Dubai off-plan handovers: August 2026 16 marked completed by DLD · 19 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026
In August 2026, DLD marked 16 projects completed. 19 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 13 · Completed 6. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
13 projects| % completed | Projects |
|---|---|
| 0–25% | 3 |
| 25–50% | 4 |
| 50–75% | 4 |
| 75–100% | 2 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
19 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
Marked completed by DLD in August 2026 (16)
| Project | Area | Developer | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|---|
| The EDGE | Business Bay | Select Global Development L.L.C | 11 Oct 2026 | 27 Aug 2026 | 1 mo before | 1,030 |
| Damac Lagoons - Costa Brava (2) | Al Hebiah Fifth | Island Oasis Properties | 29 Jul 2025 | 4 Aug 2026 | 12 mo after | — |
| The Mayfair | Al Yelayiss 2 | Nshama Properties Owned By Nshmi Development One Person Company L.L.C | — | 12 Aug 2026 | — | 242 |
| Joya Dorado Residence | Al Barshaa South Third | Green Yard Propertes Development L.L.C | 30 Mar 2025 | 11 Aug 2026 | 16 mo after | 422 |
| Sobha Hartland Waves Opulence | Al Merkadh | Sobha L.L.C | 30 Sep 2026 | 6 Aug 2026 | 1 mo before | 363 |
| Castleton | Al Wasl | Citywalk Residential 1 L.L.C | — | 5 Aug 2026 | — | 214 |
| Avant Garde Residences By Skyline | Al Barsha South Fourth | Skyline Builders Real Estate L.L.C | — | 25 Aug 2026 | — | 174 |
| Arabian Ranches lll - May | Wadi Al Safa 5 | Emaar Development P.J.S.C. | 30 Sep 2027 | 11 Aug 2026 | 13 mo before | 298 |
| 399 Hills Park B | Hadaeq Sheikh Mohammed Bin Rashid | National Properties Owned By National Bonds Corporation Sole Proprietorship PSC Sole Proprietorship L.L.C | 31 Oct 2025 | 3 Aug 2026 | 9 mo after | 199 |
| Trafford Residence | Madinat Al Mataar | Deviate For Real Estate Development L.L.C | 31 Dec 2025 | 27 Aug 2026 | 7 mo after | 44 |
| Beach Walk Residences 2 | Palm Deira | Imtiaz Ghd Real Estate Development L.L.C | 10 Aug 2026 | 10 Aug 2026 | On the end date | 63 |
| Vida Residences Dubai Hills Estate | Hadaeq Sheikh Mohammed Bin Rashid | Dubai Hills Estate L.L.C | 30 Nov 2027 | 31 Aug 2026 | 14 mo before | 217 |
| Belmont Residences | Al Barsha South Fifth | Ellington Properties Development L.L.C | — | 24 Aug 2026 | — | 69 |
| Thyme | Al Wasl | Citywalk Residential 1 L.L.C | — | 31 Aug 2026 | — | 148 |
| Azizi riviera 58 | Al Merkadh | Azizi Developments L.L.C | 30 May 2027 | 18 Aug 2026 | 9 mo before | 90 |
| The Veranda Collection 2 | Al Barsha South Fourth | Pacifique Global Properties L.L.C | 7 Apr 2026 | 4 Aug 2026 | 3 mo after | 13 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end date in August 2026: DLD status in the register of 1 November 2026 (19) 19 projects, by sales over 24 months
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology