Damac Elite Investment CO. L.L.C شركة داماك ايليت للاستثمار ذ.م.م 20 projects in the DLD register: 0 completed, 18 under construction, 2 not started or pending. 0 of the 18 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 20- 0 units and villas in completed projects; 4,035 in projects not yet completed.
- Under construction past their DLD end date: 0 of 18 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Damac Elite Investment CO. L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Damac Islands - Maldives 23437 · Al Yelayiss 1 | Under construction | 14.1% | Dec 2028 25 mo to go | — | 3 |
| Damac Islands - Bora Bora 33500 · Al Yelayiss 1 | Under construction | 4.2% | Dec 2028 25 mo to go | — | 2 |
| Damac Islands - Maldives 33438 · Al Yelayiss 1 | Under construction | 12.1% | Dec 2028 25 mo to go | — | 2 |
| Damac Islands - Bali 23490 · Al Yelayiss 1 | Under construction | 5.7% | Dec 2028 25 mo to go | — | 1 |
| DAMAC Sun City3268 · Al Yelayiss 1 | Under construction | 36.5% | Mar 2028 16 mo to go | — | 0 |
| DAMAC Islands - Bora Bora 23499 · Al Yelayiss 1 | Under construction | 2.5% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Maldives 43501 · Al Yelayiss 1 | Under construction | 2.9% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Bali 13475 · Al Yelayiss 1 | Under construction | 7% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Bora Bora 43476 · Al Yelayiss 1 | Under construction | 2.1% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Fiji 23507 · Al Yelayiss 1 | Under construction | 2.2% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Fiji 13505 · Al Yelayiss 1 | Under construction | 1.7% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Maldives 53502 · Al Yelayiss 1 | Under construction | 2.6% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Bora Bora 13498 · Al Yelayiss 1 | Under construction | 6.8% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Maldives 13388 · Al Yelayiss 1 | Under construction | 6.6% | Dec 2028 25 mo to go | — | 0 |
| DAMAC Islands - Bali 43697 · Al Yelayiss 1 | Under construction | 2.1% | Jun 2029 31 mo to go | — | 0 |
| DAMAC Islands - Bali 33693 · Al Yelayiss 1 | Under construction | 2.8% | Jun 2029 31 mo to go | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 20, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.