DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

P C I Real Estate Developers L.L.C بي سي اي للتطوير العقاري ش.ذ.م.م DLD developer no. 1397 · Registered with DLD on 6 December 2021 · Licence 1005173 4 projects in the DLD register: 1 completed, 1 under construction, 2 not started or pending. DLD projects register, export of 1 November 2026

Projects
4
in the DLD register
Completed
1
26 units delivered
Not yet completed
3
301 units in the pipeline

Delivery record

Projects: 4
Completed 1Under construction 1Not started or pending 2
  • 26 units and villas in completed projects; 301 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by P C I Real Estate Developers L.L.C Most registered sales in the last 24 months first

Projects by P C I Real Estate Developers L.L.C
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
South Lofts by Premier Choice4350 · Saih Shuaib 2 Not started 0% Jan 2029 26 mo to go 149 103
Gateway By Premier Choice2688 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 68% — 152 65
barari views2500 · Wadi Al Safa 3 · Majan Completed 100% Nov 2025 Completed 26 12
Project 4443, Saih Shuaib 24443 · Saih Shuaib 2 Pending 0% Dec 2029 37 mo to go — 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 3, all pinned

GATEWAY BY PREMIER CHOICE · 50–75% built2 projects2GATEWAY BY PREMIER CHOICE · 50–75% built2 projects2Makani
50–75% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.