DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1854Completed654 units

Mag 330 ماج 330 Wadi Al Safa 4 · City Of Arabia by Mag Property Development L.L.CAll phases of City Of Arabia Completed 14 May 2026 (DLD) DLD end date Feb 2026 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
May 2026
DLD end date Feb 2026
Build time
38 months
Mar 2023 → May 2026
Launch → resale
1,190 AED/sqft
-10.6% on launch Launch 1,338 · 27 sales since completion
1 BR rent
66,000 AED/yr
32 leases, 12 months
Developer
2 projects
2 completed · 1,105 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 100% built on 11 May 2026 (inspections: 10).
Every DLD inspection and every change in the register %, newest first
Date % built Source
11 May 2026 100% DLD inspection
5 February 2026 91.4% DLD inspection
19 September 2025 75.5% DLD inspection
20 May 2025 56.9% DLD inspection
21 January 2025 43% DLD inspection
20 August 2024 25.2% DLD inspection
20 March 2024 20% DLD inspection
16 October 2023 13.1% DLD inspection
13 July 2023 3.4% DLD inspection
2 January 2023 3.4% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
35 monthsActual build
38 months
Start date
1 March 2023
DLD end date
1 February 2026
Completion date
14 May 2026
Completion vs DLD end date
3 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Structure.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Open
238938
Issued
22 December 2016
Work start
22 December 2016
Expected completion
31 May 2026
Consultant · contractor
A E PRIME ENGINEERING CONSULTANTS L.L.C · INTERMASS ENGINEERING & CONTRACTING L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Structure1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1854
Escrow agent
First Abu Dhabi Bank P.J.S.C.
Zoning authority
Dubai Development Authority (DDA)
Master project
City Of Arabia
DLD area
Wadi Al Safa 4
Units · villas
654 · 0
Start → DLD end
Mar 2023 → Feb 2026
Registered unitsStudio 231 · 1 bed 284 · 2 bed 139; sizes 593–1,056 sqft

Also registered: other units 2.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: G+5P + HC/ Tech F+ 23F+R Residential.The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,338 AED/sqft
Median of 238 off-plan sales in the 90 days from the first one (Mar 2024)
Latest registered sales
1,191 AED/sqft
Median of 62 home sales in the last 12 months, ready and off-plan
Change
-7.9%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2024-Q1 to 2026-Q2: +10.8%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
Studio 1,342 (88) 1,169 (12) -12.9%
1 BR 1,336 (116) 1,268 (7) -5.1%
2 BR 1,331 (34) 1,278 (16) -4%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 70 1,169 (12) Nov 2025 – Nov 2026
1 BR 56 1,268 (7) Nov 2025 – Nov 2026
2 BR 80 1,278 (16) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2024-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Wadi Al Safa 4, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
1,338 AED/sqft
Median of 238 off-plan sales, Mar 2024 – Jun 2024
Resales after completion
1,190 AED/sqft
Median of 27 ready sales, May 2026 – Nov 2026
Change
-10.6%
Same home types, weighted by the resales

Too few ready sales in DLD area Wadi Al Safa 4 in both windows for a comparison over the same span.

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.

Bedrooms Median annual rent New contracts Change on a year earlier Gross yield
Studio AED 50,000 20 — —
1 BR AED 66,000 32 — —
2 BR AED 95,000 14 — 4.8%

Gross yield is before service charges, other costs and empty months.

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 7; registered amount AED 5M.

Since the first registration in 2012-Q1: 9 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 62 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
27 October 2026readyApartment · 1 BR 798 875,000 1,096
27 October 2026readyApartment · 1 BR 839 666,385 794
26 October 2026readyApartment · 1 BR 880 880,000 1,000
23 October 2026readyApartment · 1 BR 1,077 1,040,000 966
20 October 2026readyApartment · Studio 602 680,000 1,130
19 October 2026readyApartment · 1 BR 798 1,060,000 1,328
15 October 2026readyApartment · Studio 591 833,000 1,409
12 October 2026readyApartment · 1 BR 796 950,000 1,193
7 October 2026readyApartment · Studio 591 700,000 1,184
21 September 2026readyApartment · 2 BR 1,454 1,643,450 1,130

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationWadi Al Safa 4 · Dubai Municipality community

School · 1.2 kmProject location© OpenStreetMap contributors · Dubai Municipality · Makani
Project location Schools and hospitals

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallRemal Mall · 1.5 km
SupermarketZoom Market Al Bararri · 1.5 km
HospitalHLG Umar · 6.9 km
SchoolSchool · 1.2 km
ParkCourtyard 6 · 2 km
BeachBeach · 7.5 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 56, with 23,679 units and villas.

2026: 7242027: 13,3792028: 6,9222029: 2,5732030: 02031: 0No end date: 81

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 4: 24

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Azizi Milan Heights 0% Sep 2028 1,756 829
Capria West 1.2% May 2029 2,044 716
Capria East 0.9% May 2029 2,143 553
Distrikt 8.4% Sep 2028 1,984 434
Azizi Milan 20 0% Apr 2027 1,604 394
Azizi Milan 30 0% Apr 2027 1,650 386
Laguna Residence 5.7% Dec 2027 1,632 361
Lacina 20.8% Dec 2027 1,958 331
Arancia Yards 2 By Beyond 0% Jan 2029 — 295
Azizi Milan 55 0% Apr 2027 1,713 248
Arancia Yards By Beyond 0% Oct 2028 — 248
Azizi Milan 51 0% Mar 2027 1,740 221

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 4

Developer in DLD data Mag Property Development L.L.C · DLD developer no. 1164

Projects registered
2
2 completed · 0 under construction · 0 not started
Units delivered
1,105
0 in the pipeline

Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in City Of Arabia

DLD lists 15 projects in the master project City Of Arabia.

Laguna ResidenceUnder construction · 5.7% · Dec 2027
Azizi Milan 51Not started · 0% · Mar 2027
Azizi Milan 30Not started · 0% · Apr 2027
Azizi Milan 18Not started · 0% · Apr 2027
Azizi Milan 53Not started · 0% · Apr 2027
Azizi Milan 20Not started · 0% · Apr 2027
Azizi Milan 55Not started · 0% · Apr 2027
Azizi Milan 28Not started · 0% · Jun 2027
Azizi Milan HeightsNot started · 0% · Sep 2028
Arancia Yards By BeyondNot started · 0% · Oct 2028
Project 4479, Wadi Al Safa 4Not started · 0% · Oct 2028
Arancia Yards 2 By BeyondNot started · 0% · Jan 2029

Questions about Mag 330

When was Mag 330 completed?

Mag 330 is recorded as completed on 14 May 2026 (DLD register of 1 November 2026).

Who is the developer of Mag 330?

Mag Property Development L.L.C, as registered with DLD.

What is the DLD project number of Mag 330?

1854.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error