DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2954Under construction

The Palm Crown ذا بالم كراون Palm Jumeirah by The Pointe L.L.CAll phases of Palm Jumeirah 11% built (DLD register as of 1 November 2026) DLD end date Jul 2027 8 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

Palm Jumeirah fronds and Atlantis The Royal from the air
Area photo: Palm Jumeirah, not this project
% built
11%
DLD register, 1 November 2026
Period elapsed
77%
Jul 2024 → Jul 2027
Latest sales
—
Fewer than 5 recent sales
Developer
1 project
0 completed · 0 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built and period elapsed

28 October 2026
Built
11%Elapsed
77%

Two separate measures: one is DLD's % built, the other is time on the calendar.

Latest DLD register reading: 11% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 11% built on 21 July 2026 (inspections: 2).
Every DLD inspection and every change in the register %, newest first
Date % built Source
21 July 2026 11% DLD inspection
2 February 2024 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.

Our completion calculation

Recent pace
0.4 pt/month
0% on 2 February 2024 → 11% on 21 July 2026
At the register date
12.3%
1 November 2026

Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.

Site timeline

± 6 months
Works startedJan 2025 ± 6 months
Structure risingNot seen yet
Topped outNot seen yet
FinishedNot seen yet

Each date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 18 April 2022 to 7 June 2026; method imagery-v1.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
2954
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Trakhees
Master project
Palm Jumeirah
DLD area
Palm Jumeirah
Units · villas
0 · 0
Start → DLD end
Jul 2024 → Jul 2027
Registered units5+ bed 38; sizes 7,745–7,745 sqft

Homes: villas 38.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Development of 38 luxury villa, demolishing of existing buildings and infrastructure works within the development boundary

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Rents in DLD area Palm Jumeirah

New Ejari rent contracts for apartments across DLD area Palm Jumeirah, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 90,000 185 -5.3%
1 BR AED 150,000 663 0%
2 BR AED 210,000 912 -5.5%
3 BR AED 300,000 433 -3.2%
4 BR AED 650,000 49 -3%
5 BR AED 650,000 17 0%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
25.11 AED/sqft a year
Palm Jumeirah: median of 26 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Looking for a unit in this or similar projects?

Tell us what you are looking for in The Palm Crown or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).

Automated estimate, not a valuation

Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Resale asking prices against the original price

Fewer than 5 resale offers with an original price are tracked for this project.

Across all Dubai off-plan resale offers we track: -3.9% (1,105 offers).

Median asking premium by share of the price already paid (number of offers); shown from 5 offers
Paid to the developer This project All Dubai
0–30% paid—0% (9)
30–50% paid—-5% (51)
50–70% paid—-1.5% (65)
70% paid or more—-3.5% (45)

Asking prices of off-plan resale offers we track, compared with each offer's original price, with the 4% DLD fee removed on both sides. A negative value means asking below the original price. Only aggregates of at least 5 offers are shown; no individual offer, seller or agent is.

Thinking of selling your unit?

Thinking of reselling your unit in The Palm Crown? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jul 2027); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Jul 2027
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in The Palm Crown? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationNakhlat Jumeira · Dubai Municipality community

Union Coop · 120 mJuiced · 150 mBeach · 200 mBeach · 300 mPark · 740 mPark · 750 mPark · 910 mAtlantis Mall · 930 mApproximate project location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Approximate project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationNakheel Metro Station · Red Metro line · 5.3 km
MallAtlantis Mall · 930 m
SupermarketUnion Coop · 120 m
HospitalWelcare Hospital · 4.6 km
ParkPark · 740 m
BeachBeach · 200 m

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 2, with 110 units and villas.

2026: 90No end date: 20

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Nakhlat Jumeira: 20

Open projects in the same DLD area with a DLD end year from 2026 to 2028, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
The Alba Residences by Omniyat 8.4% Mar 2028 9,123 55
Palm Beach Towers - 2 81.6% Dec 2026 3,287 53
Palm Beach Towers -3 74.3% Dec 2026 3,364 45
Palm Beach Towers -1 82.8% Dec 2026 3,295 43
Olaia Residences 14.3% Dec 2027 4,028 36
Como Residences 24.8% Mar 2027 5,624 25
Vitalia by Pinnacle 12.3% Jun 2026 — 22
Orla By Omniyat 70% Dec 2026 7,001 15
Ava At Palm Jumeirah By Omniyat 95.9% Jun 2026 — 6
Armani Beach Residences At Palm Jumeirah 10.2% Dec 2027 — 6
Sls Residences At Palm Jumeirah 60% Jul 2026 — 2
One Crescent 80.1% Mar 2026 — 1

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Nakhlat Jumeira

Developer in DLD data The Pointe L.L.C · DLD developer no. 1830

Projects registered
1
0 completed · 1 under construction · 0 not started
Units delivered
0
0 in the pipeline
Past the DLD end date
0
of 1 under construction with a DLD end date

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Palm Jumeirah

DLD lists 58 projects in the master project Palm Jumeirah.

One CrescentUnder construction · 80.1% · Mar 2026
Ava At Palm Jumeirah By OmniyatUnder construction · 95.9% · Jun 2026
Vitalia by PinnacleUnder construction · 12.3% · Jun 2026
Sls Residences At Palm JumeirahUnder construction · 60% · Jul 2026
Palm Beach Towers -1Under construction · 82.8% · Dec 2026
Palm Beach Towers -3Under construction · 74.3% · Dec 2026
Orla By OmniyatUnder construction · 70% · Dec 2026
Palm Beach Towers - 2Under construction · 81.6% · Dec 2026
Como ResidencesUnder construction · 24.8% · Mar 2027
Olaia ResidencesUnder construction · 14.3% · Dec 2027
Armani Beach Residences At Palm JumeirahUnder construction · 10.2% · Dec 2027
Maison Margiela ResidencesUnder construction · 6.4% · Mar 2028

Questions about The Palm Crown

When is The Palm Crown's handover?

DLD lists an end date of Jul 2027 (register of 1 November 2026); the SPA sets the handover terms.

Is The Palm Crown past its DLD end date?

No. Its DLD end date is Jul 2027, 8 months after the register of 1 November 2026.

How far along is The Palm Crown?

11% built in the DLD register of 1 November 2026.

Who is the developer of The Palm Crown?

The Pointe L.L.C, as registered with DLD.

What is the DLD project number of The Palm Crown?

2954.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error