Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2964Pending66 units

Ayana Gardens ايانا جاردنز Nad Al Shiba First · Meydan Racecourse Community by Tuscany Real Estate Development L.L.CAll phases of Meydan Racecourse Community DLD status: Pending (DLD register as of 1 November 2026) DLD end date Aug 2027 9 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Sep 2025
DLD end date Aug 2027
Latest sales
—
Fewer than 5 recent sales
Developer
1 project
0 completed · 0 units delivered

Completion

DLD status: Pending. 0% built, DLD end date 31 August 2027. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 31 August 2027Pending
12 May 2024 0% —Pending

Source: DLD projects register, export of 1 November 2026.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Site works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Open
412959
Issued
13 February 2024
Work start
1 March 2024
Consultant · contractor
NATIONAL ENGINEERING BUREAU · NEW SYSTEM ENGINEERING (L L C)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Site works1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
2964
Escrow agent
Sharjah Islamic Bank
Zoning authority
Dubai Municipality
Master project
Meydan Racecourse Community
DLD area
Nad Al Shiba First
Units · villas
66 · 0
Start → DLD end
Sep 2025 → Aug 2027
Registered units1 bed 36 · 2 bed 28; sizes 933–1,601 sqft

Also registered: shops and showrooms 2.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: G + 5F + R

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationNadd Al Shiba First · Dubai Municipality community

Day by 12 Grocery · 640 mPark · 730 mPark · 740 mPark · 740 mMOUNT WAY MINIMART · 890 mBradosti Trading · 1 kmNorth London Collegiate School · 1.3 kmHartland International School · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationBurj Khalifa/ Dubai Mall Metro Station · Red Metro line · 5.5 km
MallSobha Mall (Under Construction) · 1.6 km
SupermarketDay by 12 Grocery · 640 m
HospitalHospital · 2 km
SchoolNorth London Collegiate School · 1.3 km
ParkPark · 730 m
BeachBeach · 3 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 20, with 5,803 units and villas.

2018: 362024: 02025: 5082027: 3,3862028: 1,4532029: 78No end date: 342

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Nadd Al Shiba First: 35

Open projects in the same DLD area with a DLD end year from 2026 to 2028, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Maybach Six 0% Aug 2027 3,521 1,099
Maybach Ultimate Luxury 0% Aug 2027 3,653 276
Tonino Lamborghini Residences 60% Dec 2026 — 245
Project Maybach 0% Jun 2027 3,421 214
Nad Al Sheba Gardens Phase 10 0.4% Oct 2028 — 204
Nad Al Sheba Gardens Phase 8 & 9 0.7% Oct 2028 1,862 202
Nad Al Sheba Gardens Phase 7 4% Feb 2028 2,603 155
Emerge Residences 21.1% Nov 2027 2,245 47
Nad Al Sheba Gardens Phase 3 97% Apr 2026 2,085 39
Sukoon by Nuri 46.8% Dec 2026 1,885 36
Woodland Crest 1.4% Jun 2027 2,239 33
La Vue Parc 15.4% Sep 2027 2,267 25

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Nadd Al Shiba First

Developer in DLD data Tuscany Real Estate Development L.L.C · DLD developer no. 1446

Projects registered
1
0 completed · 0 under construction · 1 not started
Units delivered
0
66 in the pipeline

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error