DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers: August 2027 27 projects · 27 not yet completed · 8,676 units DLD projects register as of 1 November 2026 · sales to 5 November 2026

August 2027 has not started yet. 27 projects in the Dubai Land Department projects register have their DLD end date in August 2027 (register of 1 November 2026). DLD can change an end date before it comes. By DLD status: Not started 4 · Under construction 19 · Pending 4. These are the DLD end dates registered for each project, not handover forecasts.

Projects with a DLD end date in each month. “Past”: under construction and a month or more past that date.

% built, under construction

19 projects
0–25%: 1225–50%: 650–75%: 175–100%: 0

Latest register reading of % built. Source: DLD projects register, export of 1 November 2026.

By DLD status

27 projects
Not started4
Under construction19
Pending4

Status as recorded by DLD. Source: DLD projects register, export of 1 November 2026.

DLD end date in August 2027 (27) 27 projects, by sales over 24 months

DLD end date in August 2027 (27)
ProjectArea Developer Built DLD end dateTo DLD end date Units
Maybach SixNad Al Shiba FirstBinghatti Developers FZE 0% 31 Aug 2027 9 mo to go 1,878
Damac Hills (2) - Violet 4Madinat Hind 4Front Line Investment Management L.L.C 14.2% 30 Aug 2027 9 mo to go —
Azizi Venice 11Madinat Al MataarAzizi Developments L.L.C 25.9% 30 Aug 2027 9 mo to go 1,094
Legado By PrescottAl Barsha South FourthPrescott Real Estate Development L.L.C 23.3% 31 Aug 2027 9 mo to go 343
Onda By KascoBusiness BayKasco Real Estate Development L.L.C 61.1% 31 Aug 2027 9 mo to go 352
Rove Home Marasi DriveBusiness BayIrth Signature Development L.L.C 10% 31 Aug 2027 9 mo to go 811
Maybach Ultimate LuxuryNad Al Shiba FirstBinghatti Developers FZE 0% 31 Aug 2027 9 mo to go 1,233
MontageAl JadafKey Mavens Montage Real Estate Development L.L.C 40% 31 Aug 2027 9 mo to go 257
Floarea GrandeAl Barshaa South ThirdMashriq Elite Real Estate Development L.L.C 48.2% 14 Aug 2027 9 mo to go 222
Time 3Wadi Al Safa 5Time Properties 47.1% 1 Aug 2027 9 mo to go 288
Samana Park MeadowsWadi Al Safa 5Samana International Real Estate Development L.L.C 38% 31 Aug 2027 9 mo to go 221
Solara Tower DubaiBurj KhalifaS O L Properties Development L.L.C 20.7% 15 Aug 2027 9 mo to go 231
The ElysianAl SatwaNew M F O U R Real Estate Development L.L.C 4.5% 31 Aug 2027 9 mo to go 84
Azha Downtown ResidencesBurj KhalifaAzha Downtown Residences L.L.C 27% 31 Aug 2027 9 mo to go 73
MIORAH By ZoyaMadinat Al MataarZoya One Real Estate Developments L.L.C 16.1% 31 Aug 2027 9 mo to go 60
Nautis ResidencesPalm DeiraStamn Real Estate Development L.L.C 0.9% 30 Aug 2027 9 mo to go 63
Astra ResidencesMadinat Al MataarDugasta Properties Development L.L.C 15.3% 31 Aug 2027 9 mo to go 108
Listone ResidenceAl Warsan FirstLion Stone Properties L.L.C 0% 31 Aug 2027 9 mo to go 312
Sea Coral By Next RealtyPalm DeiraNext Realty Real Estate L.L.C 10.7% 31 Aug 2027 9 mo to go 80
Symphony by ChaimaaWadi Al Safa 3Deval Real Estate Development L.L.C 0% 31 Aug 2027 9 mo to go 71
Azizi AbrahamJabal Ali Industrial SecondAzizi Developments L.L.C 2% 4 Aug 2027 9 mo to go 420
Lincoln Star Residence IIMadinat Al MataarLincoln Rise Real Estate Development L.L.C 5.3% 31 Aug 2027 9 mo to go 56
Ayana GardensNad Al Shiba FirstTuscany Real Estate Development L.L.C 0% 31 Aug 2027 9 mo to go 66
Orbit Residences by JewelAl Warsan FirstJewel DEVELOPMENT&REAL Estate Investment L.L.C 0% 1 Aug 2027 9 mo to go 105
The LXAl Barshaa South ThirdMulk Properties L.L.C 4.9% 30 Aug 2027 9 mo to go 74
Azure Park ResidencesAl Barshaa South SecondAzure Premier Real Estate Development L.L.C 0% 7 Aug 2027 9 mo to go 174
Project 4569, Madinat Al MataarMadinat Al MataarBuyut Aljiwar Real Estate Development LLC S.O.C 0% 15 Aug 2027 9 mo to go —

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Marked completed by DLD in August 2027 (0)

DLD marked no project completed in August 2027.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology