Dubai off-plan handovers: November 2025 13 marked completed by DLD · 9 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026
In November 2025, DLD marked 13 projects completed. 9 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Conditionally activating 1 · Under construction 2 · Completed 6. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
2 projects| % completed | Projects |
|---|---|
| 0–25% | 0 |
| 25–50% | 0 |
| 50–75% | 2 |
| 75–100% | 0 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
9 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
Marked completed by DLD in November 2025 (13)
| Project | Area | Developer | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|---|
| Luma Park Views | Al Barsha South Fourth | Townx Real Estate Development L.L.C | 26 Nov 2025 | 28 Nov 2025 | 2 d after | 606 |
| Creek Beach - Canopy - Moor | Al Khairan First | Dubai Creek Harbour L.L.C | 30 Nov 2026 | 7 Nov 2025 | 12 mo before | 444 |
| SKYZ By Danube | Al Barshaa South Third | Danube Properties Development L.L.C | 1 Nov 2024 | 21 Nov 2025 | 12 mo after | 827 |
| Creek Beach - Savanna-Cedar-Mangrove | Al Khairan First | Dubai Creek Harbour L.L.C | 31 Jul 2026 | 7 Nov 2025 | 8 mo before | 595 |
| Damac Hills (2) - Camelia | Madinat Hind 4 | Front Line Investment Management L.L.C | 30 Jun 2025 | 5 Nov 2025 | 4 mo after | 578 |
| Beach Mansion | Marsa Dubai | Emaar Development P.J.S.C. | 30 Dec 2025 | 11 Nov 2025 | 1 mo before | 495 |
| Holland Gardens | Al Yelayiss 2 | Nshama Properties Owned By Nshmi Development One Person Company L.L.C | 30 Sep 2025 | 17 Nov 2025 | 1 mo after | 228 |
| Royal Regency | Business Bay | Alseeb Real Estate Development L.L.C | 28 Feb 2026 | 5 Nov 2025 | 3 mo before | 165 |
| Azizi Riviera 69 | Al Merkadh | Azizi Developments L.L.C | 30 Mar 2026 | 28 Nov 2025 | 4 mo before | 123 |
| The East Crest By Meteora | Al Barsha South Fourth | Meteora Real Estate Development L.L.C | 13 Mar 2025 | 21 Nov 2025 | 8 mo after | 121 |
| Amalia Residences | Jabal Ali First | Deyaar Development (P.J.S.C) | 31 Jan 2025 | 17 Nov 2025 | 9 mo after | 98 |
| Hyde Walk Residence by Imtiaz | Al Satwa | Imtiaz Real Estate Investment & Development L.L.C | — | 18 Nov 2025 | — | 89 |
| barari views | Wadi Al Safa 3 | P C I Real Estate Developers L.L.C | 23 Mar 2024 | 7 Nov 2025 | 19 mo after | 26 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end date in November 2025: DLD status in the register of 1 November 2026 (9) 9 projects, by sales over 24 months
| Project | Area | Developer | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|---|
| Seven City Jlt | Al Thanyah Fifth | Seven Tides Real Estate Development L.L.C | 28.4% | 24 Nov 2025 | — | 2,666 |
| Glorious Central Residences | Warsan Fourth | Glorious Future Real Estate Development L.L.C | — | 1 Nov 2025 | Completed | 151 |
| Hadley Heights | Al Barsha South Fourth | Leos Development L.L.C | — | 30 Nov 2025 | Completed | 219 |
| Amethyst By Siroya | Wadi Al Safa 3 | Siroya Ventures Realty L.L.C | — | 30 Nov 2025 | Completed | 53 |
| Arabian Ranches lll - Elie Saab ll | Wadi Al Safa 5 | Emaar Development P.J.S.C. | — | 30 Nov 2025 | Completed | — |
| Cubix Residences | Al Barsha South Fourth | Qube Development L.L.C | — | 1 Nov 2025 | Completed | 72 |
| The Residence By Prestige One | Al Barsha South Fourth | Prestige One Luxury Real Estate L.L.C | — | 30 Nov 2025 | Completed | 98 |
| One By Nine | Nad Al Shiba First | Nine Asset Developments L.L.C | 50.3% | 8 Nov 2025 | 11 mo past | 46 |
| Serenity Lakes 2 | Al Barsha South Fourth | Gulf Land Property Developers L.L.C | 50.5% | 5 Nov 2025 | 11 mo past | 268 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology