DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: January 2027 15 projects · 15 not yet completed · 2,847 units DLD projects register as of 1 November 2026 · sales to 5 November 2026

January 2027 has not started yet. 15 projects in the Dubai Land Department projects register have their DLD end date in January 2027 (register of 1 November 2026). DLD can change an end date before it comes. By DLD status: Under construction 14 · Not started 1. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

14 projects
0–25%: 225–50%: 950–75%: 375–100%: 0

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

15 projects
Under construction14
Not started1

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

DLD end date in January 2027 (15) 15 projects, by sales over 24 months

DLD end date in January 2027 (15)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Cove Edition Residence 4 By ImtiazWadi Al Safa 5Imtiaz Real Estate Investment & Development L.L.C 30.2% 21 Jan 2027 2 mo to go 260
Edgewater Residences 3Palm DeiraM G S Development L.L.C 30.4% 31 Jan 2027 2 mo to go 328
Damac BayMarsa DubaiDamac J R Two Investment L.L.C 33.8% 15 Jan 2027 2 mo to go 1,087
Cotier House 1 By ImtiazPalm DeiraImtiaz Ghd Real Estate Development L.L.C 43.5% 15 Jan 2027 2 mo to go 137
The Hub Residences by ZaZENJabal Ali FirstZazen Property Development L.L.C 34% 15 Jan 2027 2 mo to go 105
MR.C Residences DowntownAl WaslAlta Real Estate Development L.L.C 73.2% 27 Jan 2027 2 mo to go 169
Pristine By ZoyaJabal Ali FirstZoya One Real Estate Developments L.L.C 58.4% 1 Jan 2027 2 mo to go 73
Dreamlife ResidencesPalm DeiraNova Power Real Estate L.L.C 31% 15 Jan 2027 2 mo to go 103
La Cle by Maaia DevelopersJabal Ali FirstMaaia Prime Real Estate Developers L.L.C 34.6% 14 Jan 2027 2 mo to go 58
27 East End Garden Residences By Mirha Homes Real Estate DevelopmentWarsan FourthMirha Homes Real Estate Development L.L.C 40.3% 31 Jan 2027 2 mo to go 96
Luzora ResidencesPalm DeiraD I A Homes Real Estate Development L.L.C 21.3% 6 Jan 2027 2 mo to go 108
Sadaat TowerWarsan FourthGulab Real Estate Development L.L.C 32.1% 31 Jan 2027 2 mo to go 89
EVERGRIN House 4Al SatwaOBJ1 Real Estate Development L.L.C 23.6% 15 Jan 2027 2 mo to go 89
Island Living by CondorPalm DeiraCondor Island Living Real Estate Development L.L.C S.O.C 0% 10 Jan 2027 2 mo to go 62
Ahs TowerTrade Center SecondAhs Tower Holding Development L.L.C S.O.C 67.4% 31 Jan 2027 2 mo to go 83

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Marked completed by DLD in January 2027 (0)

DLD marked no project completed in January 2027.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology