DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1493Completed

Bloomingdale بلومنجديل Al Hebiah Fourth · Dubai Sports City by S O L Properties Development L.L.CAll phases of Dubai Sports City Completed 31 May 2015 (DLD) DLD end date Nov 2015 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
May 2015
DLD end date Nov 2015
Build time
27 months
Mar 2013 → May 2015
Latest sales
—
Fewer than 5 recent sales
Developer
11 projects
5 completed · 999 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 27 January 2016 (inspections: 3).
Every DLD inspection and every change in the register %, newest first
Date % built Source
27 January 2016 100% DLD inspection
5 October 2015 97.3% DLD inspection
23 September 2014 57.8% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
33 monthsActual build
27 months
Start date
2 March 2013
DLD end date
30 November 2015
Completion date
31 May 2015
Completion vs DLD end date
5 months before

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

47 of 72 buildings

Buildings on the project’s plots: 72, on construction permits: 72, as Dubai Municipality lists them.

Furthest stage reached: Final works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
72
72 on construction permits
Permit status
Closed
217984
Issued
11 December 2013
Work start
1 February 2014
Completion
10 September 2015
Consultant · contractor
DIAR CONSULT L.L.C · BHATIA GENERAL CONTRACTING CO.(L.L.C.)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Finishes25
Final works47

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1493
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Development Authority (DDA)
Master project
Dubai Sports City
DLD area
Al Hebiah Fourth
Units · villas
0 · 0
Start → DLD end
Mar 2013 → Nov 2015
Registered units4 bed 36 · 5+ bed 36; sizes 3,368–3,439 sqft

Homes: villas 72.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Freehold 72 Residential Townhouses located in Dubai Sport City. Townhouse is designated to have (Ground + First + Roof) with RCC structure and complete finishing (internal and external)

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over villas and townhouses, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q3

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Hebiah Fourth, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 7; registered amount AED 20.6M.

Since the first registration in 2015-Q3: 100 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.02 AED/sqft a year
Dubai Sports City: median of 43 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 3 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
20 July 2026readyVilla 2,147 3,500,000 1,630
20 April 2026readyVilla 2,901 4,800,000 1,655
26 January 2026readyVilla 2,147 4,550,000 2,119
20 October 2025readyVilla 2,156 4,500,000 2,087
2 May 2025readyVilla 2,901 4,600,000 1,586
31 October 2024readyVilla 2,147 4,000,000 1,863
24 October 2024readyVilla 2,147 4,000,000 1,863
21 October 2024readyVilla 2,173 4,150,000 1,910
4 October 2024readyVilla 2,147 4,000,000 1,863
3 October 2024readyVilla 2,152 4,000,000 1,859

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Hebiah Fourth · Dubai Municipality community

Carrefour City Centre Meaisem · 860 mCity Centre Meaisem · 930 mMe'aisem City Center · 930 mSpinneys · 1.1 kmFarfar · 1.1 kmAwadia Grocery · 1.2 kmPark · 1.2 kmHalfa · 1.3 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Approximate project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationJumeirah Golf Estates Metro Station · Red Metro line · 4.9 km
MallCity Centre Meaisem · 930 m
SupermarketCarrefour City Centre Meaisem · 860 m
HospitalMediclinic Springs · 4 km
SchoolVictory Heights Primary School · 1.7 km
ParkFarfar · 1.1 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 64, with 18,586 units and villas.

2013: 1652022: 3942025: 7072026: 4,0622027: 4,5872028: 4,8642029: 439No end date: 3,368

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Hebiah Fourth: 35

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Haven 76.1% Mar 2026 1,489 485
Azizi Grand 82.1% Feb 2025 1,351 290
ASPIRZ By Danube 5.1% Dec 2028 2,216 267
Verde By Vision 12% Sep 2027 1,388 236
The Community - Sports Arena 22.4% Oct 2027 1,320 217
Hadley Heights 2 0% Oct 2027 1,306 193
Sportz By Danube 80.2% Mar 2026 1,594 146
Mag 777 67.4% Jan 2026 — 142
Urban Park Residences 67.6% Apr 2026 1,519 121
Antalya By Karma 0.1% Sep 2028 1,491 108
Golf Residences By Prestige One 35.7% Feb 2028 1,258 104
Vega 20.3% May 2027 1,519 103

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Hebiah Fourth

Developer in DLD data S O L Properties Development L.L.C · DLD developer no. 999

Projects registered
11
5 completed · 3 under construction · 3 not started
Units delivered
999
1,538 in the pipeline
Median build time
26 months
completed projects measured: 5
Past the DLD end date
0
of 3 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai Sports City

DLD lists 92 projects in the master project Dubai Sports City.

Champions Tower2Under construction · 78.2% · Oct 2017
Eden GardenUnder construction · 96% · Aug 2022
Mars ResidencesUnder construction · 79.9% · Mar 2024
Azizi GrandUnder construction · 82.1% · Feb 2025
Mag 777Under construction · 67.4% · Jan 2026
Sportz By DanubeUnder construction · 80.2% · Mar 2026
Binghatti HavenUnder construction · 76.1% · Mar 2026
Urban Park ResidencesUnder construction · 67.6% · Apr 2026
Lime Light Twin TowersUnder construction · 71.1% · Jun 2026
All Seasons ResidenceUnder construction · 8.1% · Mar 2027
VegaUnder construction · 20.3% · May 2027
Oasis Tower 2Under construction · 73.9% · Jun 2027

Questions about Bloomingdale

When was Bloomingdale completed?

Bloomingdale is recorded as completed on 31 May 2015 (DLD register of 1 November 2026).

Who is the developer of Bloomingdale?

S O L Properties Development L.L.C, as registered with DLD.

What is the DLD project number of Bloomingdale?

1493.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error