Dubai off-plan handovers: September 2026 21 marked completed by DLD · 24 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026
In September 2026, DLD marked 21 projects completed. 24 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 18 · Conditionally activating 1 · Pending 1 · Completed 4. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
18 projects| % completed | Projects |
|---|---|
| 0–25% | 4 |
| 25–50% | 7 |
| 50–75% | 6 |
| 75–100% | 1 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
24 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
Marked completed by DLD in September 2026 (21)
| Project | Area | Developer | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|---|
| Binghatti Ghost | Al Jadaf | Binghatti Developers FZE | 31 Mar 2026 | 23 Sep 2026 | 5 mo after | 785 |
| Binghatti Ivory | Al Jadaf | Binghatti Developers FZE | 31 Dec 2025 | 15 Sep 2026 | 8 mo after | 332 |
| Helvetia Residences | Al Barsha South Fourth | D H G Property Development L.L.C | — | 30 Sep 2026 | — | 432 |
| Elbrus Tower | Al Barsha South Fifth | Tiger Properties | 31 Mar 2026 | 3 Sep 2026 | 5 mo after | 270 |
| Gharbi I Residences | Al Barshaa South Third | Rabdan Real Estate Development L.L.C | 14 Sep 2026 | 21 Sep 2026 | 1 wk after | 170 |
| 4B Living | Warsan Fourth | H S E Realty Real Estate L.L.C | 30 Aug 2025 | 16 Sep 2026 | 12 mo after | 74 |
| Mudon Al Ranim 7 | Al Hebiah Sixth | Mdn Real Estate L.L.C | 30 Sep 2026 | 17 Sep 2026 | 1 wk before | 248 |
| Society House Downtown Dubai | Burj Khalifa | Digo Real Estate Development (Br Of Invest Group Overseas (L L C) ) | — | 14 Sep 2026 | — | 417 |
| Mudon Al Ranim 8 | Al Hebiah Sixth | Mdn Real Estate L.L.C | 30 Sep 2026 | 17 Sep 2026 | 1 wk before | 228 |
| Jomana | Um Suqaim Third | Jumeirah Hills Development L.L.C | 30 Apr 2026 | 8 Sep 2026 | 4 mo after | 326 |
| Weybridge Gardens | Wadi Al Safa 5 | Leos Development L.L.C | — | 8 Sep 2026 | — | 187 |
| Beachgate by Address | Marsa Dubai | Emaar Development P.J.S.C. | 31 Dec 2026 | 22 Sep 2026 | 3 mo before | 252 |
| Starlight Park | Wadi Al Safa 3 | A & B Unicorn Real Estate Development L.L.C | — | 3 Sep 2026 | — | 180 |
| Six Senses Residences The Palm, Dubai | Palm Jumeirah | Select Global Development L.L.C | 31 Dec 2024 | 3 Sep 2026 | 20 mo after | 173 |
| Kaya | Al Yelayiss 2 | Nshama Properties Owned By Nshmi Development One Person Company L.L.C | — | 24 Sep 2026 | — | 164 |
| Elegance Tower | Burj Khalifa | Pathfinder Property Development L.L.C | 28 Feb 2026 | 17 Sep 2026 | 6 mo after | 296 |
| Marquis Elegance | Al Barshaa South Third | Marquis Circle Real Estate Developer L.L.C | — | 7 Sep 2026 | — | 139 |
| GARDENIA1 & 2 | Al Barsha South Fourth | Memon Investments L.L.C | 30 Jun 2023 | 1 Sep 2026 | 38 mo after | 172 |
| Celia gardens | Nad Al Shiba First | Abou Eid Real Estate Development L.L.C | 15 May 2026 | 21 Sep 2026 | 4 mo after | 44 |
| THE RESIDENCE | Burj Khalifa | Burj Khalifa | Emaar Properties (P.J.S.C) | 31 Dec 2024 | 22 Sep 2026 | 20 mo after | 35 |
| Aura Central | Al Barshaa South Third | Aura Infinite Real Estate Development L.L.C | 14 Jul 2027 | 1 Sep 2026 | 10 mo before | 38 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end date in September 2026: DLD status in the register of 1 November 2026 (24) 24 projects, by sales over 24 months
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology