Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 647Completed172 units

GARDENIA1 & 2 جاردينيا 1 و 2 Al Barsha South Fourth · Jumeirah Village Circle by Memon Investments L.L.CAll phases of Jumeirah Village Circle Completed 1 September 2026 (DLD) DLD end date Jun 2023 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Sep 2026
DLD end date Jun 2023
Build time
151 months
Feb 2014 → Sep 2026
Latest sales
—
Fewer than 5 recent sales
Developer
3 projects
2 completed · 288 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 100% built on 27 August 2026 (inspections: 16).
Every DLD inspection and every change in the register %, newest first
Date % built Source
27 August 2026 100% DLD inspection
29 April 2025 96.8% DLD inspection
15 February 2024 74.8% DLD inspection
5 August 2022 65% DLD register, archived export
4 July 2022 65.4% DLD inspection
18 July 2021 64% DLD inspection
15 December 2020 56.8% DLD inspection
24 August 2020 56.1% DLD inspection
24 December 2019 56.1% DLD inspection
21 January 2019 55.9% DLD inspection
13 February 2018 48.6% DLD inspection
25 July 2017 45.1% DLD inspection
5 January 2017 36.1% DLD inspection
14 July 2016 29.2% DLD inspection
19 January 2016 12.6% DLD inspection
6 October 2015 4.1% DLD inspection
13 July 2014 4.1% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
113 monthsActual build
151 months
Start date
1 February 2014
DLD end date
30 June 2023
Completion date
1 September 2026
Completion vs DLD end date
38 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
647
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Trakhees
Master project
Jumeirah Village Circle
DLD area
Al Barsha South Fourth
Units · villas
171 · 1
Start → DLD end
Feb 2014 → Jun 2023
Registered unitsStudio 60 · 1 bed 94 · 2 bed 7 · 3 bed 7 · no bedroom count 1; sizes 546–1,016 sqft

Homes: flats 168 · villas 1.

Also registered: shops and showrooms 3.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: PROJECT CONSISTS OF B+G+4+R RESIDENTIAL APARTMENTS LOCATED IN AL BARSHA SOUTH FOURTH. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 8 — —
1 BR 13 — —

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2021-Q1 → 2024-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Barsha South Fourth, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.31 AED/sqft a year
Jumeirah Village Circle: median of 112 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

No registered sales in the 12 months to 5 November 2026; the newest 10 before that
DateMarketType Size (sqft) Price (AED) AED/sqft
17 December 2024off-planApartment · 1 BR 940 640,000 681
9 December 2024off-planApartment · Studio 1,283 705,650 550
9 December 2024off-planApartment · 1 BR 889 488,950 550
9 December 2024off-planApartment · 1 BR 846 465,300 550
6 December 2024off-planApartment · Studio 543 477,306 879
5 December 2024off-planApartment · 1 BR 941 541,075 575
5 December 2024off-planApartment · 1 BR 911 523,825 575
2 December 2024off-planApartment · 1 BR 941 541,075 575
2 December 2024off-planApartment · 1 BR 932 535,900 575
2 December 2024off-planApartment · Studio 607 531,706 876

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Barsha South Fourth · Dubai Municipality community

Park · 90 mSider Park · 160 mGreens Mini Mart · 250 mQaret · 260 mZaynal Grocery · 460 mStar Mart Supermarket · 530 mProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationNakheel Metro Station · Red Metro line · 5.9 km
MallThe Springs Souk · 1.5 km
SupermarketGreens Mini Mart · 250 m
HospitalMediclinic Springs · 3.4 km
SchoolKinderopvang smallsteps leidsche rijn · 1.6 km
ParkPark · 90 m
BeachBeach · 7.2 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 139, with 30,685 units and villas.

2010: 02013: 1652024: 2292025: 1,6972026: 7,2152027: 7,0472028: 6,7252029: 2,719No end date: 4,888

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Barsha South Fourth: 153

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Circle 22.1% May 2027 1,611 779
Serenz by Danube 0.1% Dec 2029 2,302 673
Binghatti Amberhall 70% Feb 2026 1,696 623
Binghatti Ruby 65% Feb 2026 1,967 552
One Sky Park By Iman 21.7% Mar 2028 1,650 549
Auresta Tower 4.4% Dec 2028 1,609 523
Skyhills II by HRE 96% Jun 2026 1,531 481
Skyhills III by HRE 75.7% Jun 2026 1,598 418
Legado By Prescott 23.3% Aug 2027 1,748 342
Violet Tower 90.2% Jun 2026 1,345 285
The AUTOGRAPH-I Series 4% Aug 2028 1,691 269
Maison Elysee Iii By Pantheon 4.4% Oct 2027 1,679 260

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Barsha South Fourth

Developer in DLD data Memon Investments L.L.C · DLD developer no. 952

Projects registered
3
2 completed · 0 under construction · 1 not started
Units delivered
288
254 in the pipeline

Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Jumeirah Village Circle

DLD lists 410 projects in the master project Jumeirah Village Circle.

Luxury Family ResidenceUnder construction · 76% · Dec 2023
North Forty Three Serviced ResidencesUnder construction · 94.7% · Jul 2024
7 Park Central By MeteoraUnder construction · 90.2% · Apr 2025
The PortmanUnder construction · 78.7% · Sep 2025
Serenity Lakes 2Under construction · 50.5% · Nov 2025
Levanto By ORO24Under construction · 66% · Dec 2025
Sky Suites by Peace HomesUnder construction · 55.5% · Dec 2025
Ashton Park Residences The SecondUnder construction · 70.1% · Dec 2025
Maimoon GardensUnder construction · 78% · Dec 2025
99 Park PlaceUnder construction · 90% · Dec 2025
Elitz By DanubeUnder construction · 91.8% · Dec 2025
Q Gardens LoftsUnder construction · 90.7% · Dec 2025

Questions about GARDENIA1 & 2

When was GARDENIA1 & 2 completed?

GARDENIA1 & 2 is recorded as completed on 1 September 2026 (DLD register of 1 November 2026).

Who is the developer of GARDENIA1 & 2?

Memon Investments L.L.C, as registered with DLD.

What is the DLD project number of GARDENIA1 & 2?

647.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error