DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: April 2026 30 marked completed by DLD · 25 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026

In April 2026, DLD marked 30 projects completed. 25 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 22 · Completed 3. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

22 projects
0–25%: 125–50%: 350–75%: 1075–100%: 8

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

25 projects
Under construction22
Completed before April 20263

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

Marked completed by DLD in April 2026 (30)

Marked completed by DLD in April 2026 (30)
ProjectArea Developer DLD end dateCompletedAgainst the end date Units
Binghatti ApexAl Barsha South FourthBinghatti Developers FZE 30 Apr 2026 23 Apr 2026 1 wk before 552
The Fields At D11 - MbrmcWadi Al Safa 3G&CO Real Estate Development LLC - FZ 31 May 2023 10 Apr 2026 34 mo after 1,028
Sobha Hartland - Crest GrandeAl MerkadhSobha L.L.C 30 Jun 2026 15 Apr 2026 2 mo before 985
RegaliaBusiness BayDeyaar Development (P.J.S.C) 31 Dec 2024 29 Apr 2026 15 mo after 913
Damac Lagoons - Costa Brava (1)Al Hebiah FifthIsland Oasis Properties 29 Jul 2025 10 Apr 2026 8 mo after —
Koro OneAl SatwaKoro Real Estate Development L.L.C 31 Jan 2026 24 Apr 2026 2 mo after 147
Ab CavalierAl Barsha South FourthAb Developers L.L.C — 23 Apr 2026 — 165
Olivo Park Residences By EveraAl Barsha South FourthEvera Real Estate Development CO. L.L.C 15 Dec 2025 28 Apr 2026 4 mo after 122
Damac Lagoons - Malta (2)Al Hebiah FifthIsland Oasis Properties 29 Sep 2025 8 Apr 2026 6 mo after —
Serenia LivingPalm JumeirahPalma Homes Real Estate Development L.L.C 31 Dec 2025 23 Apr 2026 3 mo after 226
The Haven GardenAl Barsha South FourthMetrical Real Estate Development L.L.C — 6 Apr 2026 — 199
Arbor ViewAl Barshaa South ThirdE L P D Developers L.L.C — 6 Apr 2026 — 171
Volna By KascoAl JadafKasco Real Estate Development L.L.C 31 May 2026 22 Apr 2026 1 mo before 71
NAS3Al Barshaa South ThirdRabdan Real Estate Development L.L.C 1 Feb 2026 8 Apr 2026 2 mo after 288
WAHA LIVING by AL YAKKAAl SatwaAlyakka Developers L.L.C 30 Sep 2025 7 Apr 2026 6 mo after 71
Vista by Prestige OneAl Hebiah FourthPrestige One Luxury Real Estate L.L.C 30 Jun 2025 2 Apr 2026 9 mo after 140
Marquis GalleriaAl Barshaa South ThirdMarquis Home Developer L.L.C 31 Dec 2024 10 Apr 2026 15 mo after 126
Cresswell ResidencesMadinat Al MataarAbdulwahed Faqeeh Properties L.L.C 26 Jun 2025 20 Apr 2026 9 mo after 72
Divine ResidenciaAl Hebiah SecondTakmeel Real Estate Development L.L.C — 20 Apr 2026 — 69
The Valley - Farm GardensAl Yufrah 1Emaar Development P.J.S.C. 31 Aug 2026 6 Apr 2026 4 mo before —
Aark ResidencesWadi Al Safa 5Aark Developers L.L.C 23 Dec 2024 27 Apr 2026 16 mo after 100
Pearl House III by ImtiazAl Barsha South FourthImtiaz Ghd Real Estate Development L.L.C 1 Aug 2026 26 Apr 2026 3 mo before 165
Jebel Ali VillageJabal Ali FirstJebel Ali Village (L.L.C) 30 Dec 2025 29 Apr 2026 3 mo after —
Damac Lagoons - Santorini (3)Al Hebiah FifthIsland Oasis Properties 29 Jul 2025 9 Apr 2026 8 mo after —
Haven LivingPalm DeiraMetac Properties L.L.C 26 Dec 2025 28 Apr 2026 4 mo after 51
The Veranda Collection 1Al Barsha South FourthPacifique Global Properties L.L.C 15 Sep 2025 16 Apr 2026 7 mo after 12
Jebel Ali Village Townhouses- Phase 1Jabal Ali FirstJebel Ali Village (L.L.C) 31 Dec 2025 29 Apr 2026 3 mo after —
Jebel Ali Village Townhouses - Phase 2Jabal Ali FirstJebel Ali Village (L.L.C) 31 Dec 2025 29 Apr 2026 3 mo after —
Jebel Ali Village Townhouses - Phase 3Jabal Ali FirstJebel Ali Village (L.L.C) 31 Dec 2025 29 Apr 2026 3 mo after —
Azizi Riviera 56Al MerkadhAzizi Developments L.L.C 13 Mar 2027 29 Apr 2026 10 mo before 87

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end date in April 2026: DLD status in the register of 1 November 2026 (25) 25 projects, by sales over 24 months

DLD end date in April 2026: DLD status in the register of 1 November 2026 (25)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Binghatti HillviewsAl Barshaa South SecondBinghatti Developers FZE 32.6% 1 Apr 2026 7 mo past 1,575
Beach Oasis 2Al Hebiah SecondAzizi Developments L.L.C 53.2% 30 Apr 2026 6 mo past 704
Binghatti TwilightAl JadafBinghatti Developers FZE 55.4% 30 Apr 2026 6 mo past 277
Verdana Residence 2Dubai Investment Park FirstReportage Prime Properties L.L.C 20% 30 Apr 2026 6 mo past 239
Urban Park ResidencesAl Hebiah FourthUrban Venture Real Estate Development L.L.C 67.6% 1 Apr 2026 7 mo past 187
Hills ParkHadaeq Sheikh Mohammed Bin RashidDubai Hills Estate L.L.C — 30 Apr 2026 Completed 450
Parkwood ResidencesAl Barsha South FourthArabian Gulf Properties 57% 30 Apr 2026 6 mo past 174
Aura EliteNadd HessaAura Infinite Real Estate Development L.L.C 44.3% 30 Apr 2026 6 mo past 86
Imperial ResidenceMe'Aisem FirstImperial 55 Real Estate Development L.L.C 43% 30 Apr 2026 6 mo past 137
Allegro ResidencesPalm DeiraMill Hill Riviera Development L.L.C 84.5% 7 Apr 2026 6 mo past 60
JomanaUm Suqaim ThirdJumeirah Hills Development L.L.C — 30 Apr 2026 Completed 326
Dalmore TowerWadi Al Safa 5Dalmore Real Estate Development L.L.C 95.1% 23 Apr 2026 6 mo past 120
Mackerel TowerPalm DeiraTarrad Development L.L.C 56.6% 1 Apr 2026 7 mo past 62
Samana WavesAl Barsha South FourthSamana Si Holding Limited Dubai Branch 90.6% 15 Apr 2026 6 mo past 197
ROVE HOME RESIDENCES by IRTHBurj KhalifaIrth Development L.L.C 62.7% 30 Apr 2026 6 mo past 349
Nad Al Sheba Gardens Phase 3Nad Al Shiba FirstAl Qudra Estates L.L.C 97% 19 Apr 2026 6 mo past 235
Almaan 101Al Barsha South FourthM N Vision Real Estate Development L.L.C 50.9% 13 Apr 2026 6 mo past 102
Samana SkyrosAl Barshaa South ThirdSamana Signature Real Estate Developments L.L.C 71.3% 30 Apr 2026 6 mo past 441
Samana Mykonos SignatureAl Barshaa South ThirdSamana International Real Estate Development L.L.C 86% 30 Apr 2026 6 mo past 300
Samana MykonosAl Hebiah SecondSamana International Real Estate Development L.L.C 91.1% 30 Apr 2026 6 mo past 198
Elysee HeightsAl Barsha South FourthPantheon Elysee Real Estate Development L.L.C 81.3% 14 Apr 2026 6 mo past 193
Eywa DubaiBusiness BayRvl Real Estate L.L.C 65.7% 1 Apr 2026 7 mo past 53
The Woodland ResidencesWadi Al Safa 3A M I S Real Estate Development L.L.C 75.4% 8 Apr 2026 6 mo past 30
The Veranda Collection 2Al Barsha South FourthPacifique Global Properties L.L.C — 7 Apr 2026 Completed 13
W1Jabal Ali FirstMalina W1 Real Estate Development L.L.C 70.2% 30 Apr 2026 6 mo past 83

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology