DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 3117Completed44 units

Trafford Residence ترافورد ريزيدنس Madinat Al Mataar · Dubai South Residential District by Deviate For Real Estate Development L.L.CAll phases of Dubai South Residential District Completed 27 August 2026 (DLD) DLD end date Dec 2025 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Aug 2026
DLD end date Dec 2025
Build time
27 months
Jun 2024 → Aug 2026
Latest sales
1,169 AED/sqft
7 sales
Developer
2 projects
1 completed · 44 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 1). Latest DLD inspection: 100% built on 24 August 2026 (inspections: 4).
Every DLD inspection and every change in the register %, newest first
Date % built Source
24 August 2026 100% DLD inspection
10 August 2026 95.1% DLD inspection
24 June 2025 54.8% DLD inspection
6 June 2024 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
19 monthsActual build
27 months
Start date
1 June 2024
DLD end date
31 December 2025
Completion date
27 August 2026
Completion vs DLD end date
7 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
3117
Escrow agent
Emirates Islamic Bank P.J.S.C.
Zoning authority
Dubai South
Master project
Dubai South Residential District
DLD area
Madinat Al Mataar
Units · villas
44 · 0
Start → DLD end
Jun 2024 → Dec 2025
Registered units1 bed 12 · 2 bed 32; sizes 870–1,106 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Ground + 4 Floors + Roof.The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,153 AED/sqft
Median of 18 off-plan sales in the 90 days from the first one (Jan 2025)
Latest registered sales
1,169 AED/sqft
Median of 7 home sales in the last 12 months, ready and off-plan
Change
-0.8%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2025-Q1 to 2026-Q2: +2.7%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
2 BR 1,179 (6) 1,164 (6) -1.3%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 12 — —
2 BR 32 1,164 (6) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2025-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Madinat Al Mataar, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 7 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
28 October 2026readyApartment · 2 BR 1,106 1,490,000 1,347
2 June 2026off-planApartment · 2 BR 1,136 1,358,000 1,195
9 March 2026off-planApartment · 2 BR 1,136 1,353,380 1,191
2 February 2026off-planApartment · 2 BR 1,261 1,433,740 1,137
12 January 2026off-planApartment · 2 BR 1,261 1,377,500 1,092
22 December 2025off-planApartment · 2 BR 1,136 1,327,930 1,169
18 December 2025off-planApartment · 2 BR 1,136 1,322,400 1,164
28 October 2025off-planApartment · 2 BR 1,079 1,300,000 1,205
9 October 2025off-planApartment · 2 BR 1,104 1,308,450 1,185
9 October 2025off-planApartment · 2 BR 1,079 1,288,950 1,195

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationMadinat Al Mataar · Dubai Municipality community

Mag 5 Park area · 810 mSupermarket · 1.4 kmPark · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationEXPO Metro Station · Red Metro line · 8.5 km
MallRijat Retail Mall-12 · 5.4 km
SupermarketSupermarket · 1.4 km
HospitalNMC dip · 9.9 km
ParkMag 5 Park area · 810 m

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 81, with 6,925 units and villas.

2019: 1082020: 2092026: 9542027: 1,6132028: 2,5912029: 1,1602030: 290

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Madinat Al Mataar: 168

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Azizi Venice 14 30.3% May 2026 1,649 2,546
Azizi Venice 6 11.6% Dec 2027 2,032 1,302
Azizi Venice 7 29.2% Jan 2026 1,849 1,180
Terra Heights 9.1% Mar 2029 1,994 1,017
Azizi Venice 15 0% May 2027 1,715 904
azizi venice 13 45.9% Sep 2027 1,675 797
Azizi Venice 10 36.3% — 1,707 776
azizi venice 12 21.6% Sep 2027 1,685 753
Azizi Venice 11 25.9% Aug 2027 1,667 696
Terra Gardens 0.1% Oct 2029 2,127 544
Terra Woods 0% Mar 2030 2,200 505
South Square 2.6% Jun 2028 1,473 428

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Madinat Al Mataar

Developer in DLD data Deviate For Real Estate Development L.L.C · DLD developer no. 1788

Projects registered
2
1 completed · 1 under construction · 0 not started
Units delivered
44
61 in the pipeline
Past the DLD end date
1
of 1 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai South Residential District

DLD lists 119 projects in the master project Dubai South Residential District.

South LivingUnder construction · 88.8% · Feb 2020
South Bay 1Under construction · 93.7% · Mar 2025
The HarmonyUnder construction · 97.8% · Oct 2025
Orchid Residence 1Under construction · 48.5% · Mar 2026
South Bay 2Under construction · 93.8% · May 2026
Bling Avenue 1Under construction · 68.3% · Jul 2026
Views VII by Golden WoodsUnder construction · 90.4% · Jul 2026
Cresswell PlazaUnder construction · 60.1% · Sep 2026
VOI Residence by HVM LivingUnder construction · 15.6% · Sep 2026
Lincoln Star ResidenceUnder construction · 47.2% · Sep 2026
The SereneUnder construction · 46.3% · Oct 2026
The Eighty ThreeUnder construction · 60% · Dec 2026

Questions about Trafford Residence

When was Trafford Residence completed?

Trafford Residence is recorded as completed on 27 August 2026 (DLD register of 1 November 2026).

Who is the developer of Trafford Residence?

Deviate For Real Estate Development L.L.C, as registered with DLD.

What is the DLD project number of Trafford Residence?

3117.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error