Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: May 2026 10 marked completed by DLD · 14 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026

In May 2026, DLD marked 10 projects completed. 14 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 11 · Completed 3. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

11 projects
0–25%: 025–50%: 250–75%: 375–100%: 6

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

14 projects
Under construction11
Completed before May 20263

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

Marked completed by DLD in May 2026 (10)

Marked completed by DLD in May 2026 (10)
ProjectArea Developer DLD end dateCompletedAgainst the end date Units
Mag 330Wadi Al Safa 4Mag Property Development L.L.C 1 Feb 2026 14 May 2026 3 mo after 654
The Cove llAl Khairan FirstThe Lagoons Phase One L.L.C 31 Dec 2026 6 May 2026 7 mo before 806
48 ParksideAl Barshaa South ThirdTabeer Real Estate Development L.L.C 30 Sep 2025 11 May 2026 7 mo after 187
Parkside ViewsHadaeq Sheikh Mohammed Bin RashidDubai Hills Estate L.L.C — 8 May 2026 — 389
Golf Vista HeightsAl Hebiah FourthLondon Gate Real Estate Development L.L.C — 13 May 2026 — 209
DGM VisionAl SatwaD G M Vision House Real Estate Development L.L.C 30 Aug 2025 22 May 2026 8 mo after 95
The Spark by EsnaadWadi Al Safa 3Esnaad Real Estate Development L.L.C — 12 May 2026 — 50
ZaZEN IvyJabal Ali FirstZazen Property Development L.L.C 1 Feb 2026 11 May 2026 3 mo after 73
Damac Hills - Cavalli EstatesAl Hebiah ThirdDamac Crescent Properties 31 Dec 2024 13 May 2026 16 mo after —
Beach Walk Residences 1Palm DeiraImtiaz Real Estate Investment & Development L.L.C 1 Jun 2026 19 May 2026 1 wk before 76

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end date in May 2026: DLD status in the register of 1 November 2026 (14) 14 projects, by sales over 24 months

DLD end date in May 2026: DLD status in the register of 1 November 2026 (14)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Azizi Venice 14Madinat Al MataarAzizi Developments L.L.C 30.3% 30 May 2026 5 mo past 3,438
One by BinghattiBusiness BayBinghatti Developers FZE 50.2% 30 May 2026 5 mo past 755
WAREF residences by sido developmentAl Barsha South FourthSido Development L.L.C 81.1% 1 May 2026 6 mo past 228
08 Life ResidencesWarsan FourthDeniz Properties L.L.C 64.9% 31 May 2026 5 mo past 107
Mudon Al Ranim 4Al Hebiah SixthMdn Real Estate L.L.C — 31 May 2026 Completed 134
Alma GardensWadi Al Safa 2Alma Real Estate Developments L.L.C 50.3% 15 May 2026 5 mo past 80
Volna By KascoAl JadafKasco Real Estate Development L.L.C — 31 May 2026 Completed 71
Terrazzo ResidencesAl Barsha South FourthTaraf Development L.L.C 95.2% 20 May 2026 5 mo past 211
South Bay 2Madinat Al MataarDubai South Properties DWC LLC 93.8% 30 May 2026 5 mo past 145
Cavara 42Al Barshaa South ThirdCavara Real Estate Development L.L.C 75.8% 2 May 2026 5 mo past 49
Celia gardensNad Al Shiba FirstAbou Eid Real Estate Development L.L.C — 15 May 2026 Completed 44
Estrella By NexusWadi Al Safa 3Nexus Capital Real Estate Developement L.L.C 45.5% 31 May 2026 5 mo past 60
Signature MansionsMe'Aisem FirstSignature Jge Real Estate Development L.L.C 86.9% 25 May 2026 5 mo past 18
Babette Sapphire ResidenceAl JadafBabette Realty Development L.L.C 78.4% 15 May 2026 5 mo past 66

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology