Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2495Completed354 units

Petalz By Danube بيتلز من دانوب Al Warsan First · Warsan First Development by Danube Properties Development L.L.CAll phases of Warsan First Development Completed 29 October 2025 (DLD) DLD end date Dec 2025 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Oct 2025
DLD end date Dec 2025
Build time
32 months
Mar 2023 → Oct 2025
Launch → resale
1,218 AED/sqft
+9% on launch Launch 1,188 · 31 sales since completion
1 BR rent
64,000 AED/yr
Gross yield 7.9% · 85 leases
Developer
42 projects
19 completed · 8,200 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 100% built on 28 October 2025 (inspections: 10).
Every DLD inspection and every change in the register %, newest first
Date % built Source
28 October 2025 100% DLD inspection
7 October 2025 98.8% DLD inspection
24 September 2025 95.3% DLD inspection
31 May 2025 77.6% DLD inspection
9 January 2025 41.3% DLD inspection
22 July 2024 11.4% DLD inspection
12 May 2024 6% DLD register, archived export
20 March 2024 6.2% DLD inspection
7 November 2023 1.7% DLD inspection
5 June 2023 0% DLD inspection
24 October 2022 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
34 monthsActual build
32 months
Start date
1 March 2023
DLD end date
31 December 2025
Completion date
29 October 2025
Completion vs DLD end date
2 months before

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2495
Escrow agent
Ajman Bank /P.J.S.C
Zoning authority
Dubai Development Authority (DDA)
Master project
Warsan First Development
DLD area
Al Warsan First
Units · villas
354 · 0
Start → DLD end
Mar 2023 → Dec 2025
Registered unitsStudio 122 · 1 bed 130 · 2 bed 89 · 4 bed 1; sizes 428–1,096 sqft

Also registered: shops and showrooms 12.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 2B+G+6F+R Residential+Commercal,The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,188 AED/sqft
Median of 164 off-plan sales in the 90 days from the first one (Jan 2023)
Latest registered sales
1,218 AED/sqft
Median of 31 home sales in the last 12 months, ready and off-plan
Change
+9%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2023-Q1 to 2026-Q2: +19.6%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
1 BR 1,195 (49) 1,229 (5) +2.8%
2 BR 987 (39) 1,128 (5) +14.3%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 18 1,368 (7) Nov 2025 – Nov 2026
1 BR 27 1,229 (5) May 2026 – Nov 2026
2 BR 20 1,128 (5) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Skyline Index

Buildings with sales: 2

Registered sale prices, rents and yields for Petalz By Danube, from DLD records.

Petalz By Danube: registered prices and rents on Skyline Index ↗

Median AED/sqft by quarter

2023-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Warsan First, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
1,188 AED/sqft
Median of 164 off-plan sales, Jan 2023 – Apr 2023
Resales after completion
1,218 AED/sqft
Median of 31 ready sales, Nov 2025 – Nov 2026
Change
+9%
Same home types, weighted by the resales

Over the same span, ready homes in DLD area Al Warsan First changed +41.1% (same home types).

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.

Bedrooms Median annual rent New contracts Change on a year earlier Gross yield
Studio AED 46,000 83 -2.1% —
1 BR AED 64,000 85 +1.6% 7.9%
2 BR AED 88,000 39 +1.1% —

Gross yield is before service charges, other costs and empty months.

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 22; registered amount AED 16.9M.

Since the first registration in 2025-Q4: 23 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 31 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
26 October 2026readyApartment · 2 BR 1,098 1,300,000 1,184
20 October 2026readyApartment · 2 BR 1,136 1,235,000 1,087
20 October 2026readyApartment · 1 BR 642 800,000 1,246
21 September 2026readyApartment · 1 BR 729 800,000 1,097
7 September 2026readyApartment · 2 BR 1,134 1,100,000 970
25 August 2026readyApartment · Studio 387 483,000 1,248
23 July 2026readyApartment · 1 BR 643 800,000 1,244
7 July 2026readyApartment · 2 BR 1,099 1,240,000 1,128
1 July 2026readyApartment · Studio 402 550,000 1,368
24 June 2026readyApartment · 1 BR 664 816,000 1,229

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationWarsan First · Dubai Municipality community

Friendly Supermarket · 220 mPark · 350 mPark · 660 mArabian Supermarket- S03 · 750 mPark · 870 mSanad Al Madina Supermarket · 970 mProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationRashidiya Metro Station · Red Metro line · 7 km
MallDragon Mart Sun Tour · 2.1 km
SupermarketFriendly Supermarket · 220 m
HospitalFakeeh University Hospital · 5.1 km
SchoolSharjah American International School Dubai · 2.2 km
ParkPark · 350 m
BeachBeach · 3 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 10, with 1,735 units and villas.

2026: 1332027: 6552028: 947

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Warsan First: 13

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Ayami Residence, By Ayat Development 0.1% Dec 2028 1,266 221
Longford Residences by Devan Real Estate Development 32.7% May 2028 1,055 174
YIGO26 1.1% Dec 2027 1,176 128
Ryze by AUM 0.1% Jun 2028 1,128 64
Crystal Tower 0.3% Dec 2028 1,199 24
Listone Residence 0% Aug 2027 — 17
Lusin Residences by Ermax Development 35% Dec 2026 — 5
Tomorrow Commercial Tower 70% Jul 2026 — 0
Al Warsan Star 7.5% Feb 2027 — 0
Orbit Residences by Jewel 0% Aug 2027 — 0
Longfor International Center 1.6% Dec 2027 — 0
06 Life Residences 0% Dec 2028 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Warsan First

Developer in DLD data Danube Properties Development L.L.C · DLD developer no. 1009

Projects registered
42
19 completed · 19 under construction · 4 not started
Units delivered
8,200
19,317 in the pipeline
Median build time
32 months
completed projects measured: 19
Past the DLD end date
4
of 11 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 19 completed projects with both dates. In 11 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Warsan First Development

DLD lists 7 projects in the master project Warsan First Development.

Al Warsan StarUnder construction · 7.5% · Feb 2027
Longfor International CenterUnder construction · 1.6% · Dec 2027
Listone ResidenceNot started · 0% · Aug 2027
Ryze by AUMNot started · 0.1% · Jun 2028
Crystal TowerNot started · 0.3% · Dec 2028
Ayami Residence, By Ayat DevelopmentNot started · 0.1% · Dec 2028
Olivz ResidenceCompleted · 100% · Jul 2023

Questions about Petalz By Danube

When was Petalz By Danube completed?

Petalz By Danube is recorded as completed on 29 October 2025 (DLD register of 1 November 2026).

Who is the developer of Petalz By Danube?

Danube Properties Development L.L.C, as registered with DLD.

What is the DLD project number of Petalz By Danube?

2495.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error