DLD project no. 2582Completed326 units
Jomana جومانه Completed 8 September 2026 (DLD) · DLD end date Apr 2026 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.

CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 4 September 2026 | 100% | DLD inspection |
| 20 May 2026 | 83.5% | DLD inspection |
| 20 January 2026 | 71.7% | DLD inspection |
| 17 October 2025 | 61.5% | DLD inspection |
| 28 July 2025 | 45.9% | DLD inspection |
| 29 April 2025 | 39% | DLD inspection |
| 16 January 2025 | 20.8% | DLD inspection |
| 23 September 2024 | 4.6% | DLD inspection |
| 12 May 2024 | 0% | DLD register, archived export |
| 8 May 2024 | 0.4% | DLD inspection |
| 14 February 2023 | 0% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
DLD registration
DLD services ↗Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: 8 x Townhouses: G+5 Residential, The project designed to have a concrete structure and block with internal and external finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Dubai Statistics Center residential price index (flats), 2023-Q2 to 2026-Q2: +17.7%.
Prices are over apartments, the type most sales in this project are.
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| 1 BR | 18 | 3,166 (13) | Nov 2025 – Nov 2026 |
| 2 BR | 23 | 2,604 (10) | Nov 2025 – Nov 2026 |
| 3 BR | 12 | — | — |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2023-Q2 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Um Suqaim Third |
|---|---|---|---|
| 2023-Q2 | 199 (off-plan 199, ready 0) | 2,655 | 2,684 |
| 2023-Q3 | 100 (off-plan 100, ready 0) | 2,693 | 2,924 |
| 2023-Q4 | 25 (off-plan 25, ready 0) | 2,724 | 2,720 |
| 2024-Q1 | 3 (off-plan 3, ready 0) | — | 2,652 |
| 2024-Q2 | 4 (off-plan 4, ready 0) | — | 2,829 |
| 2024-Q3 | 3 (off-plan 3, ready 0) | — | 2,542 |
| 2024-Q4 | 5 (off-plan 5, ready 0) | 2,429 | 2,644 |
| 2025-Q1 | 3 (off-plan 3, ready 0) | — | 2,808 |
| 2025-Q2 | 8 (off-plan 8, ready 0) | 2,583 | 3,001 |
| 2025-Q3 | 8 (off-plan 8, ready 0) | 2,509 | 2,770 |
| 2025-Q4 | 7 (off-plan 7, ready 0) | 2,704 | 3,054 |
| 2026-Q1 | 12 (off-plan 12, ready 0) | 2,798 | 3,016 |
| 2026-Q2 | 6 (off-plan 6, ready 0) | 2,786 | 2,463 |
| 2026-Q3 | 4 (off-plan 3, ready 1) | — | 2,664 |
| 2026-Q4 | 4 (off-plan 0, ready 4) | — | 2,820 |
Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Um Suqaim Third, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Um Suqaim Third |
|---|---|---|---|
| 2023-Q2 | 199 (off-plan 199, ready 0) | 2,655 | 2,684 |
| 2023-Q3 | 100 (off-plan 100, ready 0) | 2,693 | 2,924 |
| 2023-Q4 | 25 (off-plan 25, ready 0) | 2,724 | 2,720 |
| 2024-Q1 | 3 (off-plan 3, ready 0) | — | 2,652 |
| 2024-Q2 | 4 (off-plan 4, ready 0) | — | 2,829 |
| 2024-Q3 | 3 (off-plan 3, ready 0) | — | 2,542 |
| 2024-Q4 | 5 (off-plan 5, ready 0) | 2,429 | 2,644 |
| 2025-Q1 | 3 (off-plan 3, ready 0) | — | 2,808 |
| 2025-Q2 | 8 (off-plan 8, ready 0) | 2,583 | 3,001 |
| 2025-Q3 | 8 (off-plan 8, ready 0) | 2,509 | 2,770 |
| 2025-Q4 | 7 (off-plan 7, ready 0) | 2,704 | 3,054 |
| 2026-Q1 | 12 (off-plan 12, ready 0) | 2,798 | 3,016 |
| 2026-Q2 | 6 (off-plan 6, ready 0) | 2,786 | 2,463 |
| 2026-Q3 | 4 (off-plan 3, ready 1) | — | 2,664 |
| 2026-Q4 | 4 (off-plan 0, ready 4) | — | 2,820 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
What launch buyers got
The launch price against the registered resales after completion, same home types on both sides.
Too few ready sales in DLD area Um Suqaim Third in both windows for a comparison over the same span.
Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 27 October 2026 | ready | Apartment · 1 BR | 9 | 785,395 | 87,266 |
| 26 October 2026 | ready | Apartment · 1 BR | 903 | 3,225,105 | 3,572 |
| 14 October 2026 | ready | Apartment · 3 BR | 2,420 | 6,960,000 | 2,876 |
| 6 October 2026 | ready | Apartment · 2 BR | 1,330 | 3,750,000 | 2,820 |
| 21 September 2026 | ready | Apartment · 2 BR | 1,342 | 4,250,000 | 3,167 |
| 14 August 2026 | off-plan | Apartment · 2 BR | 1,344 | 3,500,000 | 2,604 |
| 20 July 2026 | off-plan | Apartment · 3 BR | 2,185 | 5,721,000 | 2,618 |
| 13 July 2026 | off-plan | Apartment · 2 BR | 1,600 | 3,600,000 | 2,250 |
| 22 June 2026 | off-plan | Apartment · 2 BR | 1,354 | 2,800,000 | 2,068 |
| 3 June 2026 | off-plan | Apartment · 1 BR | 799 | 2,534,000 | 3,171 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationUmm Suqeim Third · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 3, with 718 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2026 | 1 | 238 |
| 2029 | 1 | 236 |
| No end date | 1 | 244 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Umm Suqeim Third: 3
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Nourelle | 4% | Mar 2029 | 4,204 | 220 |
| Riwa | 12.5% | — | — | 28 |
| Elara | 64.3% | Nov 2026 | 2,570 | 13 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Jumeirah Hills Development L.L.C · DLD developer no. 1076
Completed a month or more after their DLD end date: 3 of 7 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Questions about Jomana
When was Jomana completed?
Jomana is recorded as completed on 8 September 2026 (DLD register of 1 November 2026).
Who is the developer of Jomana?
Jumeirah Hills Development L.L.C, as registered with DLD.
What is the DLD project number of Jomana?
2582.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error