Taraf Development L.L.C ترف للتطوير ش.ذ.م.م 5 projects in the DLD register: 1 completed, 4 under construction, 0 not started or pending. 1 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 5- 38 units and villas in completed projects; 731 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Taraf Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Cello Residences2843 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 39% | — | — | 392 | 196 |
| Terrazzo Residences2675 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 95.2% | May 2026 5 mo past | 5 mo | 211 | 37 |
| Terra Golf Collection2877 · Me'Aisem First · Jumeirah Golf Estates | Under construction | 20.1% | Dec 2027 13 mo to go | — | 77 | 35 |
| Karl Lagerfeld Villas By Taraf2982 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Under construction | 10.5% | — | — | 51 | 29 |
| Luce2572 · Palm Jumeirah | Completed | 100% | Oct 2026 Completed | — | 38 | 7 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.