Memon Investments L.L.C ميمون للاستثمارات ذ.م.م 3 projects in the DLD register: 2 completed, 0 under construction, 1 not started or pending. DLD projects register, export of 1 November 2026
Delivery record
Projects: 3- 288 units and villas in completed projects; 254 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Memon Investments L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| GARDENIA1 & 2647 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Sep 2026 Completed | 172 | 22 |
| Champion Tower 3646 · Al Hebiah Fourth · Dubai Sports City | Pending | 94.5% | Sep 2028 22 mo to go | 254 | 1 |
| Cambridge Business Centre645 · Nadd Hessa · Silicon Oasis | Completed | 100% | Apr 2015 Completed | 116 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 1, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.