DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

This project is not in the latest DLD projects feed (1 November 2026). The figures below come from the last export that listed it, 28 October 2026. It may have been merged, renumbered or withdrawn.

DLD project no. 4465Not started264 units

Coventry Centro كوفينتري سينترو Saih Shuaib 2 by G F S Real Estate L.L.C DLD status: Not started (DLD register as of 1 November 2026) DLD end date Jul 2028 20 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

Lake and French Village buildings at Riverland, Dubai Parks and Resorts, Saih Shuaib, Dubai
Area photo: Saih Shuaib 2, not this project Photo: Aleksandr SerebrennikovCC BY 4.0
% built
0%
DLD register, 1 November 2026
Registered start
Jul 2026
DLD end date Jul 2028
Latest sales
1,266 AED/sqft
11 sales
Studio estimate
0.38–0.50 M AED
Automated estimate, not a valuation
Developer
7 projects
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 1 July 2028. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 1 July 2028Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4465
Escrow agent
Emirates Nbd Bank (P.J.S.C)
Zoning authority
Dubai Development Authority (DDA)
DLD area
Saih Shuaib 2
Units · villas
264 · 0
Start → DLD end
Jul 2026 → Jul 2028

Description in the DLD register: 2B+G+9+R

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
Studio 1,206 (10) 1,206 (10) 0%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 10 1,206 (10) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2026-Q3 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Saih Shuaib 2, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Saih Shuaib 2

New Ejari rent contracts for apartments across DLD area Saih Shuaib 2, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 38,000 260 +2.7%
1 BR AED 50,000 169 -9.1%
2 BR AED 70,000 148 0%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 11 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
30 October 2026off-planApartment · Studio 394 475,168 1,206
27 October 2026off-planApartment · Studio 379 494,438 1,305
19 October 2026off-planApartment · Studio 394 498,750 1,266
15 October 2026off-planApartment · Studio 425 404,685 952
30 September 2026off-planApartment · Studio 394 375,000 952
24 September 2026off-planApartment · Studio 392 502,680 1,282
23 September 2026off-planApartment · Studio 394 375,000 952
17 September 2026off-planApartment · 1 BR 676 860,589 1,273
9 September 2026off-planApartment · Studio 390 370,000 949
1 September 2026off-planApartment · Studio 394 515,316 1,308

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Coventry Centro or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
Studio 380,000 – 500,000 10 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jul 2028); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Jul 2028
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Coventry Centro? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationSaih Shuaib 2 · Dubai Municipality community

Project location© OpenStreetMap contributors · Dubai Municipality · Makani
Project location

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallThe Outlet Village · 5 km
HospitalShifa International Hospitals DWC · 8.2 km

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 18, with 3,332 units and villas.

2026: 2482027: 7732028: 1,4582029: 853

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Saih Shuaib 2: 22

Open projects in the same DLD area with a DLD end year from 2027 to 2029, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Samana Hills South 12.1% May 2028 1,455 512
Al Haseen Residence 3 10.1% May 2027 1,480 148
Samana Hills South 3 4.6% Aug 2028 1,389 145
Samana Hills South 2 5.3% Aug 2028 1,696 130
Samana South Haven 0% Dec 2028 — 123
South Lofts by Premier Choice 0% Jan 2029 1,360 103
Elanora by zoya 0% Mar 2028 1,327 56
South Park Residences By Wellington 96.8% Dec 2027 980 25
Coventry Curve 0% Jun 2028 1,099 23
Coventry Residence 3 0% Dec 2027 1,317 18
Samana South Haven 2 0% Jun 2029 — 14
South Park Residences 2 By Wellington 98.9% Jun 2028 1,019 13

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Saih Shuaib 2

Developer in DLD data G F S Real Estate L.L.C · DLD developer no. 2053

Projects registered
7
0 completed · 1 under construction · 6 not started
Units delivered
0
1,522 in the pipeline
Past the DLD end date
0
of 1 under construction with a DLD end date

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error