DLD project no. 4439Under construction72 units
Longfor International Center مركز لونجفور الدولي 1.6% built (DLD register as of 1 November 2026) · DLD end date Dec 2027 · 13 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.
CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 15 October 2026 | 1.6% | DLD inspection |
| 13 March 2026 | 0% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsEach date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 28 April 2023 to 18 February 2026; method imagery-v1.
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
DLD registration
DLD services ↗Description in the DLD register: Proposed (G+2P+6+R) Offices Building
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Rents in DLD area Al Warsan First
New Ejari rent contracts for apartments across DLD area Al Warsan First, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 31,700 | 4,304 | +5.7% |
| 1 BR | AED 43,000 | 4,107 | +4.9% |
| 2 BR | AED 60,000 | 827 | +7.1% |
| 3 BR | AED 105,000 | 156 | +5% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Looking for a unit in this or similar projects?
Tell us what you are looking for in Longfor International Center or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Dec 2027); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 245,000 · AED 245,000 paid so far |
| 2027-Q1 | AED 100,000 · AED 345,000 paid so far |
| 2027-Q2 | AED 100,000 · AED 445,000 paid so far |
| 2027-Q3 | AED 200,000 · AED 645,000 paid so far |
| 2027-Q4 | AED 400,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in Longfor International Center? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationWarsan First · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 7, with 1,217 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2027 | 3 | 550 |
| 2028 | 4 | 667 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Warsan First: 12
Open projects in the same DLD area with a DLD end year from 2026 to 2028, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Ayami Residence, By Ayat Development | 0.1% | Dec 2028 | 1,266 | 221 |
| Longford Residences by Devan Real Estate Development | 32.7% | May 2028 | 1,055 | 174 |
| YIGO26 | 1.1% | Dec 2027 | 1,176 | 128 |
| Ryze by AUM | 0.1% | Jun 2028 | 1,128 | 64 |
| Crystal Tower | 0.3% | Dec 2028 | 1,199 | 24 |
| Listone Residence | 0% | Aug 2027 | — | 17 |
| Lusin Residences by Ermax Development | 35% | Dec 2026 | — | 5 |
| Tomorrow Commercial Tower | 70% | Jul 2026 | — | 0 |
| Al Warsan Star | 7.5% | Feb 2027 | — | 0 |
| Orbit Residences by Jewel | 0% | Aug 2027 | — | 0 |
| 06 Life Residences | 0% | Dec 2028 | — | 0 |
| Project 4590, Al Warsan First | 0% | Dec 2028 | — | 0 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Star Lang Real Estate Development L.L.C · DLD developer no. 2576
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Warsan First Development
DLD lists 7 projects in the master project Warsan First Development.
Questions about Longfor International Center
When is Longfor International Center's handover?
DLD lists an end date of Dec 2027 (register of 1 November 2026); the SPA sets the handover terms.
Is Longfor International Center past its DLD end date?
No. Its DLD end date is Dec 2027, 13 months after the register of 1 November 2026.
How far along is Longfor International Center?
1.6% built in the DLD register of 1 November 2026.
Who is the developer of Longfor International Center?
Star Lang Real Estate Development L.L.C, as registered with DLD.
What is the DLD project number of Longfor International Center?
4439.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error