DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: January 2026 12 marked completed by DLD · 14 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026

In January 2026, DLD marked 12 projects completed. 14 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 8 · Completed 6. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

8 projects
0–25%: 025–50%: 250–75%: 275–100%: 4

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

14 projects
Under construction8
Completed before January 20266

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

Marked completed by DLD in January 2026 (12)

Marked completed by DLD in January 2026 (12)
ProjectArea Developer DLD end dateCompletedAgainst the end date Units
Condor Golf Links 18Al Hebiah FourthCondor Golf Links 18 Real Estate Development L.L.C 30 Jun 2026 19 Jan 2026 5 mo before 256
Equiti HomeJabal Ali FirstB N H Real Estate Developer — 8 Jan 2026 — 302
Celine By VisionWadi Al Safa 2Clear Vision Real Estate Development L.L.C 1 Feb 2026 22 Jan 2026 1 wk before 104
Orra The EmbankmentAl Thanyah FifthOrra Real Estate Development L.L.C 1 Aug 2023 29 Jan 2026 29 mo after 464
Stonehenge ResidencesAl Barsha South FourthSegrex Development L.L.C 31 Mar 2025 26 Jan 2026 9 mo after 156
Mudon Al Ranim 4Al Hebiah SixthMdn Real Estate L.L.C 31 May 2026 19 Jan 2026 4 mo before 134
Port De La Mer - Le SoleilJumeirah FirstPdlm Residential L.L.C 8 Dec 2024 9 Jan 2026 13 mo after 184
Golf GrandHadaeq Sheikh Mohammed Bin RashidDubai Hills Estate L.L.C 31 Mar 2027 23 Jan 2026 14 mo before 329
Rise ResidencesAl Barsha South FourthS And S Real Estate Development L.L.C 31 Aug 2025 6 Jan 2026 4 mo after 174
Marina LivingMarsa DubaiContinental Investments Lmd L.L.C 30 Jun 2025 14 Jan 2026 6 mo after 205
Le Parc HomesAl Barsha South FourthKbw Real Estate Development L.L.C — 21 Jan 2026 — 10
Azizi Riviera 55Al MerkadhAzizi Developments L.L.C 13 Mar 2027 21 Jan 2026 13 mo before 124

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end date in January 2026: DLD status in the register of 1 November 2026 (14) 14 projects, by sales over 24 months

DLD end date in January 2026: DLD status in the register of 1 November 2026 (14)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Azizi Venice 7Madinat Al MataarAzizi Developments L.L.C 29.2% 28 Jan 2026 9 mo past 2,276
FH ResidencyAl Barsha South FifthForum Real Estate Development L.L.C — 30 Jan 2026 Completed 297
Koro OneAl SatwaKoro Real Estate Development L.L.C — 31 Jan 2026 Completed 147
Mag 777Al Hebiah FourthDng Property Development L.L.C 67.4% 15 Jan 2026 9 mo past 266
Mudon Al Ranim 3Al Hebiah SixthMdn Real Estate L.L.C — 31 Jan 2026 Completed 242
LamaaUm Suqaim ThirdJumeirah Hills Development L.L.C — 27 Jan 2026 Completed 372
Trussardi ResidencesJabal Ali FirstM I R A Developments L.L.C 36.2% 31 Jan 2026 9 mo past 142
Altai TowerAl Barsha South FifthTiger Properties — 31 Jan 2026 Completed 240
Expo City Mangrove ResidencesMadinat Al MataarExpo City Mangrove Residences Development FZCO 91.2% 31 Jan 2026 9 mo past 470
The GrandalaAl SatwaPalladium Prime Real Estate Development L.L.C 90.7% 31 Jan 2026 9 mo past 86
Aria By BeyondMadinat Dubai AlmelaheyahBlue Star Real Estate Development L.L.C 84.9% 31 Jan 2026 9 mo past 192
Expo City ValleyMadinat Al MataarExpo City Valley Development FZCO 66% 31 Jan 2026 9 mo past 528
Volante 2Business BayVolante Real Estate L.L.C — 2 Jan 2026 Completed 52
Biltmore SufouhAl Safouh FirstG J R E Real Estate L.L.C 87.6% 29 Jan 2026 9 mo past 477

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology