Dubai off-plan handovers: April 2026 30 marked completed by DLD · 25 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026
In April 2026, DLD marked 30 projects completed. 25 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 22 · Completed 3. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
22 projects| % completed | Projects |
|---|---|
| 0–25% | 1 |
| 25–50% | 3 |
| 50–75% | 10 |
| 75–100% | 8 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
25 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
Marked completed by DLD in April 2026 (30)
| Project | Area | Developer | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|---|
| Binghatti Apex | Al Barsha South Fourth | Binghatti Developers FZE | 30 Apr 2026 | 23 Apr 2026 | 1 wk before | 552 |
| The Fields At D11 - Mbrmc | Wadi Al Safa 3 | G&CO Real Estate Development LLC - FZ | 31 May 2023 | 10 Apr 2026 | 34 mo after | 1,028 |
| Sobha Hartland - Crest Grande | Al Merkadh | Sobha L.L.C | 30 Jun 2026 | 15 Apr 2026 | 2 mo before | 985 |
| Regalia | Business Bay | Deyaar Development (P.J.S.C) | 31 Dec 2024 | 29 Apr 2026 | 15 mo after | 913 |
| Damac Lagoons - Costa Brava (1) | Al Hebiah Fifth | Island Oasis Properties | 29 Jul 2025 | 10 Apr 2026 | 8 mo after | — |
| Koro One | Al Satwa | Koro Real Estate Development L.L.C | 31 Jan 2026 | 24 Apr 2026 | 2 mo after | 147 |
| Ab Cavalier | Al Barsha South Fourth | Ab Developers L.L.C | — | 23 Apr 2026 | — | 165 |
| Olivo Park Residences By Evera | Al Barsha South Fourth | Evera Real Estate Development CO. L.L.C | 15 Dec 2025 | 28 Apr 2026 | 4 mo after | 122 |
| Damac Lagoons - Malta (2) | Al Hebiah Fifth | Island Oasis Properties | 29 Sep 2025 | 8 Apr 2026 | 6 mo after | — |
| Serenia Living | Palm Jumeirah | Palma Homes Real Estate Development L.L.C | 31 Dec 2025 | 23 Apr 2026 | 3 mo after | 226 |
| The Haven Garden | Al Barsha South Fourth | Metrical Real Estate Development L.L.C | — | 6 Apr 2026 | — | 199 |
| Arbor View | Al Barshaa South Third | E L P D Developers L.L.C | — | 6 Apr 2026 | — | 171 |
| Volna By Kasco | Al Jadaf | Kasco Real Estate Development L.L.C | 31 May 2026 | 22 Apr 2026 | 1 mo before | 71 |
| NAS3 | Al Barshaa South Third | Rabdan Real Estate Development L.L.C | 1 Feb 2026 | 8 Apr 2026 | 2 mo after | 288 |
| WAHA LIVING by AL YAKKA | Al Satwa | Alyakka Developers L.L.C | 30 Sep 2025 | 7 Apr 2026 | 6 mo after | 71 |
| Vista by Prestige One | Al Hebiah Fourth | Prestige One Luxury Real Estate L.L.C | 30 Jun 2025 | 2 Apr 2026 | 9 mo after | 140 |
| Marquis Galleria | Al Barshaa South Third | Marquis Home Developer L.L.C | 31 Dec 2024 | 10 Apr 2026 | 15 mo after | 126 |
| Cresswell Residences | Madinat Al Mataar | Abdulwahed Faqeeh Properties L.L.C | 26 Jun 2025 | 20 Apr 2026 | 9 mo after | 72 |
| Divine Residencia | Al Hebiah Second | Takmeel Real Estate Development L.L.C | — | 20 Apr 2026 | — | 69 |
| The Valley - Farm Gardens | Al Yufrah 1 | Emaar Development P.J.S.C. | 31 Aug 2026 | 6 Apr 2026 | 4 mo before | — |
| Aark Residences | Wadi Al Safa 5 | Aark Developers L.L.C | 23 Dec 2024 | 27 Apr 2026 | 16 mo after | 100 |
| Pearl House III by Imtiaz | Al Barsha South Fourth | Imtiaz Ghd Real Estate Development L.L.C | 1 Aug 2026 | 26 Apr 2026 | 3 mo before | 165 |
| Jebel Ali Village | Jabal Ali First | Jebel Ali Village (L.L.C) | 30 Dec 2025 | 29 Apr 2026 | 3 mo after | — |
| Damac Lagoons - Santorini (3) | Al Hebiah Fifth | Island Oasis Properties | 29 Jul 2025 | 9 Apr 2026 | 8 mo after | — |
| Haven Living | Palm Deira | Metac Properties L.L.C | 26 Dec 2025 | 28 Apr 2026 | 4 mo after | 51 |
| The Veranda Collection 1 | Al Barsha South Fourth | Pacifique Global Properties L.L.C | 15 Sep 2025 | 16 Apr 2026 | 7 mo after | 12 |
| Jebel Ali Village Townhouses- Phase 1 | Jabal Ali First | Jebel Ali Village (L.L.C) | 31 Dec 2025 | 29 Apr 2026 | 3 mo after | — |
| Jebel Ali Village Townhouses - Phase 2 | Jabal Ali First | Jebel Ali Village (L.L.C) | 31 Dec 2025 | 29 Apr 2026 | 3 mo after | — |
| Jebel Ali Village Townhouses - Phase 3 | Jabal Ali First | Jebel Ali Village (L.L.C) | 31 Dec 2025 | 29 Apr 2026 | 3 mo after | — |
| Azizi Riviera 56 | Al Merkadh | Azizi Developments L.L.C | 13 Mar 2027 | 29 Apr 2026 | 10 mo before | 87 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end date in April 2026: DLD status in the register of 1 November 2026 (25) 25 projects, by sales over 24 months
| Project | Area | Developer | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|---|
| Binghatti Hillviews | Al Barshaa South Second | Binghatti Developers FZE | 32.6% | 1 Apr 2026 | 7 mo past | 1,575 |
| Beach Oasis 2 | Al Hebiah Second | Azizi Developments L.L.C | 53.2% | 30 Apr 2026 | 6 mo past | 704 |
| Binghatti Twilight | Al Jadaf | Binghatti Developers FZE | 55.4% | 30 Apr 2026 | 6 mo past | 277 |
| Verdana Residence 2 | Dubai Investment Park First | Reportage Prime Properties L.L.C | 20% | 30 Apr 2026 | 6 mo past | 239 |
| Urban Park Residences | Al Hebiah Fourth | Urban Venture Real Estate Development L.L.C | 67.6% | 1 Apr 2026 | 7 mo past | 187 |
| Hills Park | Hadaeq Sheikh Mohammed Bin Rashid | Dubai Hills Estate L.L.C | — | 30 Apr 2026 | Completed | 450 |
| Parkwood Residences | Al Barsha South Fourth | Arabian Gulf Properties | 57% | 30 Apr 2026 | 6 mo past | 174 |
| Aura Elite | Nadd Hessa | Aura Infinite Real Estate Development L.L.C | 44.3% | 30 Apr 2026 | 6 mo past | 86 |
| Imperial Residence | Me'Aisem First | Imperial 55 Real Estate Development L.L.C | 43% | 30 Apr 2026 | 6 mo past | 137 |
| Allegro Residences | Palm Deira | Mill Hill Riviera Development L.L.C | 84.5% | 7 Apr 2026 | 6 mo past | 60 |
| Jomana | Um Suqaim Third | Jumeirah Hills Development L.L.C | — | 30 Apr 2026 | Completed | 326 |
| Dalmore Tower | Wadi Al Safa 5 | Dalmore Real Estate Development L.L.C | 95.1% | 23 Apr 2026 | 6 mo past | 120 |
| Mackerel Tower | Palm Deira | Tarrad Development L.L.C | 56.6% | 1 Apr 2026 | 7 mo past | 62 |
| Samana Waves | Al Barsha South Fourth | Samana Si Holding Limited Dubai Branch | 90.6% | 15 Apr 2026 | 6 mo past | 197 |
| ROVE HOME RESIDENCES by IRTH | Burj Khalifa | Irth Development L.L.C | 62.7% | 30 Apr 2026 | 6 mo past | 349 |
| Nad Al Sheba Gardens Phase 3 | Nad Al Shiba First | Al Qudra Estates L.L.C | 97% | 19 Apr 2026 | 6 mo past | 235 |
| Almaan 101 | Al Barsha South Fourth | M N Vision Real Estate Development L.L.C | 50.9% | 13 Apr 2026 | 6 mo past | 102 |
| Samana Skyros | Al Barshaa South Third | Samana Signature Real Estate Developments L.L.C | 71.3% | 30 Apr 2026 | 6 mo past | 441 |
| Samana Mykonos Signature | Al Barshaa South Third | Samana International Real Estate Development L.L.C | 86% | 30 Apr 2026 | 6 mo past | 300 |
| Samana Mykonos | Al Hebiah Second | Samana International Real Estate Development L.L.C | 91.1% | 30 Apr 2026 | 6 mo past | 198 |
| Elysee Heights | Al Barsha South Fourth | Pantheon Elysee Real Estate Development L.L.C | 81.3% | 14 Apr 2026 | 6 mo past | 193 |
| Eywa Dubai | Business Bay | Rvl Real Estate L.L.C | 65.7% | 1 Apr 2026 | 7 mo past | 53 |
| The Woodland Residences | Wadi Al Safa 3 | A M I S Real Estate Development L.L.C | 75.4% | 8 Apr 2026 | 6 mo past | 30 |
| The Veranda Collection 2 | Al Barsha South Fourth | Pacifique Global Properties L.L.C | — | 7 Apr 2026 | Completed | 13 |
| W1 | Jabal Ali First | Malina W1 Real Estate Development L.L.C | 70.2% | 30 Apr 2026 | 6 mo past | 83 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology