Dubai off-plan handovers: July 2027 16 projects · 15 not yet completed · 3,851 units DLD projects register as of 1 November 2026 · sales to 5 November 2026
July 2027 has not started yet. 16 projects in the Dubai Land Department projects register have their DLD end date in July 2027 (register of 1 November 2026). DLD can change an end date before it comes. By DLD status: Under construction 13 · Not started 2 · Completed 1. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
13 projects| % completed | Projects |
|---|---|
| 0–25% | 8 |
| 25–50% | 5 |
| 50–75% | 0 |
| 75–100% | 0 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
16 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
DLD end date in July 2027 (16) 16 projects, by sales over 24 months
| Project | Area | Developer | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|---|
| Binghatti Flare 01 | Al Barsha South Fifth | Binghatti Developers FZE | 20% | 14 Jul 2027 | 8 mo to go | 845 |
| Gharbi Ii Residences | Al Barsha South Fourth | Rabdan Real Estate Development L.L.C | 14.5% | 20 Jul 2027 | 8 mo to go | 236 |
| Binghatti Luxuria | Al Barsha South Fifth | Binghatti Developers FZE | 7% | 30 Jul 2027 | 8 mo to go | 469 |
| Allura Residences by Citi Developers | Al Barsha South Fourth | Citi Developers Real Estate Development L.L.C | 7.8% | 27 Jul 2027 | 8 mo to go | 264 |
| Mercer House | Al Thanyah Fifth | Eln Properties Development L.L.C | 18.1% | 31 Jul 2027 | 8 mo to go | 610 |
| Trussardi Residences 2 | Jabal Ali First | M I R A Developments L.L.C | 4.6% | 3 Jul 2027 | 8 mo to go | 389 |
| Oasis Residences | Madinat Al Mataar | Al Helal Al Zahaby Real Estate Development L.L.C | 35.3% | 1 Jul 2027 | 8 mo to go | 159 |
| Park Boulevard By Meteora | Al Barsha South Fourth | Meteora Real Estate Development L.L.C | 30% | 31 Jul 2027 | 8 mo to go | 143 |
| Timber Terrace | Madinat Al Mataar | Timber Terrace Development L.L.C | 0% | 31 Jul 2027 | 8 mo to go | 77 |
| Valore | Al Barsha South Fourth | Srg Real Estate Developer L.L.C | 20.9% | 15 Jul 2027 | 8 mo to go | 172 |
| Aero 1 | Madinat Al Mataar | Bithaus Real Estate Development L.L.C | 35.6% | 15 Jul 2027 | 8 mo to go | 48 |
| Bottega Nove by Lalav | Wadi Al Safa 3 | Bottega Nove By Lalav Real Estate Development L.L.C | 30% | 30 Jul 2027 | 8 mo to go | 60 |
| The Palm Crown | Palm Jumeirah | The Pointe L.L.C | 11% | 15 Jul 2027 | 8 mo to go | — |
| Azizi Neila | Jabal Ali First | Azizi Developments L.L.C | 38.5% | 30 Jul 2027 | 8 mo to go | 274 |
| Aura Central | Al Barshaa South Third | Aura Infinite Real Estate Development L.L.C | — | 14 Jul 2027 | Completed | 38 |
| Elevia Residences III | Warsan Fourth | Valores Wbay Property Development L.L.C | 0% | 31 Jul 2027 | 8 mo to go | 105 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Marked completed by DLD in July 2027 (0)
DLD marked no project completed in July 2027.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology