Phase 1)Dubai Investment Park First 94.6% 31 Dec 2025 10 mo past 178
Verdana(Phase 2)Dubai Investment Park First 94% 31 Dec 2025 10 mo past 127
Trillium HeightsAl Satwa 61.6% 31 Dec 2025 10 mo past 56
DO ResidencesPalm Deira 1.7% 31 Dec 2025 10 mo past 120
Banyan Tree Residences Aurelia DubaiBurj Khalifa 0% 31 Dec 2025 — 33
Project 3267, Wadi Al Safa 2Wadi Al Safa 2 0% 31 Dec 2025 — —
Project 2983, Burj KhalifaBurj Khalifa 48.3% 31 Dec 2025 — —
Amana JewelsWadi Al Safa 2 22% 31 Dec 2025 — 24
Mews MansionsNad Al Shiba First 55.6% 31 Dec 2025 10 mo past —

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Completed145 projects with a 2025 DLD end date, marked completed by DLD

145 projects with a 2025 DLD end date, marked completed by DLD
ProjectAreaDLD end dateCompletedAgainst the end date Units
Mass ResidenceAl Barsha South Fourth 2 Jan 2025 2 Jan 2025 On the end date 69
Amal TowerAl Hebiah Fourth 7 Jan 2025 7 Jan 2025 On the end date 342
The ResidenceWarsan Fourth 7 Jan 2025 31 Jul 2022 29 mo before 67
Jasmine LaneMe'Aisem First 10 Jan 2025 10 Jan 2025 On the end date 138
Mag 22Nad Al Shiba First 15 Jan 2025 15 Jan 2025 On the end date 22
Arabian Ranches lll - CayaWadi Al Safa 5 19 Jan 2025 19 Jan 2025 On the end date —
Hamilton HouseAl Barsha South Fourth 30 Jan 2025 30 Jan 2025 On the end date 102
PEARLZ by DanubeJabal Ali First 31 Jan 2025 31 Jan 2025 On the end date 302
Amalia ResidencesJabal Ali First 31 Jan 2025 17 Nov 2025 9 mo after 98
La Violeta 1Wadi Al Safa 5 1 Feb 2025 1 Feb 2025 On the end date 244
Damac HILLS-PARK Residences 1Al Hebiah Third 12 Feb 2025 12 Feb 2025 On the end date 129
Azizi Riviera 63Al Merkadh 13 Feb 2025 13 Feb 2025 On the end date 122
Park Lane By HeilbronnAl Barsha South Fourth 14 Feb 2025 14 Feb 2025 On the end date 82
Azizi Riviera 59Al Merkadh 14 Feb 2025 14 Feb 2025 On the end date 123
RA1N ResidenceAl Barsha South Fourth 23 Feb 2025 10 Mar 2026 12 mo after 146
Island Park IAl Khairan First 24 Feb 2025 24 Feb 2025 On the end date 160
Island Park IIAl Khairan First 24 Feb 2025 24 Feb 2025 On the end date 160
Symbolic AlphaWadi Al Safa 2 24 Feb 2025 24 Feb 2025 On the end date 97
CLOUD TowerAl Barsha South Fifth 28 Feb 2025 21 Oct 2025 7 mo after 456
Al Serh Residences 11 By Asak Real Estate DevelopmentAl Barsha South Fourth 28 Feb 2025 4 Jun 2026 15 mo after 105
Ellington HouseHadaeq Sheikh Mohammed Bin Rashid 28 Feb 2025 28 Feb 2025 On the end date 150
MAYA Luxury CollectionWadi Al Safa 3 2 Mar 2025 25 Sep 2025 6 mo after 9
Adhara StarAl Barshaa South Third 10 Mar 2025 25 Dec 2025 9 mo after 115
The East Crest By MeteoraAl Barsha South Fourth 13 Mar 2025 21 Nov 2025 8 mo after 121
The 100Nad Al Shiba First 19 Mar 2025 19 Mar 2025 On the end date 91
H Three By AuroraAl Barsha South Fourth 20 Mar 2025 2 Apr 2025 1 wk after 147
Azizi Riviera 67Al Merkadh 27 Mar 2025 27 Mar 2025 On the end date 198
Azizi Riviera 61Al Merkadh 27 Mar 2025 27 Mar 2025 On the end date 240
Azizi Riviera 65Al Merkadh 27 Mar 2025 27 Mar 2025 On the end date 169
Oxford GardensAl Barshaa South Third 30 Mar 2025 24 Sep 2025 5 mo after 240
Joya Dorado ResidenceAl Barshaa South Third 30 Mar 2025 11 Aug 2026 16 mo after 422
Lagoon Views at District OneAl Merkadh 30 Mar 2025 30 Mar 2025 On the end date 104
The Valley - TaliaAl Yufrah 1 31 Mar 2025 31 Mar 2025 On the end date 330
MBL RoyalAl Thanyah Fifth 31 Mar 2025 31 Mar 2025 On the end date 333
ELEVATE by PrescottAl Barshaa South Third 31 Mar 2025 4 Jun 2026 14 mo after 223
Stonehenge ResidencesAl Barsha South Fourth 31 Mar 2025 26 Jan 2026 9 mo after 156
GEMZ by DanubeJabal Ali First 31 Mar 2025 31 Mar 2025 On the end date 279
Alef Noon ResidenceAl Barsha South Fourth 31 Mar 2025 31 Mar 2025 On the end date 113
Floarea ResidenceAl Barshaa South Third 1 Apr 2025 19 Aug 2025 4 mo after 206
Aura EleganceNadd Hessa 1 Apr 2025 10 Feb 2026 10 mo after 109
MyrtleAl Wasl 1 Apr 2025 1 Apr 2025 On the end date 130
Samana SantoriniAl Hebiah Second 1 Apr 2025 22 Feb 2026 10 mo after 157
Opalz By DanubeAl Barshaa South Second 24 Apr 2025 24 Apr 2025 On the end date 575
Lumina Vista ResidencesAl Barsha South Fourth 29 Apr 2025 22 Oct 2024 6 mo before 74
Azizi Mirage 1Al Hebiah Second 30 Apr 2025 16 Oct 2025 5 mo after 762
Azizi VistaAl Hebiah Second 30 Apr 2025 30 Sep 2025 5 mo after 163
The Pulse Beachfront 3Madinat Al Mataar 30 Apr 2025 30 Apr 2025 On the end date 291
Ellington House IiHadaeq Sheikh Mohammed Bin Rashid 30 Apr 2025 15 Mar 2026 10 mo after 166
Manam PrimeMadinat Al Mataar 30 Apr 2025 8 Jul 2025 2 mo after 40
CielMarsa Dubai 30 Apr 2025 9 Oct 2025 5 mo after 1,019
Talia ResidencesJabal Ali First 30 Apr 2025 1 Jun 2026 13 mo after 160
Iliyaa 5Wadi Al Safa 3 30 Apr 2025 20 Oct 2025 5 mo after 100
555 Park ViewsAl Barsha South Fifth 3 May 2025 3 May 2025 On the end date 71
The Paragon By IGOBusiness Bay 13 May 2025 13 May 2025 On the end date 328
Mudon Al Ranim 2Al Hebiah Sixth 28 May 2025 31 Dec 2025 7 mo after 176
Liv MarinaMarsa Dubai 30 May 2025 30 May 2025 On the end date 243
Arista OneAl Satwa 30 May 2025 3 Sep 2025 3 mo after 64
Peninsula ThreeBusiness Bay 1 Jun 2025 3 Dec 2025 6 mo after 859
Jumeirah Living Business BayBusiness Bay 14 Jun 2025 17 Dec 2025 6 mo after 82
Cresswell ResidencesMadinat Al Mataar 26 Jun 2025 20 Apr 2026 9 mo after 72
Damac Hills (2) - CameliaMadinat Hind 4 30 Jun 2025 5 Nov 2025 4 mo after 578
Arabian Ranches lll - JuneWadi Al Safa 5 30 Jun 2025 30 Jun 2025 On the end date 183
Eden House The CanalJumeirah Second 30 Jun 2025 10 Dec 2025 5 mo after 100
Vista by Prestige OneAl Hebiah Fourth 30 Jun 2025 2 Apr 2026 9 mo after 140
Marina LivingMarsa Dubai 30 Jun 2025 14 Jan 2026 6 mo after 205
The S TowerAl Safouh Second 30 Jun 2025 27 Feb 2026 7 mo after 95
Pearl House I by ImtiazAl Barsha South Fourth 9 Jul 2025 9 Jul 2025 On the end date 185
Kempinski Residences The CreekAl Jadaf 10 Jul 2025 8 Dec 2025 4 mo after 283
The HavenWadi Al Safa 3 12 Jul 2025 12 Jul 2025 On the end date 326
Sunrise Living at Jumeirah ParkAl Thanyah Fifth 15 Jul 2025 25 Jun 2026 11 mo after —
Sensoria at Five LuxeMarsa Dubai 26 Jul 2025 8 Oct 2025 2 mo after 54
Damac Lagoons - Santorini (1)Al Hebiah Fifth 29 Jul 2025 29 Jul 2025 On the end date —
Damac Lagoons - Costa Brava (1)Al Hebiah Fifth 29 Jul 2025 10 Apr 2026 8 mo after —
Damac Lagoons - Costa Brava (2)Al Hebiah Fifth 29 Jul 2025 4 Aug 2026 12 mo after —
Damac Lagoons - Santorini (2)Al Hebiah Fifth 29 Jul 2025 11 Feb 2026 6 mo after —
Damac Lagoons - Santorini (3)Al Hebiah Fifth 29 Jul 2025 9 Apr 2026 8 mo after —
Azizi Riviera AzureAl Merkadh 30 Jul 2025 30 Jul 2025 On the end date 124
Sobha Creek Vistas GrandeAl Merkadh 31 Jul 2025 31 Jul 2025 On the end date 400
The RegentAl Yelayiss 2 31 Jul 2025 31 Jul 2025 On the end date 238
Azizi AmberJabal Ali First 31 Jul 2025 31 Jul 2025 On the end date 115
Ellington House IiiHadaeq Sheikh Mohammed Bin Rashid 31 Jul 2025 30 Jul 2026 11 mo after 110
Pearls by VisionNadd Hessa 10 Aug 2025 10 Aug 2025 On the end date 114
MOONSA ResidencesWarsan Fourth 25 Aug 2025 30 Oct 2026 14 mo after 93
4B LivingWarsan Fourth 30 Aug 2025 16 Sep 2026 12 mo after 74
DGM VisionAl Satwa 30 Aug 2025 22 May 2026 8 mo after 95
Maha TownhousesAl Yelayiss 2 31 Aug 2025 31 Aug 2025 On the end date 500
Rise ResidencesAl Barsha South Fourth 31 Aug 2025 6 Jan 2026 4 mo after 174
V1TER ResidenceAl Barsha South Fourth 15 Sep 2025 9 Jul 2026 9 mo after 175
The VybeAl Barsha South Fourth 15 Sep 2025 15 Sep 2025 On the end date 276
The Veranda Collection 1Al Barsha South Fourth 15 Sep 2025 16 Apr 2026 7 mo after 12
Altia OneNadd Hessa 22 Sep 2025 20 Oct 2025 4 wk after 123
Riva ResidenceMadinat Dubai Almelaheyah 25 Sep 2025 26 Dec 2025 3 mo after 155
Damac Lagoons - Malta (1)Al Hebiah Fifth 29 Sep 2025 19 Jun 2026 8 mo after —
Damac Lagoons - Malta (2)Al Hebiah Fifth 29 Sep 2025 8 Apr 2026 6 mo after —
LivaAl Yelayiss 2 30 Sep 2025 30 Sep 2025 On the end date 484
48 ParksideAl Barshaa South Third 30 Sep 2025 11 May 2026 7 mo after 187
Avelon BoulevardAl Barshaa South Third 30 Sep 2025 25 Dec 2025 2 mo after 135
Holland GardensAl Yelayiss 2 30 Sep 2025 17 Nov 2025 1 mo after 228
Creek Beach - LotusAl Khairan First 30 Sep 2025 30 Sep 2025 On the end date 270
Creek Beach - OrchidAl Khairan First 30 Sep 2025 30 Sep 2025 On the end date 208
WAHA LIVING by AL YAKKAAl Satwa 30 Sep 2025 7 Apr 2026 6 mo after 71
SeagateMadinat Dubai Almelaheyah 30 Sep 2025 30 Sep 2025 On the end date 302
Arabian Ranches lll - Elie SaabWadi Al Safa 5 30 Sep 2025 11 Sep 2025 2 wk before —
Fairway VillasMadinat Al Mataar 30 Sep 2025 21 Oct 2025 3 wk after —
Silver Park ResidencyWarsan Fourth 30 Oct 2025 18 Mar 2026 4 mo after 76
Palace Beach ResidenceMarsa Dubai 31 Oct 2025 31 Oct 2025 On the end date 552
The HamiltonAl Yelayiss 2 31 Oct 2025 31 Dec 2025 2 mo after 242
Mudon Al Ranim 1Al Hebiah Sixth 31 Oct 2025 31 Oct 2025 On the end date 224
Greenview 3Madinat Al Mataar 31 Oct 2025 31 Oct 2025 On the end date 241
399 Hills Park BHadaeq Sheikh Mohammed Bin Rashid 31 Oct 2025 3 Aug 2026 9 mo after 199
Glorious Central ResidencesWarsan Fourth 1 Nov 2025 17 Dec 2025 1 mo after 151
Cubix ResidencesAl Barsha South Fourth 1 Nov 2025 12 Mar 2026 4 mo after 72
Luma Park ViewsAl Barsha South Fourth 26 Nov 2025 28 Nov 2025 2 d after 606
Hadley HeightsAl Barsha South Fourth 30 Nov 2025 2 Oct 2025 1 mo before 219
Amethyst By SiroyaWadi Al Safa 3 30 Nov 2025 15 Jul 2026 7 mo after 53
Arabian Ranches lll - Elie Saab llWadi Al Safa 5 30 Nov 2025 15 Sep 2025 2 mo before —
The Residence By Prestige OneAl Barsha South Fourth 30 Nov 2025 27 Mar 2026 3 mo after 98
Olivo Park Residences By EveraAl Barsha South Fourth 15 Dec 2025 28 Apr 2026 4 mo after 122
Park FieldHadaeq Sheikh Mohammed Bin Rashid 15 Dec 2025 15 Dec 2025 On the end date 306
LaurelAl Wasl 21 Dec 2025 31 Jul 2026 7 mo after 218
The Roof ResidenceNad Al Shiba First 25 Dec 2025 5 Feb 2026 1 mo after 68
Haven LivingPalm Deira 26 Dec 2025 28 Apr 2026 4 mo after 51
Azizi Riviera BeachfrontAl Merkadh 30 Dec 2025 31 Dec 2025 1 d after 609
Beach MansionMarsa Dubai 30 Dec 2025 11 Nov 2025 1 mo before 495
Arabian Ranches lll - Bliss 2Wadi Al Safa 5 30 Dec 2025 18 Dec 2025 1 wk before 269
Jebel Ali VillageJabal Ali First 30 Dec 2025 29 Apr 2026 3 mo after —
Sobha Hartland - The CrestAl Merkadh 31 Dec 2025 31 Dec 2025 On the end date 1,518
Binghatti IvoryAl Jadaf 31 Dec 2025 15 Sep 2026 8 mo after 332
Binghatti AuroraAl Barsha South Fourth 31 Dec 2025 15 Oct 2025 2 mo before 275
Neva ResidencesAl Barsha South Fourth 31 Dec 2025 12 Mar 2026 2 mo after 409
Seslia TowerAl Barsha South Fifth 31 Dec 2025 22 Jul 2026 6 mo after 378
Binghatti PinnacleAl Jadaf 31 Dec 2025 30 Jul 2026 6 mo after 178
Viera ResidencesMe'Aisem First 31 Dec 2025 2 Feb 2026 1 mo after 144
The Valley - OraniaAl Yufrah 1 31 Dec 2025 31 Dec 2025 On the end date 308
Serenia LivingPalm Jumeirah 31 Dec 2025 23 Apr 2026 3 mo after 226
Coral by VisionAl Satwa 31 Dec 2025 16 Feb 2026 1 mo after 88
Petalz By DanubeAl Warsan First 31 Dec 2025 29 Oct 2025 2 mo before 354
Exquisite Living ResidencesBurj Khalifa 31 Dec 2025 15 Jul 2026 6 mo after 234
Lucky Royale ResidenceAl Barsha South Fourth 31 Dec 2025 14 Oct 2026 9 mo after 147
Trafford ResidenceMadinat Al Mataar 31 Dec 2025 27 Aug 2026 7 mo after 44
Celeste by WestarAl Barsha South Fourth 31 Dec 2025 3 Dec 2025 4 wk before 15
LucePalm Jumeirah 31 Dec 2025 20 Oct 2026 9 mo after 38
Jebel Ali Village Townhouses- Phase 1Jabal Ali First 31 Dec 2025 29 Apr 2026 3 mo after —
Jebel Ali Village Townhouses - Phase 2Jabal Ali First 31 Dec 2025 29 Apr 2026 3 mo after —
Jebel Ali Village Townhouses - Phase 3Jabal Ali First 31 Dec 2025 29 Apr 2026 3 mo after —

Completed: the completion date DLD records for the project. Source: DLD projects register, export of 1 November 2026.

Months of 2025

Other years: 2024 · 2026

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology