Dubai off-plan handovers: June 2026 18 marked completed by DLD · 36 with the DLD end date in the month DLD projects register as of 1 November 2026 · sales to 5 November 2026
In June 2026, DLD marked 18 projects completed. 36 other projects had their DLD end date in the month; the list shows their DLD status in the register of 1 November 2026. By DLD status: Under construction 30 · Conditionally activating 1 · Completed 5. These are the DLD end dates registered for each project, not handover forecasts.
Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.
% built, under construction
30 projects| % completed | Projects |
|---|---|
| 0–25% | 4 |
| 25–50% | 4 |
| 50–75% | 10 |
| 75–100% | 12 |
Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.
By DLD status
36 projectsStatus as recorded by DLD. Source: DLD projects register, export of 1 November 2026.
Marked completed by DLD in June 2026 (18)
| Project | Area | Developer | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|---|
| Peninsula Four | Business Bay | Select Global Development L.L.C | 1 Feb 2026 | 25 Jun 2026 | 4 mo after | 1,038 |
| Damac Lagoons - Malta (1) | Al Hebiah Fifth | Island Oasis Properties | 29 Sep 2025 | 19 Jun 2026 | 8 mo after | — |
| Jannat | Me'Aisem First | Deyaar Development (P.J.S.C) | — | 4 Jun 2026 | — | 362 |
| Tulip Oasis 10 | Wadi Al Safa 3 | A M E Real Estate Development L.L.C | 30 Jun 2026 | 29 Jun 2026 | 1 d before | 130 |
| Al Serh Residences 11 By Asak Real Estate Development | Al Barsha South Fourth | Asak Real Estate Development L.L.C | 28 Feb 2025 | 4 Jun 2026 | 15 mo after | 105 |
| ELEVATE by Prescott | Al Barshaa South Third | Prescott Real Estate Development L.L.C | 31 Mar 2025 | 4 Jun 2026 | 14 mo after | 223 |
| Azizi Central | Jabal Ali First | Azizi Developments L.L.C | — | 9 Jun 2026 | — | 97 |
| Golf Heights | Al Thanyah Third | Emaar Properties (P.J.S.C) | 31 Dec 2026 | 18 Jun 2026 | 6 mo before | 281 |
| Golf Residences by Fortimo | Hadaeq Sheikh Mohammed Bin Rashid | Fortimo Real Estate Development L.L.C | 15 Dec 2026 | 7 Jun 2026 | 6 mo before | 200 |
| Vyb | Business Bay | Ginco Properties L.L.C | 28 Feb 2026 | 23 Jun 2026 | 3 mo after | 181 |
| Erin | Al Wasl | Citywalk Residential 1 L.L.C | 10 Aug 2026 | 12 Jun 2026 | 1 mo before | 200 |
| Beverly Residence 2 | Al Barsha South Fourth | H M B Homes Real Estate Development | — | 4 Jun 2026 | — | 108 |
| Damac Hills (2) - Verona | Madinat Hind 4 | Front Line Investment Management L.L.C | — | 21 Jun 2026 | — | — |
| Alba | Wadi Al Safa 2 | Amaya Properties L.L.C | — | 18 Jun 2026 | — | 22 |
| Sunrise Living at Jumeirah Park | Al Thanyah Fifth | Sunrise Valley L.L.C | 15 Jul 2025 | 25 Jun 2026 | 11 mo after | — |
| Eome | Palm Jumeirah | Blue Haven Real Estate Development L.L.C | 1 Nov 2024 | 12 Jun 2026 | 19 mo after | 26 |
| Samana Miami | Al Barsha South Fourth | Samana Si Holding Limited Dubai Branch | 1 Dec 2024 | 3 Jun 2026 | 18 mo after | 93 |
| Talia Residences | Jabal Ali First | Deyaar Development (P.J.S.C) | 30 Apr 2025 | 1 Jun 2026 | 13 mo after | 160 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end date in June 2026: DLD status in the register of 1 November 2026 (36) 36 projects, by sales over 24 months
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology