Dubai off-plan handovers: January 2027 15 projects · 15 not yet completed · 2,847 units DLD projects register as of 1 November 2026 · sales to 5 November 2026
January 2027 has not started yet. 15 projects in the Dubai Land Department projects register have their DLD end date in January 2027 (register of 1 November 2026). DLD can change an end date before it comes. By DLD status: Under construction 14 · Not started 1. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
14 projects| % completed | Projects |
|---|---|
| 0–25% | 2 |
| 25–50% | 9 |
| 50–75% | 3 |
| 75–100% | 0 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
15 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
DLD end date in January 2027 (15) 15 projects, by sales over 24 months
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Marked completed by DLD in January 2027 (0)
DLD marked no project completed in January 2027.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology