Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2572Completed38 units

Luce لوتشه Palm Jumeirah by Taraf Development L.L.CAll phases of Palm Jumeirah Completed 20 October 2026 (DLD) DLD end date Dec 2025 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Palm Jumeirah fronds and Atlantis The Royal from the air
Area photo: Palm Jumeirah, not this project
Completed
Oct 2026
DLD end date Dec 2025
Build time
40 months
Jul 2023 → Oct 2026
Latest sales
—
Fewer than 5 recent sales
Developer
5 projects
1 completed · 38 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 100% built on 19 October 2026 (inspections: 13).
Every DLD inspection and every change in the register %, newest first
Date % built Source
19 October 2026 100% DLD inspection
31 August 2026 98.3% DLD inspection
11 May 2026 91.5% DLD inspection
26 January 2026 82.2% DLD inspection
1 October 2025 63.9% DLD inspection
19 June 2025 48.1% DLD inspection
18 April 2025 38.3% DLD inspection
22 January 2025 23% DLD inspection
8 October 2024 15% DLD inspection
25 August 2024 9% DLD inspection
12 May 2024 5% DLD register, archived export
3 April 2024 5.5% DLD inspection
21 June 2023 0% DLD inspection
6 February 2023 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
30 monthsActual build
40 months
Start date
1 July 2023
DLD end date
31 December 2025
Completion date
20 October 2026
Completion vs DLD end date
9 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2572
Escrow agent
First Abu Dhabi Bank P.J.S.C.
Zoning authority
Trakhees
Master project
Palm Jumeirah
DLD area
Palm Jumeirah
Units · villas
38 · 0
Start → DLD end
Jul 2023 → Dec 2025
Registered units2 bed 7 · 3 bed 21 · 4 bed 10; sizes 2,377–3,511 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Residential Building 2B+G+9 , The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Dubai Statistics Center residential price index (flats), 2023-Q2 to 2026-Q2: +17.7%.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
3 BR 6 — —

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2023-Q2 → 2026-Q1

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Palm Jumeirah, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
25.11 AED/sqft a year
Palm Jumeirah: median of 26 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 3 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
30 January 2026off-planApartment · 3 BR 3,456 11,300,000 3,270
10 December 2025off-planApartment · 4 BR 4,144 17,800,000 4,295
21 November 2025off-planApartment · 3 BR 2,349 9,800,000 4,172
29 October 2025off-planApartment · 3 BR 2,770 11,000,000 3,971
19 June 2025off-planApartment · 3 BR 2,313 10,185,000 4,403
29 May 2025off-planApartment · 3 BR 2,387 9,800,000 4,106
10 April 2025off-planApartment · 3 BR 2,601 10,477,174 4,028
20 June 2024off-planApartment · 3 BR 2,642 13,500,000 5,110
2 April 2024off-planApartment · 3 BR 2,514 12,500,000 4,972
26 February 2024off-planApartment · 4 BR 8,298 40,000,000 4,820

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationNakhlat Jumeira · Dubai Municipality community

Beach · 670 mBeach · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationDubai Internet City Metro Station · Red Metro line · 4.2 km
MallPalm Jumeirah Mall · 2.5 km
SupermarketMonoprix · 2.5 km
HospitalWelcare Hospital · 3.7 km
ParkPark · 2.4 km
BeachBeach · 670 m

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 6, with 412 units and villas.

2026: 702027: 572028: 190No end date: 95

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Nakhlat Jumeira: 21

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Passo By Beyond 0% Dec 2029 6,160 281
The Alba Residences by Omniyat 8.4% Mar 2028 9,123 55
Palm Beach Towers - 2 81.6% Dec 2026 3,287 53
Palm Beach Towers -3 74.3% Dec 2026 3,364 45
Palm Beach Towers -1 82.8% Dec 2026 3,295 43
Olaia Residences 14.3% Dec 2027 4,028 36
Como Residences 24.8% Mar 2027 5,624 25
Vitalia by Pinnacle 12.3% Jun 2026 — 22
Ocean House 80.7% — 5,131 18
Orla By Omniyat 70% Dec 2026 7,001 15
ORLA Infinity by OMNIYAT 61.3% — — 7
Ava At Palm Jumeirah By Omniyat 95.9% Jun 2026 — 6

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Nakhlat Jumeira

Developer in DLD data Taraf Development L.L.C · DLD developer no. 1549

Projects registered
5
1 completed · 4 under construction · 0 not started
Units delivered
38
731 in the pipeline
Past the DLD end date
1
of 2 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Palm Jumeirah

DLD lists 58 projects in the master project Palm Jumeirah.

One CrescentUnder construction · 80.1% · Mar 2026
Ava At Palm Jumeirah By OmniyatUnder construction · 95.9% · Jun 2026
Vitalia by PinnacleUnder construction · 12.3% · Jun 2026
Sls Residences At Palm JumeirahUnder construction · 60% · Jul 2026
Palm Beach Towers -1Under construction · 82.8% · Dec 2026
Palm Beach Towers -3Under construction · 74.3% · Dec 2026
Orla By OmniyatUnder construction · 70% · Dec 2026
Palm Beach Towers - 2Under construction · 81.6% · Dec 2026
Como ResidencesUnder construction · 24.8% · Mar 2027
The Palm CrownUnder construction · 11% · Jul 2027
Olaia ResidencesUnder construction · 14.3% · Dec 2027
Armani Beach Residences At Palm JumeirahUnder construction · 10.2% · Dec 2027

Questions about Luce

When was Luce completed?

Luce is recorded as completed on 20 October 2026 (DLD register of 1 November 2026).

Who is the developer of Luce?

Taraf Development L.L.C, as registered with DLD.

What is the DLD project number of Luce?

2572.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error