Damac Crescent Properties داماك كريسنت للعقارات (ش.ذ.م.م) 52 projects in the DLD register: 43 completed, 8 under construction, 1 not started or pending. 1 of the 6 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 52- Median time from start to completion: 48 months (43 completed projects).
- 6,466 units and villas in completed projects; 2,976 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 43 completed projects with both dates. In 31 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 6 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Damac Crescent Properties Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Damac District4064 · Al Hebiah Third · Damac Hills | Under construction | 4.1% | Mar 2029 28 mo to go | 1,139 | 737 |
| Damac Hills - Golf Greens 22780 · Al Hebiah Third · Damac Hills | Under construction | 45.2% | — | 606 | 348 |
| Damac Hills - Carson1620 · Al Hebiah Third · Damac Hills | Completed | 100% | Mar 2022 Completed | 1,575 | 331 |
| Damac Hills - Golf Promenade1504 · Al Hebiah Third · Damac Hills | Completed | 100% | Sep 2019 Completed | 740 | 237 |
| Damac Hills - Golf Vita1932 · Al Hebiah Third · Damac Hills | Completed | 100% | Mar 2021 Completed | 510 | 121 |
| Damac Hills - Golf Greens 12779 · Al Hebiah Third · Damac Hills | Under construction | 40.5% | Mar 2027 4 mo to go | 479 | 117 |
| Damac Hills - Loreto1508 · Al Hebiah Third · Damac Hills | Completed | 100% | Dec 2017 Completed | 504 | 117 |
| Damac Hills - Golf Gate2358 · Al Hebiah Third · Damac Hills | Completed | 100% | Dec 2024 Completed | 351 | 116 |
| Damac HILLS-PARK Residences 11938 · Al Hebiah Third · Damac Hills | Completed | 100% | Feb 2025 Completed | 129 | 109 |
| Damac Hills - Artesia1523 · Al Hebiah Third · Damac Hills | Completed | 100% | Jan 2021 Completed | 1,246 | 102 |
| Damac Hills - Ivory3706 · Al Hebiah Third · Damac Hills | Under construction | 0.6% | Jun 2028 19 mo to go | — | 98 |
| Damac Hills - Golf Gate 22698 · Al Hebiah Third · Damac Hills | Under construction | 80.4% | — | 464 | 84 |
| Damac HILLS-PARK Residences 41930 · Al Hebiah Third · Damac Hills | Completed | 100% | Jan 2023 Completed | 29 | 84 |
| Damac HILLS-BEL Air2236 · Al Hebiah Third · Damac Hills | Completed | 100% | Feb 2024 Completed | — | 84 |
| Damac Hills - Silver Springs 32228 · Al Hebiah Third · Damac Hills | Completed | 100% | Jan 2024 Completed | — | 70 |
| Damac Hills - Golf Horizon1363 · Al Hebiah Third · Damac Hills | Completed | 100% | Dec 2015 Completed | 159 | 38 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 9, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.