DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2466Completed157 units

Samana Santorini Samana Santorini Al Hebiah Second · Dubai Studio City by Samana International Real Estate Development L.L.CAll phases of Dubai Studio City Completed 22 February 2026 (DLD) DLD end date Apr 2025 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Feb 2026
DLD end date Apr 2025
Build time
35 months
Apr 2023 → Feb 2026
Launch → resale
1,344 AED/sqft
+4.1% on launch Launch 1,246 · 13 sales since completion
1 BR rent
72,000 AED/yr
19 leases, 12 months
Developer
19 projects
5 completed · 888 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 100% built on 19 February 2026 (inspections: 8).
Every DLD inspection and every change in the register %, newest first
Date % built Source
19 February 2026 100% DLD inspection
30 July 2025 95.3% DLD inspection
23 February 2025 84.9% DLD inspection
21 September 2024 59.1% DLD inspection
12 May 2024 10% DLD register, archived export
3 May 2024 41.3% DLD inspection
21 September 2023 10.2% DLD inspection
6 July 2023 2.7% DLD inspection
12 October 2022 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
24 monthsActual build
35 months
Start date
1 April 2023
DLD end date
1 April 2025
Completion date
22 February 2026
Completion vs DLD end date
10 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2466
Escrow agent
Emirates Nbd Bank (P.J.S.C)
Zoning authority
Dubai Development Authority (DDA)
Master project
Dubai Studio City
DLD area
Al Hebiah Second
Units · villas
157 · 0
Start → DLD end
Apr 2023 → Apr 2025
Registered unitsStudio 88 · 1 bed 46 · 2 bed 19 · 3 bed 4; sizes 388–895 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: B+G+4F+R,The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,246 AED/sqft
Median of 100 off-plan sales in the 90 days from the first one (Dec 2022)
Latest registered sales
1,335 AED/sqft
Median of 20 home sales in the last 12 months, ready and off-plan
Change
+8.4%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2022-Q4 to 2026-Q2: +24%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
Studio 1,291 (60) 1,344 (12) +4.1%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 23 1,344 (12) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2022-Q4 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Hebiah Second, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
1,246 AED/sqft
Median of 100 off-plan sales, Dec 2022 – Mar 2023
Resales after completion
1,344 AED/sqft
Median of 13 ready sales, Feb 2026 – Nov 2026
Change
+4.1%
Same home types, weighted by the resales

Over the same span, ready homes in DLD area Al Hebiah Second changed +92.2% (same home types).

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.

Bedrooms Median annual rent New contracts Change on a year earlier Gross yield
Studio AED 45,000 41 — 7.8%
1 BR AED 72,000 19 — —
2 BR AED 100,000 8 — —

Gross yield is before service charges, other costs and empty months.

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 2; the amount shows from 5 registrations.

Since the first registration in 2026-Q3: 2 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Too few of its budgets tell apartment buildings from villas, so both are counted.
18.79 AED/sqft a year
Dubai Studio City: median of 10 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 20 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
29 October 2026readyApartment · Studio 395 500,000 1,266
28 October 2026readyApartment · Studio 387 520,000 1,344
21 September 2026readyApartment · Studio 440 625,000 1,420
26 August 2026readyApartment · Studio 387 570,000 1,473
25 August 2026readyApartment · Studio 457 909,529 1,990
28 July 2026readyApartment · Studio 387 458,480 1,185
22 July 2026readyApartment · Studio 388 580,000 1,495
21 July 2026readyApartment · Studio 512 864,705 1,689
20 July 2026readyApartment · Studio 386 540,000 1,399
7 July 2026readyApartment · Studio 443 585,000 1,321

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Hebiah Second · Dubai Municipality community

Park · 560 mPark · 710 mPark · 730 mDwight School Dubai · 1.3 kmGEMS Metropole School Motor City · 1.4 kmSpinneys · 1.4 kmValue Basket · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationJumeirah Golf Estates Metro Station · Red Metro line · 7.8 km
MallMall · 1.6 km
SupermarketSpinneys · 1.4 km
HospitalMediclinic Springs · 7.5 km
SchoolDwight School Dubai · 1.3 km
ParkPark · 560 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 16, with 3,445 units and villas.

2024: 5542026: 1,6282027: 4202028: 379No end date: 464

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Hebiah Second: 8

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Beach Oasis 2 53.2% Apr 2026 1,549 466
Arisha Terraces 34% Oct 2027 1,588 334
Verano By Prescott 41.1% Dec 2026 1,545 231
Laya Courtyard 50.6% Dec 2026 — 163
Ghaff Land Residence 66.4% Jun 2026 1,246 145
RYAH LIVING by ALYAKKA 54.1% Jul 2026 1,387 92
Samana Mykonos 91.1% Apr 2026 1,560 24
The First Collection at Dubai Studio City 31.9% Jan 2028 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Hebiah Second

Developer in DLD data Samana International Real Estate Development L.L.C · DLD developer no. 1229

Projects registered
19
5 completed · 14 under construction · 0 not started
Units delivered
888
6,610 in the pipeline
Median build time
33 months
completed projects measured: 5
Past the DLD end date
2
of 10 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 5 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Samana International Real Estate Development L.L.C is one of 10 DLD-registered developers we list together as Samana. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai Studio City

DLD lists 17 projects in the master project Dubai Studio City.

Beach Oasis 2Under construction · 53.2% · Apr 2026
Samana MykonosUnder construction · 91.1% · Apr 2026
Ghaff Land ResidenceUnder construction · 66.4% · Jun 2026
RYAH LIVING by ALYAKKAUnder construction · 54.1% · Jul 2026
Laya CourtyardUnder construction · 50.6% · Dec 2026
Verano By PrescottUnder construction · 41.1% · Dec 2026
Arisha TerracesUnder construction · 34% · Oct 2027
The First Collection at Dubai Studio CityUnder construction · 31.9% · Jan 2028
Glitz Residence 2Completed · 100% · Jul 2017
Glitz Residence 1Completed · 100% · Jul 2017
Glitz Residence 3Completed · 100% · Nov 2017
Samana Golf AvenueCompleted · 100% · Feb 2023

Questions about Samana Santorini

When was Samana Santorini completed?

Samana Santorini is recorded as completed on 22 February 2026 (DLD register of 1 November 2026).

Who is the developer of Samana Santorini?

Samana International Real Estate Development L.L.C, as registered with DLD.

What is the DLD project number of Samana Santorini?

2466.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error