Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4443Pending

Project 4443, Saih Shuaib 2 ساوث لوفت 2 من بريمير تشويس Saih Shuaib 2 by P C I Real Estate Developers L.L.C DLD status: Pending (DLD register as of 1 November 2026) DLD end date Dec 2029 37 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

Lake and French Village buildings at Riverland, Dubai Parks and Resorts, Saih Shuaib, Dubai
Area photo: Saih Shuaib 2, not this project Photo: Aleksandr SerebrennikovCC BY 4.0
% built
0%
DLD register, 1 November 2026
Registered start
Jun 2026
DLD end date Dec 2029
Latest sales
—
Fewer than 5 recent sales
Developer
4 projects
1 completed · 26 units delivered

Completion

DLD status: Pending. 0% built, DLD end date 31 December 2029. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 31 December 2029Pending

Source: DLD projects register, export of 1 November 2026.

DLD registration

DLD services ↗
DLD project number
4443
Escrow agent
Sharjah Islamic Bank
Zoning authority
Dubai Development Authority (DDA)
DLD area
Saih Shuaib 2
Units · villas
0 · 0
Start → DLD end
Jun 2026 → Dec 2029

Description in the DLD register: G+P+6+R

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationSaih Shuaib 2 · Dubai Municipality community

Project location© OpenStreetMap contributors · Dubai Municipality · Makani
Project location

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallThe Outlet Village · 5.5 km
HospitalShifa International Hospitals DWC · 9.2 km

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 18, with 3,596 units and villas.

2026: 2482027: 7732028: 1,7222029: 853

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Saih Shuaib 2: 22

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Samana Hills South 12.1% May 2028 1,455 512
Samana Hills South 3 4.6% Aug 2028 1,389 145
Samana Hills South 2 5.3% Aug 2028 1,696 130
Samana South Haven 0% Dec 2028 — 123
South Lofts by Premier Choice 0% Jan 2029 1,360 103
Elanora by zoya 0% Mar 2028 1,327 56
Coventry Curve 0% Jun 2028 1,099 23
Samana South Haven 2 0% Jun 2029 — 14
South Park Residences 2 By Wellington 98.9% Jun 2028 1,019 13
Coventry Centro 0% Jul 2028 — 11
Coventry Cove 0% Jul 2029 — 4
Siana 0% Apr 2028 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Saih Shuaib 2

Developer in DLD data P C I Real Estate Developers L.L.C · DLD developer no. 1397

Projects registered
4
1 completed · 1 under construction · 2 not started
Units delivered
26
301 in the pipeline

Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error