S O L Properties Development L.L.C اس او ال للتطوير العقاري ش.ذ.م.م 11 projects in the DLD register: 5 completed, 3 under construction, 3 not started or pending. 0 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 11- Median time from start to completion: 26 months (5 completed projects).
- 999 units and villas in completed projects; 1,538 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 3 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by S O L Properties Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Sol Levante3642 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 7.2% | Sep 2028 22 mo to go | 674 | 409 |
| Solara Tower Dubai2928 · Burj Khalifa · DownTown Dubai | Under construction | 20.7% | Aug 2027 9 mo to go | 231 | 165 |
| Sol Luxe4016 · Trade Center First | Under construction | 2% | Mar 2029 28 mo to go | 370 | 76 |
| Sol Bay630 · Business Bay | Completed | 100% | Jan 2015 Completed | 325 | 52 |
| Sun Point Dubai2213 · Me'Aisem First · International Media Production Zone | Completed | 100% | Mar 2022 Completed | 255 | 18 |
| Iris Amber124 · Al Jadaf · Jaddaf Waterfront | Completed | 100% | Sep 2016 Completed | 95 | 15 |
| Bloomingdale1493 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | May 2015 Completed | — | 5 |
| Sol Terra Casa I4391 · Al Barsha South Fourth · Jumeirah Village Circle | Not started | 0% | Jun 2028 19 mo to go | 13 | 2 |
| Sol Terra Casa Ii4135 · Al Barsha South Fourth · Jumeirah Village Circle | Not started | 0% | Jun 2028 19 mo to go | 11 | 0 |
| Sol Terra Gardens4154 · Al Barsha South Fourth · Jumeirah Village Circle | Not started | 0% | May 2029 30 mo to go | 239 | 0 |
| Sol Avenue629 · Business Bay | Completed | 100% | Feb 2017 Completed | 324 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 6, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.