DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 3737Completed90 units

Azizi riviera 58 عزيزي ريفيرا 58 Al Merkadh · Meydan One Community by Azizi Developments L.L.CAll phases of Meydan One Community Completed 18 August 2026 (DLD) DLD end date May 2027 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Aug 2026
DLD end date May 2027
Build time
16 months
May 2025 → Aug 2026
Latest sales
—
Fewer than 5 recent sales
Developer
150 projects
91 completed · 20,380 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 1). Latest DLD inspection: 100% built on 17 August 2026 (inspections: 3).
Every DLD inspection and every change in the register %, newest first
Date % built Source
17 August 2026 100% DLD inspection
21 January 2026 76.1% DLD inspection
22 May 2025 48.5% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months
Works startedAug 2023 ± 6 months
Structure risingJul 2024 ± 6 months
Topped outAug 2025 ± 6 months
FinishedMar 2026 ± 6 months

Each date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 23 October 2022 to 25 May 2026; method imagery-v1.

Registered period and actual build

Registered period
25 monthsActual build
16 months
Start date
1 May 2025
DLD end date
30 May 2027
Completion date
18 August 2026
Completion vs DLD end date
9 months before

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Final works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
374035
Issued
5 February 2023
Work start
1 June 2023
Completion
16 July 2026
Consultant · contractor
360 DEGREES ARCHITECTURAL DESIGN CONSULTANCY L.L.C · GARDINIA BUILDING CONTRACTING L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Final works1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
3737
Escrow agent
Abu Dhabi Commercial Bank
Zoning authority
Dubai Municipality
Master project
Meydan One Community
DLD area
Al Merkadh
Units · villas
90 · 0
Start → DLD end
May 2025 → May 2027
Registered unitsStudio 16 · 1 bed 52 · 2 bed 14; sizes 765–929 sqft

Also registered: shops and showrooms 8.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Proposed 2B+G+8+R Residential and Commercial building. The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.

Prices are over apartments, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 3 of 3 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
7 July 2026off-planApartment · Studio 462 1,126,740 2,439
13 April 2026off-planApartment · Studio 462 1,114,960 2,413
6 April 2026off-planApartment · 1 BR 788 1,780,240 2,259

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Merkadh · Dubai Municipality community

Liv minimart · 70 mBradosti Trading · 110 mMOUNT WAY MINIMART · 240 mEden Park · 460 mCentral Park · 580 mEstates Park · 670 mNorth London Collegiate School · 930 mHartland International School · 1.3 kmSobha Mall (Under Construction) · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationBurj Khalifa/ Dubai Mall Metro Station · Red Metro line · 5.4 km
MallSobha Mall (Under Construction) · 1.4 km
SupermarketLiv minimart · 70 m
HospitalHospital · 2.4 km
SchoolNorth London Collegiate School · 930 m
ParkEden Park · 460 m
BeachBeach · 2.3 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 50, with 18,923 units and villas.

2018: 362024: 02025: 4552027: 4,9302028: 3,1842029: 9592030: 2,916No end date: 6,443

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Merkadh: 17

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Sobha Creek Vista Heights 91.5% — 2,076 224
Azizi Riviera Reve 76.6% Feb 2025 — 144
Azizi Riviera 50 60.9% Mar 2027 2,294 79
Azizi Riviera 68 74.6% May 2027 1,971 79
Azizi Riviera 49 54.4% Mar 2027 2,316 75
The Highbury 80% — 2,196 69
Azizi Riviera 66 91% May 2027 1,352 41
ِِAzizi Riviera 60 97.1% Mar 2027 2,125 40
Naya at District One 68.5% Sep 2027 2,106 33
Casa Serene 74% Dec 2024 — 2
Project 3532, Al Merkadh 0% Sep 2025 — 0
Azizi Riviera 53 63.2% Mar 2027 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Merkadh

Developer in DLD data Azizi Developments L.L.C · DLD developer no. 1002

Projects registered
150
91 completed · 43 under construction · 16 not started
Units delivered
20,380
40,083 in the pipeline
Median build time
56 months
completed projects measured: 91
Past the DLD end date
10
of 38 under construction with a DLD end date

Completed a month or more after their DLD end date: 13 of 90 completed projects with both dates. In 65 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Azizi Developments L.L.C is one of 3 DLD-registered developers we list together as Azizi. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Meydan One Community

DLD lists 71 projects in the master project Meydan One Community.

Azizi Riviera ReveUnder construction · 76.6% · Feb 2025
Azizi Riviera 53Under construction · 63.2% · Mar 2027
Azizi Riviera 62Under construction · 90.8% · Mar 2027
Azizi Riviera 49Under construction · 54.4% · Mar 2027
Azizi Riviera 50Under construction · 60.9% · Mar 2027
ِِAzizi Riviera 60Under construction · 97.1% · Mar 2027
Azizi Riviera 64Under construction · 83.8% · May 2027
Azizi Riviera 68Under construction · 74.6% · May 2027
Azizi Riviera 66Under construction · 91% · May 2027
Azizi Riviera 54Under construction · 74.6% · May 2027
Project 3740, Al MerkadhPending · 0% · May 2027
Project 4601, Al MerkadhPending · 0% · Jun 2029

Questions about Azizi riviera 58

When was Azizi riviera 58 completed?

Azizi riviera 58 is recorded as completed on 18 August 2026 (DLD register of 1 November 2026).

Who is the developer of Azizi riviera 58?

Azizi Developments L.L.C, as registered with DLD.

What is the DLD project number of Azizi riviera 58?

3737.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error