DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: March 2026 12 marked completed by DLD · 28 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026

In March 2026, DLD marked 12 projects completed. 28 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 18 · Conditionally activating 1 · Completed 9. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

18 projects
0–25%: 025–50%: 150–75%: 875–100%: 9

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

28 projects
Under construction18
Conditionally activating1
Completed before March 20269

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

Marked completed by DLD in March 2026 (12)

Marked completed by DLD in March 2026 (12)
ProjectArea Developer DLD end dateCompletedAgainst the end date Units
Neva ResidencesAl Barsha South FourthTiger Properties 31 Dec 2025 12 Mar 2026 2 mo after 409
The Valley - EloraAl Yufrah 1Emaar Development P.J.S.C. 30 Sep 2026 13 Mar 2026 6 mo before 430
Creek PalaceAl Khairan FirstThe Lagoons Phase One L.L.C 31 Mar 2026 31 Mar 2026 On the end date 337
Silver Park ResidencyWarsan FourthManjothi Real Estate Development L.L.C 30 Oct 2025 18 Mar 2026 4 mo after 76
Ellington House IiHadaeq Sheikh Mohammed Bin RashidEh 2 Development L.L.C 30 Apr 2025 15 Mar 2026 10 mo after 166
RA1N ResidenceAl Barsha South FourthObject One Real Estate Development L.L.C 23 Feb 2025 10 Mar 2026 12 mo after 146
Pg One At Al FurjanJabal Ali FirstPg Properties Development DMCC — 25 Mar 2026 — 121
Cubix ResidencesAl Barsha South FourthQube Development L.L.C 1 Nov 2025 12 Mar 2026 4 mo after 72
Elegance by Chaimaa HoldingAl Barsha South FourthDeval Real Estate Development L.L.C 1 Nov 2024 10 Mar 2026 16 mo after 118
Aras HeightsWadi Al Safa 3A R A S Real Estate Development L.L.C 31 Dec 2023 12 Mar 2026 26 mo after 73
The Residence By Prestige OneAl Barsha South FourthPrestige One Luxury Real Estate L.L.C 30 Nov 2025 27 Mar 2026 3 mo after 98
SunridgeMadinat Dubai AlmelaheyahMina Rashid Properties L.L.C — 17 Mar 2026 — 130

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end date in March 2026: DLD status in the register of 1 November 2026 (28) 28 projects, by sales over 24 months

DLD end date in March 2026: DLD status in the register of 1 November 2026 (28)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Binghatti GhostAl JadafBinghatti Developers FZE — 31 Mar 2026 Completed 785
Binghatti HavenAl Hebiah FourthBinghatti Developers FZE 76.1% 31 Mar 2026 7 mo past 501
Binghatti StarlightAl JadafBinghatti Developers FZE 63.1% 31 Mar 2026 7 mo past 511
Binghatti GroveAl Barsha South FourthBinghatti Developers FZE — 31 Mar 2026 Completed 404
PELaGOS By IGOMarsa DubaiDigo Real Estate Development (Br Of Invest Group Overseas (L L C) ) 84.2% 31 Mar 2026 7 mo past 296
Sportz By DanubeAl Hebiah FourthDanube Properties Development L.L.C 80.2% 30 Mar 2026 7 mo past 1,110
161 Jumeirah LaneAl SatwaNational Properties Owned By National Bonds Corporation Sole Proprietorship PSC Sole Proprietorship L.L.C 70% 1 Mar 2026 8 mo past 161
Elbrus TowerAl Barsha South FifthTiger Properties — 31 Mar 2026 Completed 270
Uh West By EllingtonAl Thanyah FifthEllington Properties Development L.L.C 83.7% 3 Mar 2026 7 mo past 381
Lilium TowerAl Barsha South FifthTiger Properties — 31 Mar 2026 Completed 266
Palatium ResidencesAl Barsha South FourthAhmadyar Real Estate Development L.L.C 87.9% 31 Mar 2026 7 mo past 151
Lime GardensHadaeq Sheikh Mohammed Bin RashidDubai Hills Estate L.L.C — 31 Mar 2026 Completed 293
Uh East By EllingtonAl Thanyah FifthEllington Properties Development L.L.C 62.8% 30 Mar 2026 7 mo past 381
Mayflower ResidencesWarsan FourthA J G Warsan Real Estate Development L.L.C 96.1% 31 Mar 2026 7 mo past 99
Park Lane 2 By HeilbronnAl Barsha South FourthHeilbronn Properties Development L.L.C — 31 Mar 2026 Completed 83
Milestone ResidencesAl Barsha South FifthAxiom Prime Real Estate Development L.L.C — 13 Mar 2026 Completed 53
Roma Residences by JRPAl Barsha South FourthJ R P Properties L.L.C 76.8% 31 Mar 2026 7 mo past 80
FernAl WaslCitywalk Residential 1 L.L.C — 21 Mar 2026 Completed 214
Azizi Riviera 69Al MerkadhAzizi Developments L.L.C — 30 Mar 2026 Completed 123
Lodge Residences by Riviera AzureAl Barsha South FourthRiviera Azure Properties Development 63.3% 1 Mar 2026 8 mo past 56
The QuaysideBusiness BayQuayside Developers L.L.C 54.6% 31 Mar 2026 7 mo past 119
Lua ResidencesWadi Al Safa 3Swank Real Estate Development L.L.C 64.4% 31 Mar 2026 7 mo past 37
Pier 8Marsa DubaiPier 8 Real Estate Development L.L.C 70.1% 8 Mar 2026 7 mo past 341
Samana Waves 2Al Barsha South FourthSamana Si Holding Limited Dubai Branch 52.1% 20 Mar 2026 7 mo past 173
One CrescentPalm JumeirahA H S Palm Development L.L.C 80.1% 1 Mar 2026 8 mo past 25
Orchid Residence 1Madinat Al MataarOrchid Living Real Estate L.L.C 48.5% 31 Mar 2026 7 mo past 44
Niki Lauda TowerBusiness BayPlt Properties FZCO 0.4% 31 Mar 2026 — 384
Best Town VillasAl Barsha South FifthBest City Real Estate Development L.L.C 76.1% 30 Mar 2026 7 mo past 3

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology