DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: March 2027 65 projects · 62 not yet completed · 15,160 units DLD projects register as of 1 November 2026 · sales to 5 November 2026

March 2027 has not started yet. 65 projects in the Dubai Land Department projects register have their DLD end date in March 2027 (register of 1 November 2026). DLD can change an end date before it comes. By DLD status: Not started 2 · Under construction 57 · Pending 3 · Completed 3. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

57 projects
0–25%: 2425–50%: 1450–75%: 1175–100%: 8

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

65 projects
Not started2
Under construction57
Pending3
Completed before March 20273

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

DLD end date in March 2027 (65) 65 projects, by sales over 24 months

DLD end date in March 2027 (65)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Binghatti VintageWadi Al Safa 3Binghatti Developers FZE 0% 31 Mar 2027 4 mo to go 1,572
SAAS HillsAl Barshaa South SecondSaas Properties L.L.C - Dubai Branch 13% 31 Mar 2027 4 mo to go 859
Ashley HillsAl Barshaa South ThirdTownx Real Estate Development L.L.C 74.1% 31 Mar 2027 4 mo to go 616
One ResidenceBurj KhalifaGinco Properties L.L.C 6.3% 31 Mar 2027 4 mo to go 458
City View Dubai Hills ResidencesHadaeq Sheikh Mohammed Bin RashidCity View Real Estate Development L.L.C 38.8% 31 Mar 2027 4 mo to go 239
MBL SignatureAl Thanyah FifthMag 10 Property Development DMCC 60.1% 31 Mar 2027 4 mo to go 463
11 Hills ParkAl Barshaa South SecondTownx Real Estate Development L.L.C 80.1% 31 Mar 2027 4 mo to go 571
Azizi Milan 51Wadi Al Safa 4Azizi Developments L.L.C 0% 26 Mar 2027 4 mo to go 579
Jade TowerWadi Al Safa 3Tiger Properties 11% 31 Mar 2027 4 mo to go 436
Verdania 1Wadi Al Safa 5OBJ1 Real Estate Development L.L.C 16.7% 30 Mar 2027 4 mo to go 208
Maison Elysee IAl Barsha South FourthPantheon Elysee Real Estate Development L.L.C 21.1% 31 Mar 2027 4 mo to go 355
Samana Barari ViewsWadi Al Safa 3Samana International Real Estate Development L.L.C 26.8% 31 Mar 2027 4 mo to go 669
Luminar Tower 3Al Barsha South FifthOBJ1 Real Estate Development L.L.C 13.6% 30 Mar 2027 4 mo to go 188
Park Views Residences BAl KifafPark 1 L.L.C 98.8% 1 Mar 2027 4 mo to go 476
Azurline Residences by MAAS DevelopersAl Barsha South FourthM A A S Developers L.L.C 56.5% 31 Mar 2027 4 mo to go 205
The Valley - RivanaAl Yufrah 1Emaar Development P.J.S.C. 95.2% 31 Mar 2027 4 mo to go 486
Damac Hills - Golf Greens 1Al Hebiah ThirdDamac Crescent Properties 40.5% 30 Mar 2027 4 mo to go 479
Living Legends Phase 4Wadi Al Safa 3Amer Alghurair Real Estate Development CO. L.L.C 62.1% 31 Mar 2027 4 mo to go 554
Vistara HouseJabal Ali FirstObject One Real Estate Development L.L.C 7% 30 Mar 2027 4 mo to go 141
Bluewaters BayMarsa DubaiDhre 2 Bts L.L.C 37% 1 Mar 2027 4 mo to go 679
Canal Heights 2Business BayResta Real Estate Development L.L.C 36.4% 31 Mar 2027 4 mo to go 505
Ayamore ResidencePalm DeiraAyat Real Estate Development L.L.C 67.6% 7 Mar 2027 4 mo to go 94
Azizi Riviera 50Al MerkadhAzizi Developments L.L.C 60.9% 13 Mar 2027 4 mo to go 234
Blossom 76 by TranquilAl Barsha South FourthTranquil Infra Developers L.L.C 40% 26 Mar 2027 4 mo to go 113
All Seasons ResidenceAl Hebiah FourthAbdulrahim Alzarooni Real Estate Development L.L.C 8.1% 30 Mar 2027 4 mo to go 286
Ocean Pearl 2 By SDPalm DeiraSamana Star Real Estate Development L.L.C 23.3% 31 Mar 2027 4 mo to go 96
Azizi Riviera 49Al MerkadhAzizi Developments L.L.C 54.4% 13 Mar 2027 4 mo to go 234
Khk 31Wadi Al Safa 5Khk Realestate Development L.L.C 25.8% 22 Mar 2027 4 mo to go 160
Golf GrandHadaeq Sheikh Mohammed Bin RashidDubai Hills Estate L.L.C — 31 Mar 2027 Completed 329
Coventry GardensWadi Al Safa 5G F S Real Estate L.L.C 1.2% 14 Mar 2027 4 mo to go 97
Sunset Bay Three By ImtiazPalm DeiraImtiaz Sunset Real Estate Development L.L.C 60% 20 Mar 2027 4 mo to go 63
Canal Crown 2Business BayOne Quantem Real Estate Development L.L.C 32.5% 31 Mar 2027 4 mo to go 351
Verdania 2Wadi Al Safa 5OBJ1 Real Estate Development L.L.C 9% 30 Mar 2027 4 mo to go 108
Stamn YuniAl SatwaStamn Real Estate Development L.L.C 11.6% 18 Mar 2027 4 mo to go 88
Avion ResidenceMadinat Al MataarSky View Development L.L.C 35.8% 31 Mar 2027 4 mo to go 66
Woodland TerracesWadi Al Safa 3A M I S Real Estate Development L.L.C 10.3% 30 Mar 2027 4 mo to go 78
Silviana Park LivingAl Barsha South FifthOBJ1 Real Estate Development L.L.C 2.7% 30 Mar 2027 4 mo to go 83
Isolana ResidencesPalm DeiraHayaat Ikhlaq Developments L.L.C 5.5% 20 Mar 2027 4 mo to go 73
ِِAzizi Riviera 60Al MerkadhAzizi Developments L.L.C 97.1% 13 Mar 2027 4 mo to go 87
Ag 7EVENWadi Al Safa 5Ag Properties L.L.C 93.7% 31 Mar 2027 4 mo to go 234
Ashwood Residences by Skyland Horizons Real Estate DevelopmentAl Barsha South FifthSkyland Horizons Real Estate Development L.L.C 14.6% 31 Mar 2027 4 mo to go 153
Como ResidencesPalm JumeirahThe Palm - Jumeirah CO. (L.L.C) 24.8% 27 Mar 2027 4 mo to go 81
Repose ResidenceJabal Ali FirstSaion Real Estate Development L.L.C 37.5% 31 Mar 2027 4 mo to go 80
Damac Lagoons - Lagoon Views 10Al Hebiah FifthIsland Oasis Properties 47.4% 31 Mar 2027 4 mo to go 108
The Orchard Place - Tower CAl Barsha South FourthPeak Summit Real Estate Development L.L.C 13% 31 Mar 2027 4 mo to go 196
Zyra Vista ResidencesWarsan FourthLaraix Developers L.L.C 2.1% 31 Mar 2027 4 mo to go 51
Xenia ResidenceAl Barsha South FourthN Y X Real Estate Development L.L.C 51.6% 1 Mar 2027 4 mo to go 73
Kingdom GateJabal Ali FirstKingdom Gate Property Development L.L.C 55.5% 31 Mar 2027 4 mo to go 86
Sikanta ResidencesMadinat Al MataarSikanta Real Estate Development L.L.C 13.9% 31 Mar 2027 4 mo to go 64
Damac Hills (2) - Park Greens 1Madinat Hind 4Front Line Investment Management L.L.C 21.7% 30 Mar 2027 4 mo to go —
Purvanchal Triana ResidencesAl SatwaPurvanchal Real Estate Developers L.L.C 26.4% 1 Mar 2027 4 mo to go 72
Amali IslandWorld IslandsAmali Properties L.L.C 16.4% 31 Mar 2027 4 mo to go 24
Damac Lagoons - Lagoon Views 9Al Hebiah FifthIsland Oasis Properties 47.3% 31 Mar 2027 4 mo to go 108
Bulgari Lighthouse DubaiIsland 2Dhre 2 Bts L.L.C 80% 27 Mar 2027 4 mo to go 31
Coral Isle ResidencesPalm DeiraGrovy Homes Real Estate Development L.L.C 7.2% 31 Mar 2027 4 mo to go 68
Azizi Riviera 55Al MerkadhAzizi Developments L.L.C — 13 Mar 2027 Completed 124
Aptos ResidenzaAl Barsha South FourthVantage Capital Real Estate Development L.L.C 0% 14 Mar 2027 4 mo to go 148
Amaya ResidencesJabal Ali FirstPolygon Real Estate Development L.L.C 3.7% 1 Mar 2027 4 mo to go 78
Azizi Riviera 53Al MerkadhAzizi Developments L.L.C 63.2% 13 Mar 2027 4 mo to go 225
Azizi Riviera 56Al MerkadhAzizi Developments L.L.C — 13 Mar 2027 Completed 87
Azizi Riviera 62Al MerkadhAzizi Developments L.L.C 90.8% 13 Mar 2027 4 mo to go 112
Project 3733, Madinat Al MataarMadinat Al MataarSouth Living Real Estate Development L.L.C 0% 31 Mar 2027 4 mo to go —
Marwa ViewsAl Barsha South FifthNew World Developments L.L.C 40.1% 31 Mar 2027 4 mo to go 70
Project 3806, Madinat Al MataarMadinat Al MataarNusuk Real Estate Development L.L.C 0% 15 Mar 2027 4 mo to go —
24HCUm Hurair SecondO&F Dhcc Real Estate Development L.L.C 80% 30 Mar 2027 4 mo to go 49

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Marked completed by DLD in March 2027 (0)

DLD marked no project completed in March 2027.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology