Dubai off-plan handovers in 2024 148 projects registered to end in 2024 · 142 completed · 6 under construction DLD projects register as of 1 November 2026 · sales to 5 November 2026
148 projects in the Dubai Land Department projects register have an end date in 2024. As of 1 November 2026, 142 are completed, 6 are under construction and 0 have not started. 6 of those under construction are past their DLD end date. These are the DLD end dates registered for each project, not handover forecasts.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end dates by month
148 projects| Month | Completed | Not yet completed | Past the DLD end date |
|---|---|---|---|
| January | 24 | 0 | 0 |
| February | 6 | 2 | 2 |
| March | 11 | 1 | 1 |
| April | 5 | 0 | 0 |
| May | 5 | 0 | 0 |
| June | 16 | 0 | 0 |
| July | 7 | 1 | 1 |
| August | 9 | 0 | 0 |
| September | 12 | 1 | 1 |
| October | 8 | 0 | 0 |
| November | 10 | 0 | 0 |
| December | 29 | 1 | 1 |
Columns link to their monthly pages. Source: DLD projects register, export of 1 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Not yet completed (6)6 projects with a 2024 DLD end date, by sales over 24 months
| Project | Area | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|
| West Bay Tower | Business Bay | 82.5% | 7 Feb 2024 | 32 mo past | 253 |
| Varazze Tower | Al Safouh First | 91.5% | 17 Feb 2024 | 32 mo past | 242 |
| Mars Residences | Al Hebiah Fourth | 79.9% | 23 Mar 2024 | 31 mo past | 554 |
| North Forty Three Serviced Residences | Al Barsha South Fourth | 94.7% | 31 Jul 2024 | 27 mo past | 229 |
| Damac Hills - Gems Estates 2 | Al Hebiah Third | 62.6% | 15 Sep 2024 | 25 mo past | — |
| Casa Serene | Al Merkadh | 74% | 2 Dec 2024 | 22 mo past | — |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Completed142 projects with a 2024 DLD end date, marked completed by DLD
| Project | Area | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|
| La Perla Homes 12 | Al Barsha South Fourth | 10 Jan 2024 | 10 Jan 2024 | On the end date | 18 |
| La Perla Homes 10 | Al Barsha South Fourth | 10 Jan 2024 | 10 Jan 2024 | On the end date | 13 |
| The Stella | Jabal Ali First | 14 Jan 2024 | 14 Jan 2024 | On the end date | — |
| Oxford Terraces | Al Barsha South Fourth | 15 Jan 2024 | 15 Jan 2024 | On the end date | 117 |
| Greenview 2 | Madinat Al Mataar | 18 Jan 2024 | 18 Jan 2024 | On the end date | 292 |
| Greenview | Madinat Al Mataar | 18 Jan 2024 | 18 Jan 2024 | On the end date | 286 |
| Azizi Riviera 46 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 418 |
| Azizi Riviera 43 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 293 |
| Azizi Riviera 41 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 248 |
| Azizi Riviera 47 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 194 |
| Azizi Riviera 42 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 185 |
| Azizi Riviera 45 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 190 |
| Azizi Riviera 38 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 161 |
| Azizi Riviera 44 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 279 |
| Azizi Park Avenue | Nad Al Shiba First | 18 Jan 2024 | 18 Jan 2024 | On the end date | 124 |
| Azizi Riviera 36 | Al Merkadh | 18 Jan 2024 | 18 Jan 2024 | On the end date | 214 |
| Mr. C Residences Jumeirah | Jumeirah Second | 21 Jan 2024 | 21 Jan 2024 | On the end date | 27 |
| Me Do Re | Al Thanyah Fifth | 24 Jan 2024 | 24 Jan 2024 | On the end date | 394 |
| The Autograph | Al Barsha South Fourth | 26 Jan 2024 | 26 Jan 2024 | On the end date | 283 |
| Damac Hills - Silver Springs 3 | Al Hebiah Third | 29 Jan 2024 | 29 Jan 2024 | On the end date | — |
| Damac Hills (2) - Amargo 2 | Madinat Hind 4 | 29 Jan 2024 | 29 Jan 2024 | On the end date | — |
| Catch Residences By IGO | Al Barsha South Fourth | 31 Jan 2024 | 31 Jan 2024 | On the end date | 140 |
| Avenue Residence 4 | Jabal Ali First | 31 Jan 2024 | 31 Jan 2024 | On the end date | 135 |
| The Pulse Villas 2 | Madinat Al Mataar | 31 Jan 2024 | 31 Jan 2024 | On the end date | 74 |
| Bulgari Ocean Mansions | Island 2 | 1 Feb 2024 | 1 Feb 2024 | On the end date | — |
| Uniestate Supreme Residence | Al Barshaa South Third | 19 Feb 2024 | 30 Dec 2025 | 22 mo after | 138 |
| Port De La Mer - La Sirene | Jumeirah First | 20 Feb 2024 | 20 Feb 2024 | On the end date | 151 |
| Binghatti Emerald | Al Barsha South Fourth | 28 Feb 2024 | 28 Feb 2024 | On the end date | 328 |
| Rukan Residence | Wadi Al Safa 7 | 28 Feb 2024 | 28 Feb 2024 | On the end date | 153 |
| Damac HILLS-BEL Air | Al Hebiah Third | 29 Feb 2024 | 29 Feb 2024 | On the end date | — |
| Azizi Riviera 48 | Al Merkadh | 4 Mar 2024 | 4 Mar 2024 | On the end date | 335 |
| Azizi Riviera 37 | Al Merkadh | 4 Mar 2024 | 4 Mar 2024 | On the end date | 241 |
| Azizi Riviera 39 | Al Merkadh | 4 Mar 2024 | 4 Mar 2024 | On the end date | 171 |
| Azizi Greenfield | Nad Al Shiba First | 8 Mar 2024 | 8 Mar 2024 | On the end date | 102 |
| Chorisia 2 Villas | Wadi Al Safa 3 | 8 Mar 2024 | 31 Mar 2024 | 3 wk after | 57 |
| Confident Lancaster | Wadi Al Safa 2 | 15 Mar 2024 | 15 Mar 2024 | On the end date | 81 |
| barari views | Wadi Al Safa 3 | 23 Mar 2024 | 7 Nov 2025 | 19 mo after | 26 |
| Binghatti Corner | Al Barsha South Fourth | 31 Mar 2024 | 31 Mar 2024 | On the end date | 727 |
| Sobha Hartland Waves | Al Merkadh | 31 Mar 2024 | 31 Mar 2024 | On the end date | 604 |
| Canal Front Residences CF1 & CF2 | Al Wasl | 31 Mar 2024 | 31 Mar 2024 | On the end date | 154 |
| Mayas Geneva | Al Barsha South Fourth | 31 Mar 2024 | 31 Mar 2024 | On the end date | 82 |
| Peninsula One | Business Bay | 1 Apr 2024 | 1 Apr 2024 | On the end date | 525 |
| Fawad Azizi Residence | Al Jadaf | 2 Apr 2024 | 2 Apr 2024 | On the end date | 378 |
| Prime Gardens | Al Barshaa South Third | 19 Apr 2024 | 19 Apr 2024 | On the end date | 139 |
| Samana Park Views | Al Barshaa South Third | 30 Apr 2024 | 30 Apr 2024 | On the end date | 178 |
| Zazen Gardens | Jabal Ali First | 30 Apr 2024 | 30 Apr 2024 | On the end date | 157 |
| Legacy By Sunrise | Al Barshaa South Third | 15 May 2024 | 15 May 2024 | On the end date | 132 |
| Azizi Riviera 3 | Al Merkadh | 16 May 2024 | 16 May 2024 | On the end date | 301 |
| Azizi Riviera 40 | Al Merkadh | 16 May 2024 | 16 May 2024 | On the end date | 165 |
| Alexis Tower | Jabal Ali Industrial Second | 20 May 2024 | 20 May 2024 | On the end date | 378 |
| Sevilla Village | Al Hebiah Fourth | 31 May 2024 | 31 May 2024 | On the end date | — |
| Terraces Marasi Drive | Business Bay | 1 Jun 2024 | 1 Jun 2024 | On the end date | 125 |
| Gardenia Townhomes II | Jabal Ali First | 1 Jun 2024 | 17 Sep 2025 | 15 mo after | — |
| Azizi Pearl | Jabal Ali First | 5 Jun 2024 | 5 Jun 2024 | On the end date | 223 |
| Port De La Mer - La Sirene 2 | Jumeirah First | 6 Jun 2024 | 6 Jun 2024 | On the end date | 130 |
| Mohammed Bin Rashid Al Maktoum City District One- C Villas | Al Merkadh | 14 Jun 2024 | 14 Jun 2024 | On the end date | — |
| Divine Living | Al Barshaa South Third | 24 Jun 2024 | 24 Sep 2025 | 15 mo after | 118 |
| Urban Oasis | Business Bay | 27 Jun 2024 | 27 Jun 2024 | On the end date | 467 |
| Kensington Waters | Al Merkadh | 30 Jun 2024 | 30 Jun 2024 | On the end date | 281 |
| Trillionaire Residences by Binghatti | Business Bay | 30 Jun 2024 | 30 Jun 2024 | On the end date | 369 |
| Canal Front Residences-CF3&CF4 | Al Wasl | 30 Jun 2024 | 30 Jun 2024 | On the end date | 105 |
| Mohammed Bin Rashid Al Maktoum City District One, B Villas | Al Merkadh | 30 Jun 2024 | 30 Jun 2024 | On the end date | — |
| Golf Place ll | Hadaeq Sheikh Mohammed Bin Rashid | 30 Jun 2024 | 30 Jun 2024 | On the end date | — |
| Welcome Residency | Al Barshaa South Third | 30 Jun 2024 | 30 Jun 2024 | On the end date | 94 |
| Mohammed Bin Rashid Al Maktoum City District One B Extension Villas | Al Merkadh | 30 Jun 2024 | 30 Jun 2024 | On the end date | — |
| Sobha Hartland Villas Phase III | Al Merkadh | 30 Jun 2024 | 30 Jun 2024 | On the end date | — |
| Harmony | Al Hebiah Fourth | 30 Jun 2024 | 30 Dec 2025 | 18 mo after | — |
| La Violeta 2 | Wadi Al Safa 5 | 1 Jul 2024 | 1 Jul 2024 | On the end date | 226 |
| Torino By ORO24 | Al Barshaa South Third | 8 Jul 2024 | 15 Oct 2025 | 15 mo after | 625 |
| Azizi Riviera 1 | Al Merkadh | 25 Jul 2024 | 25 Jul 2024 | On the end date | 378 |
| Binghatti Gardenia | Al Barsha South Fourth | 25 Jul 2024 | 25 Jul 2024 | On the end date | 308 |
| Binghatti House | Al Barsha South Fourth | 25 Jul 2024 | 25 Jul 2024 | On the end date | 294 |
| The Ivy | Al Barsha South Fifth | 25 Jul 2024 | 25 Jul 2024 | On the end date | 228 |
| Ellington Beach House | Palm Jumeirah | 31 Jul 2024 | 31 Jul 2024 | On the end date | 126 |
| La Rosa 5 | Wadi Al Safa 5 | 1 Aug 2024 | 1 Aug 2024 | On the end date | 216 |
| Eaton | Warsan Fourth | 7 Aug 2024 | 1 Mar 2011 | 161 mo before | 107 |
| AURA by Grovy | Al Barsha South Fourth | 11 Aug 2024 | 11 Aug 2024 | On the end date | 151 |
| Concept 7 Residences | Al Barsha South Fourth | 15 Aug 2024 | 15 Aug 2024 | On the end date | 160 |
| MAG EYE Phase 1 | Hadaeq Sheikh Mohammed Bin Rashid | 16 Aug 2024 | 1 Feb 2023 | 18 mo before | 1,598 |
| The Grove By Iman | Hadaeq Sheikh Mohammed Bin Rashid | 30 Aug 2024 | 30 Aug 2024 | On the end date | 125 |
| Aura | Al Hebiah Fourth | 31 Aug 2024 | 13 Oct 2025 | 13 mo after | 808 |
| Nobles | Business Bay | 31 Aug 2024 | 31 Aug 2024 | On the end date | 562 |
| Binghatti Venus | Al Barsha South Fourth | 31 Aug 2024 | 31 Aug 2024 | On the end date | 191 |
| Peninsula Two | Business Bay | 1 Sep 2024 | 16 Feb 2026 | 17 mo after | 462 |
| Celia Residence | Al Hebiah Second | 14 Sep 2024 | 14 Sep 2024 | On the end date | 111 |
| Jadeel -Madinat Jumeirah Living | Um Suqaim Third | 15 Sep 2024 | 15 Sep 2024 | On the end date | 276 |
| The Community | Al Barsha South Fifth | 18 Sep 2024 | 18 Sep 2024 | On the end date | 379 |
| Murooj Alfurjan West | Jabal Ali First | 24 Sep 2024 | 30 Jun 2024 | 2 mo before | — |
| Belgravia Heights Ii | Al Barsha South Fourth | 27 Sep 2024 | 27 Sep 2024 | On the end date | 142 |
| Beverly Boulevard | Al Barshaa South Third | 30 Sep 2024 | 30 Sep 2024 | On the end date | 271 |
| Luma22 | Al Barsha South Fourth | 30 Sep 2024 | 30 Sep 2024 | On the end date | 407 |
| Canal Front Residences-CF5&CF6 | Al Wasl | 30 Sep 2024 | 30 Sep 2024 | On the end date | 165 |
| Elysee III by Pantheon | Al Barsha South Fourth | 30 Sep 2024 | 30 Sep 2024 | On the end date | 322 |
| Murooj Al Furjan 2 | Jabal Ali First | 30 Sep 2024 | 30 Sep 2024 | On the end date | — |
| Murooj Al Furjan 1 | Jabal Ali First | 30 Sep 2024 | 30 Sep 2024 | On the end date | — |
| Binghatti Onyx | Al Barsha South Fourth | 1 Oct 2024 | 1 Oct 2024 | On the end date | 507 |
| La Residenza | Al Barsha South Fourth | 3 Oct 2024 | 3 Oct 2024 | On the end date | 54 |
| Maya Residences 5 | Al Barsha South Fifth | 15 Oct 2024 | 9 Dec 2024 | 1 mo after | 59 |
| Binghatti Lavender | Al Barsha South Fourth | 29 Oct 2024 | 29 Oct 2024 | On the end date | 166 |
| Binghatti Amber | Al Barsha South Fourth | 30 Oct 2024 | 30 Oct 2024 | On the end date | 658 |
| Westwood Grande by Imtiaz | Al Barsha South Fourth | 31 Oct 2024 | 31 Oct 2024 | On the end date | 157 |
| Palm Hills | Hadaeq Sheikh Mohammed Bin Rashid | 31 Oct 2024 | 31 Oct 2024 | On the end date | — |
| Arabian Ranches lll - June 2 | Wadi Al Safa 5 | 31 Oct 2024 | 31 Oct 2024 | On the end date | 35 |
| SKYZ By Danube | Al Barshaa South Third | 1 Nov 2024 | 21 Nov 2025 | 12 mo after | 827 |
| Ascot Residences | Al Yelayiss 2 | 1 Nov 2024 | 1 Nov 2024 | On the end date | 153 |
| Celadon | Al Wasl | 1 Nov 2024 | 30 Sep 2025 | 10 mo after | 161 |
| Elegance by Chaimaa Holding | Al Barsha South Fourth | 1 Nov 2024 | 10 Mar 2026 | 16 mo after | 118 |
| Viridian | Al Wasl | 1 Nov 2024 | 1 Nov 2024 | On the end date | 130 |
| Eome | Palm Jumeirah | 1 Nov 2024 | 12 Jun 2026 | 19 mo after | 26 |
| Oxford Terraces 2 | Al Barsha South Fourth | 15 Nov 2024 | 15 Nov 2024 | On the end date | 101 |
| Arabain Ranches lll - Bliss | Wadi Al Safa 5 | 30 Nov 2024 | 30 Nov 2024 | On the end date | 332 |
| The Diplomat Residences | Al Yelayiss 2 | 30 Nov 2024 | 30 Nov 2024 | On the end date | 153 |
| Majestic Vistas | Hadaeq Sheikh Mohammed Bin Rashid | 30 Nov 2024 | 30 Nov 2024 | On the end date | — |
| La Rosa 6 | Wadi Al Safa 5 | 1 Dec 2024 | 1 Dec 2024 | On the end date | 272 |
| Nad Al Sheba Gardens Phase 2 | Nad Al Shiba First | 1 Dec 2024 | 17 Dec 2025 | 12 mo after | 212 |
| Samana Miami | Al Barsha South Fourth | 1 Dec 2024 | 3 Jun 2026 | 18 mo after | 93 |
| Prime Residency 3 | Jabal Ali First | 6 Dec 2024 | 6 Dec 2024 | On the end date | 292 |
| Port De La Mer - Le Soleil | Jumeirah First | 8 Dec 2024 | 9 Jan 2026 | 13 mo after | 184 |
| Peninsula Five | Business Bay | 15 Dec 2024 | 15 Dec 2024 | On the end date | 383 |
| Damac Hills - Golf Gate | Al Hebiah Third | 15 Dec 2024 | 15 Dec 2024 | On the end date | 351 |
| Al Jazi - Madinat Jumeriah Living | Um Suqaim Third | 15 Dec 2024 | 27 Oct 2025 | 10 mo after | 378 |
| West Five Business Bay Residences | Business Bay | 18 Dec 2024 | 18 Sep 2025 | 9 mo after | 139 |
| Aark Residences | Wadi Al Safa 5 | 23 Dec 2024 | 27 Apr 2026 | 16 mo after | 100 |
| Nadine Residences | Jabal Ali First | 25 Dec 2024 | 25 Dec 2024 | On the end date | 102 |
| Damac Hills (2) - Victoria 2 | Madinat Hind 4 | 29 Dec 2024 | 29 Dec 2024 | On the end date | — |
| The Valley-Nara | Al Yufrah 1 | 30 Dec 2024 | 30 Dec 2024 | On the end date | 372 |
| The Pulse- Beachfront | Madinat Al Mataar | 30 Dec 2024 | 30 Dec 2024 | On the end date | 291 |
| Dawn by Binghatti | Al Barsha South Fourth | 30 Dec 2024 | 19 May 2025 | 4 mo after | 97 |
| Shams Townhouses | Al Yelayiss 2 | 30 Dec 2024 | 30 Dec 2024 | On the end date | 212 |
| The Pulse Beachfront 2 | Madinat Al Mataar | 30 Dec 2024 | 30 Dec 2024 | On the end date | 198 |
| Regalia | Business Bay | 31 Dec 2024 | 29 Apr 2026 | 15 mo after | 913 |
| Binghatti Azure | Al Barsha South Fourth | 31 Dec 2024 | 31 Dec 2024 | On the end date | 650 |
| Canal Front Residences-CF7 & CF8 & CF9 | Al Wasl | 31 Dec 2024 | 31 Dec 2024 | On the end date | 374 |
| Bliss Homes | Wadi Al Safa 5 | 31 Dec 2024 | 31 Dec 2024 | On the end date | 105 |
| Dusk by Binghatti | Al Barsha South Fourth | 31 Dec 2024 | 31 Dec 2024 | On the end date | 107 |
| Marquis Galleria | Al Barshaa South Third | 31 Dec 2024 | 10 Apr 2026 | 15 mo after | 126 |
| Berkeley Place | Al Merkadh | 31 Dec 2024 | 31 Dec 2024 | On the end date | 127 |
| Six Senses Residences The Palm, Dubai | Palm Jumeirah | 31 Dec 2024 | 3 Sep 2026 | 20 mo after | 173 |
| Damac Hills - Cavalli Estates | Al Hebiah Third | 31 Dec 2024 | 13 May 2026 | 16 mo after | — |
| THE RESIDENCE | Burj Khalifa | Burj Khalifa | 31 Dec 2024 | 22 Sep 2026 | 20 mo after | 35 |
| Tilal AL Furjan- Phase Two | Jabal Ali First | 31 Dec 2024 | 31 Dec 2024 | On the end date | — |
| Tilal AL Furjan- Phase One | Jabal Ali First | 31 Dec 2024 | 31 Dec 2024 | On the end date | — |
Completed: the completion date DLD records for the project. Source: DLD projects register, export of 1 November 2026.
Months of 2024
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology