DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectWarsan First

Warsan First Development 6 of 8 phases not yet completed · 1,011 units · 477 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Warsan First Development has 8 projects in the Dubai Land Department projects register as of 1 November 2026: 6 not yet completed, with 1,011 units and villas. By DLD status: Not started 4 · Completed 2 · Under construction 2.

Phases
8
2 completed
Not yet completed
6
2 under construction
Units not yet completed
1,011
units and villas
Sales, 24 mo
477
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 8 of the 8 phases: those with a map pin. Pins mark approximate locations.

Ayami Residence, By Ayat Development · Not started · Project locationOlivz Residence · Completed · Project locationPetalz By Danube · Completed · Project locationRyze by AUM · Not started · Project locationCrystal Tower · Not started · Project locationListone Residence · Not started · Project locationAl Warsan Star · Under construction · Project locationLongfor International Center · Under construction · Project locationDubai Municipality · Makani
Under construction Not started Completed

Warsan First (DM community)

Phases (8)Ordered by registered sales over 24 months

Phases (8)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Ayami Residence, By Ayat DevelopmentNot started 0.1% Dec 2028 25 months to go 25 months to go 376 221 -0.2%
Olivz ResidenceCompleted 100% Jul 2023 — 411 86 +46.9%
Petalz By DanubeCompleted 100% Oct 2025 — 354 65 +9%
Ryze by AUMNot started 0.1% Jun 2028 19 months to go 19 months to go 93 64 -0.3%
Crystal TowerNot started 0.3% Dec 2028 25 months to go 25 months to go 110 24 0%
Listone ResidenceNot started 0% Aug 2027 9 months to go 9 months to go 312 17 —
Al Warsan StarUnder construction 7.5% Feb 2027 3 months to go 3 months to go 48 0 —
Longfor International CenterUnder construction 1.6% Dec 2027 13 months to go 13 months to go 72 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

6 phases
2027: 4322028: 579

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Warsan First Development

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology