Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Damac World Real Estate L.L.C داماك ورلد ريل استيت ش.ذ.م.م DLD developer no. 1095 · Registered with DLD on 3 August 2015 · Licence 713606 3 projects in the DLD register: 3 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026

Projects
3
in the DLD register
Completed
3
1,711 units delivered
Not yet completed
0
0 units in the pipeline

Delivery record

Projects: 3
Completed 3
  • Median time from start to completion: 52 months (3 completed projects).
  • 1,711 units and villas in completed projects; 0 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Damac World Real Estate L.L.C Most registered sales in the last 24 months first

Projects by Damac World Real Estate L.L.C
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Reva Residences2018 · Business Bay Completed 100% Jun 2022 Completed 604 110
Merano Tower1680 · Business Bay Completed 100% Feb 2020 Completed 581 101
Vera Tower1786 · Business Bay Completed 100% Mar 2022 Completed 526 75

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.