DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: September 2027 35 projects · 34 not yet completed · 8,082 units DLD projects register as of 1 November 2026 · sales to 5 November 2026

September 2027 has not started yet. 35 projects in the Dubai Land Department projects register have their DLD end date in September 2027 (register of 1 November 2026). DLD can change an end date before it comes. By DLD status: Under construction 29 · Not started 3 · Pending 2 · Completed 1. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

29 projects
0–25%: 1825–50%: 850–75%: 275–100%: 1

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

35 projects
Under construction29
Not started3
Pending2
Completed before September 20271

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

DLD end date in September 2027 (35) 35 projects, by sales over 24 months

DLD end date in September 2027 (35)
ProjectArea Developer Built DLD end dateTo DLD end date Units
azizi venice 13Madinat Al MataarAzizi Developments L.L.C 45.9% 16 Sep 2027 10 mo to go 1,888
azizi venice 12Madinat Al MataarAzizi Developments L.L.C 21.6% 25 Sep 2027 10 mo to go 1,428
Kensington GardensWadi Al Safa 5Leos Development L.L.C 0% 27 Sep 2027 10 mo to go 361
Vista by VisionMe'Aisem FirstClear Vision Real Estate Development L.L.C 12.2% 1 Sep 2027 10 mo to go 328
Cove Edition Residence 6 By ImtiazWadi Al Safa 5Imtiaz Cove Real Estate Development L.L.C 25.9% 10 Sep 2027 10 mo to go 264
Sola ResidencesJabal Ali FirstSola Residences Real Estate Development L.L.C 23.6% 15 Sep 2027 10 mo to go 260
Verde By VisionAl Hebiah FourthClear Vision Real Estate Development L.L.C 12% 30 Sep 2027 10 mo to go 253
MAK I'Sola BellaAl Barsha South FourthMak Developers L.L.C 27.2% 5 Sep 2027 10 mo to go 207
The BaltimoreAl Yelayiss 2Nshama Properties Owned By Nshmi Development One Person Company L.L.C 26.3% 30 Sep 2027 10 mo to go 167
Lume ResidencesAl Barsha South FourthS And S Real Estate Development L.L.C 21.7% 30 Sep 2027 10 mo to go 182
LexingtonAl Yelayiss 2Nshama Properties Owned By Nshmi Development One Person Company L.L.C 4.5% 30 Sep 2027 10 mo to go 142
Wynwood Residences By ImtiazPalm DeiraImtiaz Gi Real Estate Development L.L.C 26.3% 30 Sep 2027 10 mo to go 146
Weybridge Gardens 5Wadi Al Safa 5Leos Development L.L.C 0% 15 Sep 2027 10 mo to go 168
Provenza ResidencesAl Barsha South FourthI K R Real Estate Development L.L.C 20.3% 30 Sep 2027 10 mo to go 188
OCTA ISLE Interiors by MISSONIPalm DeiraOcta Di Development CO. L.L.C 6.2% 30 Sep 2027 10 mo to go 112
Creek WatersAl Khairan FirstThe Lagoons Phase One L.L.C 81.1% 30 Sep 2027 10 mo to go 453
Elle ResidencesPalm DeiraAnax Developments L.L.C 0% 1 Sep 2027 10 mo to go 98
Azha Millennium ResidencesAl Barsha South FifthAzha J V T Residences L.L.C 30.1% 1 Sep 2027 10 mo to go 200
Celeste Heights by Zimaya PropertiesJabal Ali FirstZimaya Properties L.L.C 41.2% 30 Sep 2027 10 mo to go 71
Nuvana by WadanPalm DeiraWadan Real Estate Development L.L.C 24.9% 1 Sep 2027 10 mo to go 57
Arabian Ranches lll - MayWadi Al Safa 5Emaar Development P.J.S.C. — 30 Sep 2027 Completed 298
Flora Shore by Calgary PropertiesPalm DeiraCalgary Properties L.L.C 2.2% 30 Sep 2027 10 mo to go 76
Tetris TowerAl Barsha South FourthLe Luminous Real Estate Development L.L.C 8.1% 30 Sep 2027 10 mo to go 205
Naya at District OneAl MerkadhDistrict One - FZ 68.5% 30 Sep 2027 10 mo to go 456
La Vue ParcNad Al Shiba FirstMaaia Prime Real Estate Developers L.L.C 15.4% 15 Sep 2027 10 mo to go 46
Sunlight HomesWarsan FourthSunn And Sand Developers 22.1% 30 Sep 2027 10 mo to go 30
Saddlewood ParkNad Al Shiba FirstMak Developers L.L.C 12.5% 30 Sep 2027 10 mo to go 62
Sea View Residence By Sama MayasPalm DeiraSama Mayas Real Estate Development L.L.C 12.7% 30 Sep 2027 10 mo to go 63
Casa Aura ResidenceMadinat Al MataarA G N Skyline Real Estate Developments L.L.C 6.3% 12 Sep 2027 10 mo to go 58
Courtyard OneMadinat Al MataarGolden Light Real Estate Developments L.L.C 8.2% 1 Sep 2027 10 mo to go 47
VIVIDA ResidencesMadinat Al MataarN A M O Real Estate Development L.L.C 0.8% 30 Sep 2027 10 mo to go 66
Palm Jebel Ali - Frond PPalm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) 34.7% 29 Sep 2027 10 mo to go —
Palm Jebel Ali - Frond OPalm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) 55.7% 29 Sep 2027 10 mo to go —
Project 3863, Wadi Al Safa 3Wadi Al Safa 3Noor Primo Real Estate Development L.L.C 0% 30 Sep 2027 10 mo to go —
Project 3865, Saih Shuaib 1Saih Shuaib 1Ab Developers L.L.C 0% 30 Sep 2027 10 mo to go —

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Marked completed by DLD in September 2027 (0)

DLD marked no project completed in September 2027.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology