Dubai off-plan handovers: January 2026 12 marked completed by DLD · 14 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026
In January 2026, DLD marked 12 projects completed. 14 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 8 · Completed 6. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
8 projects| % completed | Projects |
|---|---|
| 0–25% | 0 |
| 25–50% | 2 |
| 50–75% | 2 |
| 75–100% | 4 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
14 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
Marked completed by DLD in January 2026 (12)
| Project | Area | Developer | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|---|
| Condor Golf Links 18 | Al Hebiah Fourth | Condor Golf Links 18 Real Estate Development L.L.C | 30 Jun 2026 | 19 Jan 2026 | 5 mo before | 256 |
| Equiti Home | Jabal Ali First | B N H Real Estate Developer | — | 8 Jan 2026 | — | 302 |
| Celine By Vision | Wadi Al Safa 2 | Clear Vision Real Estate Development L.L.C | 1 Feb 2026 | 22 Jan 2026 | 1 wk before | 104 |
| Orra The Embankment | Al Thanyah Fifth | Orra Real Estate Development L.L.C | 1 Aug 2023 | 29 Jan 2026 | 29 mo after | 464 |
| Stonehenge Residences | Al Barsha South Fourth | Segrex Development L.L.C | 31 Mar 2025 | 26 Jan 2026 | 9 mo after | 156 |
| Mudon Al Ranim 4 | Al Hebiah Sixth | Mdn Real Estate L.L.C | 31 May 2026 | 19 Jan 2026 | 4 mo before | 134 |
| Port De La Mer - Le Soleil | Jumeirah First | Pdlm Residential L.L.C | 8 Dec 2024 | 9 Jan 2026 | 13 mo after | 184 |
| Golf Grand | Hadaeq Sheikh Mohammed Bin Rashid | Dubai Hills Estate L.L.C | 31 Mar 2027 | 23 Jan 2026 | 14 mo before | 329 |
| Rise Residences | Al Barsha South Fourth | S And S Real Estate Development L.L.C | 31 Aug 2025 | 6 Jan 2026 | 4 mo after | 174 |
| Marina Living | Marsa Dubai | Continental Investments Lmd L.L.C | 30 Jun 2025 | 14 Jan 2026 | 6 mo after | 205 |
| Le Parc Homes | Al Barsha South Fourth | Kbw Real Estate Development L.L.C | — | 21 Jan 2026 | — | 10 |
| Azizi Riviera 55 | Al Merkadh | Azizi Developments L.L.C | 13 Mar 2027 | 21 Jan 2026 | 13 mo before | 124 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end date in January 2026: DLD status in the register of 1 November 2026 (14) 14 projects, by sales over 24 months
| Project | Area | Developer | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|---|
| Azizi Venice 7 | Madinat Al Mataar | Azizi Developments L.L.C | 29.2% | 28 Jan 2026 | 9 mo past | 2,276 |
| FH Residency | Al Barsha South Fifth | Forum Real Estate Development L.L.C | — | 30 Jan 2026 | Completed | 297 |
| Koro One | Al Satwa | Koro Real Estate Development L.L.C | — | 31 Jan 2026 | Completed | 147 |
| Mag 777 | Al Hebiah Fourth | Dng Property Development L.L.C | 67.4% | 15 Jan 2026 | 9 mo past | 266 |
| Mudon Al Ranim 3 | Al Hebiah Sixth | Mdn Real Estate L.L.C | — | 31 Jan 2026 | Completed | 242 |
| Lamaa | Um Suqaim Third | Jumeirah Hills Development L.L.C | — | 27 Jan 2026 | Completed | 372 |
| Trussardi Residences | Jabal Ali First | M I R A Developments L.L.C | 36.2% | 31 Jan 2026 | 9 mo past | 142 |
| Altai Tower | Al Barsha South Fifth | Tiger Properties | — | 31 Jan 2026 | Completed | 240 |
| Expo City Mangrove Residences | Madinat Al Mataar | Expo City Mangrove Residences Development FZCO | 91.2% | 31 Jan 2026 | 9 mo past | 470 |
| The Grandala | Al Satwa | Palladium Prime Real Estate Development L.L.C | 90.7% | 31 Jan 2026 | 9 mo past | 86 |
| Aria By Beyond | Madinat Dubai Almelaheyah | Blue Star Real Estate Development L.L.C | 84.9% | 31 Jan 2026 | 9 mo past | 192 |
| Expo City Valley | Madinat Al Mataar | Expo City Valley Development FZCO | 66% | 31 Jan 2026 | 9 mo past | 528 |
| Volante 2 | Business Bay | Volante Real Estate L.L.C | — | 2 Jan 2026 | Completed | 52 |
| Biltmore Sufouh | Al Safouh First | G J R E Real Estate L.L.C | 87.6% | 29 Jan 2026 | 9 mo past | 477 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology