DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers in 2023 144 projects registered to end in 2023 · 139 completed · 5 under construction DLD projects register as of 1 November 2026 · sales to 5 November 2026

144 projects in the Dubai Land Department projects register have an end date in 2023. As of 1 November 2026, 139 are completed, 5 are under construction and 0 have not started. 5 of those under construction are past their DLD end date. These are the DLD end dates registered for each project, not handover forecasts.

Registered to end in 2023
144
projects · 1,579 units not yet completed
Completed
139
marked completed by DLD
Under construction
5
0 with the end date to come
Not started
0
Not yet active on the DLD register
Under construction, past end date
5
of 5 under construction

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end dates by month

144 projects

Columns link to their monthly pages. Source: DLD projects register, export of 1 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Not yet completed (5)5 projects with a 2023 DLD end date, by sales over 24 months

5 projects with a 2023 DLD end date, by sales over 24 months
ProjectArea Built DLD end dateTo DLD end date Units
Burj PacificBusiness Bay 98.8% 31 Jan 2023 45 mo past 145
The Wind Tower IAl Thanyah Fifth 74.6% 5 Jun 2023 40 mo past 515
The Wind Tower IiAl Thanyah Fifth 84.5% 5 Jun 2023 40 mo past 411
Discovery DunesMadinat Al Mataar 70% 1 Dec 2023 35 mo past 80
Luxury Family ResidenceAl Barsha South Fourth 76% 31 Dec 2023 34 mo past 428

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Completed139 projects with a 2023 DLD end date, marked completed by DLD

139 projects with a 2023 DLD end date, marked completed by DLD
ProjectAreaDLD end dateCompletedAgainst the end date Units
Vincitore BenessereAl Barshaa South Third 9 Jan 2023 9 Jan 2023 On the end date 419
Nicholas ResidenceAl Barsha South Fourth 11 Jan 2023 11 Jan 2023 On the end date 97
Address Harbour PointAl Khairan First 12 Jan 2023 12 Jan 2023 On the end date 813
RukanWadi Al Safa 7 18 Jan 2023 18 Jan 2023 On the end date 621
Taraf 2 ResidenceAl Barsha South Fifth 19 Jan 2023 19 Jan 2023 On the end date 94
Blue WaveWadi Al Safa 5 30 Jan 2023 30 Jan 2023 On the end date 578
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 25Al Merkadh 30 Jan 2023 30 Jan 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 23Al Merkadh 30 Jan 2023 30 Jan 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 24Al Merkadh 30 Jan 2023 30 Jan 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 20Al Merkadh 30 Jan 2023 30 Jan 2023 On the end date 31
SocioHadaeq Sheikh Mohammed Bin Rashid 31 Jan 2023 31 Jan 2023 On the end date 336
Damac HILLS-PARK Residences 4Al Hebiah Third 31 Jan 2023 31 Jan 2023 On the end date 29
Binghatti JasmineAl Barsha South Fourth 31 Jan 2023 31 Jan 2023 On the end date 92
The Royal ATLANTIS,RESORT And ResidencesPalm Jumeirah 12 Feb 2023 16 Jun 2022 7 mo before 232
UPSIDE LivingBusiness Bay 28 Feb 2023 28 Feb 2023 On the end date 527
Midtown - NoorMe'Aisem First 28 Feb 2023 28 Feb 2023 On the end date 606
Oxford 212Al Barsha South Fourth 28 Feb 2023 28 Feb 2023 On the end date 212
Golf PlaceHadaeq Sheikh Mohammed Bin Rashid 28 Feb 2023 28 Feb 2023 On the end date —
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences12Al Merkadh 6 Mar 2023 6 Mar 2023 On the end date 159
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14Al Merkadh 6 Mar 2023 6 Mar 2023 On the end date 136
Creek Beach - SurfAl Khairan First 7 Mar 2023 7 Mar 2023 On the end date 173
Creek Beach - SummerAl Khairan First 7 Mar 2023 7 Mar 2023 On the end date 305
Arabian Ranches lll - RubaWadi Al Safa 5 25 Mar 2023 25 Mar 2023 On the end date 430
The Address Dubai OperaBurj Khalifa 30 Mar 2023 30 Mar 2023 On the end date 873
Marina VistaMarsa Dubai 30 Mar 2023 30 Mar 2023 On the end date 625
Azizi Riviera 24Al Merkadh 30 Mar 2023 30 Mar 2023 On the end date 211
Chorisia 1 VillasWadi Al Safa 3 30 Mar 2023 30 Mar 2023 On the end date —
Creek CrescentAl Khairan First 31 Mar 2023 31 Mar 2023 On the end date 230
Creek Beach - RosewaterAl Khairan First 31 Mar 2023 31 Mar 2023 On the end date 211
LOCI ResidencesAl Barsha South Fourth 31 Mar 2023 31 Mar 2023 On the end date 114
Forum ResidencesWadi Al Safa 3 31 Mar 2023 31 Mar 2023 On the end date 46
Creek Beach - VIDA ResidencesAl Khairan First 12 Apr 2023 12 Apr 2023 On the end date 233
Sobha Hartland One Park AvenueAl Merkadh 15 Apr 2023 16 Sep 2022 6 mo before 415
Royal Park SouthAl Barsha South Fourth 15 Apr 2023 15 Apr 2023 On the end date 10
La VieMarsa Dubai 19 Apr 2023 19 Apr 2023 On the end date 269
15 NorthsideBusiness Bay 25 Apr 2023 25 Apr 2023 On the end date 358
Binghatti CreekAl Jadaf 30 Apr 2023 30 Apr 2023 On the end date 335
Beach IsleMarsa Dubai 30 Apr 2023 30 Apr 2023 On the end date 397
Samana Golf AvenueAl Hebiah Second 30 Apr 2023 28 Feb 2023 2 mo before 229
Luma21Al Barsha South Fourth 30 Apr 2023 30 Apr 2023 On the end date 238
Asayel at Madinat Jumeirah LivingUm Suqaim Third 11 May 2023 11 May 2023 On the end date 307
The Sterling West HouseBusiness Bay 24 May 2023 24 May 2023 On the end date 187
Azizi Riviera 5Al Merkadh 25 May 2023 25 May 2023 On the end date 221
Grand Bleu Tower interiors by Elie SaabMarsa Dubai 30 May 2023 30 May 2023 On the end date 639
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 26Al Merkadh 30 May 2023 30 May 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 28Al Merkadh 30 May 2023 30 May 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 29Al Merkadh 30 May 2023 30 May 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 30Al Merkadh 30 May 2023 30 May 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 27Al Merkadh 30 May 2023 30 May 2023 On the end date 31
The Fields At D11 - MbrmcWadi Al Safa 3 31 May 2023 10 Apr 2026 34 mo after 1,028
The Pulse VillasMadinat Al Mataar 1 Jun 2023 1 Jun 2023 On the end date 274
Five LuxeMarsa Dubai 2 Jun 2023 26 Dec 2023 6 mo after 459
The Villa 3Wadi Al Safa 5 2 Jun 2023 14 Oct 2012 127 mo before —
The Valley - EdenAl Yufrah 1 3 Jun 2023 3 Jun 2023 On the end date 362
Azizi Riviera 8Al Merkadh 7 Jun 2023 7 Jun 2023 On the end date 216
Azizi Riviera 9Al Merkadh 22 Jun 2023 22 Jun 2023 On the end date 231
Wilton Park ResidencesAl Merkadh 25 Jun 2023 25 Jun 2023 On the end date 320
Royal Park South 1Al Barsha South Fourth 25 Jun 2023 25 Jun 2023 On the end date 35
Zada TowerBusiness Bay 30 Jun 2023 30 Jun 2023 On the end date 703
Creek Beach - GroveAl Khairan First 30 Jun 2023 30 Jun 2023 On the end date 269
Parkside 2Madinat Al Mataar 30 Jun 2023 30 Jun 2023 On the end date 422
Damac Hills (2) - Navitas (A & B)Madinat Hind 4 30 Jun 2023 30 Jun 2023 On the end date 218
Binghatti CanalBusiness Bay 30 Jun 2023 30 Jun 2023 On the end date 306
Azizi Riviera 26Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 270
Ahad ResidencesBusiness Bay 30 Jun 2023 30 Jun 2023 On the end date 350
Azizi Riviera 25Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 276
Azizi Riviera 32Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 247
Azizi Riviera 27Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 234
Azizi Riviera 29Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 176
Azizi Riviera 31Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 134
Azizi Riviera 21Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 157
Azizi Riviera 30Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 135
Azizi Riviera 22Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 157
GARDENIA1 & 2Al Barsha South Fourth 30 Jun 2023 1 Sep 2026 38 mo after 172
Pg UpperhouseJabal Ali First 30 Jun 2023 30 Jun 2023 On the end date 105
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 22Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 31
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 7Al Merkadh 30 Jun 2023 30 Jun 2023 On the end date 62
MAYA townhousesWadi Al Safa 3 5 Jul 2023 5 Jul 2023 On the end date 30
Westar AzureAl Barsha South Fourth 5 Jul 2023 5 Jul 2023 On the end date 13
Olivz ResidenceAl Warsan First 11 Jul 2023 11 Jul 2023 On the end date 411
Marwa HeightsAl Barsha South Fourth 12 Jul 2023 12 Jul 2023 On the end date 128
Azizi Riviera 18Al Merkadh 14 Jul 2023 14 Jul 2023 On the end date 282
Azizi Riviera 15Al Merkadh 14 Jul 2023 14 Jul 2023 On the end date 251
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13Al Merkadh 16 Jul 2023 16 Jul 2023 On the end date 133
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 6Al Merkadh 16 Jul 2023 16 Jul 2023 On the end date 61
The Eugene TownhousesWadi Al Safa 3 21 Jul 2023 21 Jul 2023 On the end date 48
Orra The EmbankmentAl Thanyah Fifth 1 Aug 2023 29 Jan 2026 29 mo after 464
Al Helal Al Zahaby 3Warsan Fourth 1 Aug 2023 1 Aug 2023 On the end date 67
Damac HILLS-VENETOAl Hebiah Third 7 Aug 2023 31 Dec 2022 7 mo before —
Azizi BertonJabal Ali First 8 Aug 2023 8 Aug 2023 On the end date 250
Binghatti HeightsAl Barsha South Fourth 15 Aug 2023 15 Aug 2023 On the end date 366
Burj CrownBurj Khalifa 17 Aug 2023 17 Aug 2023 On the end date 433
The Sterling East HouseBusiness Bay 29 Aug 2023 29 Aug 2023 On the end date 222
Sobha Creek vistas ReserveAl Merkadh 30 Aug 2023 30 Aug 2023 On the end date 784
Aykon CityBusiness Bay 30 Aug 2023 30 Aug 2023 On the end date 1,224
La Rosa 3Wadi Al Safa 5 1 Sep 2023 1 Sep 2023 On the end date 206
The V TowerWadi Al Safa 5 5 Sep 2023 5 Sep 2023 On the end date 369
Azizi Riviera 28Al Merkadh 12 Sep 2023 12 Sep 2023 On the end date 243
Azizi Riviera 33Al Merkadh 13 Sep 2023 13 Sep 2023 On the end date 204
Azizi Riviera 35Al Merkadh 14 Sep 2023 14 Sep 2023 On the end date 252
Azizi Riviera 34Al Merkadh 14 Sep 2023 14 Sep 2023 On the end date 250
Creek EdgeAl Khairan First 23 Sep 2023 23 Sep 2023 On the end date 564
Gardenia LivingsAl Barshaa South Third 30 Sep 2023 30 Sep 2023 On the end date 156
Golf villeHadaeq Sheikh Mohammed Bin Rashid 8 Oct 2023 8 Oct 2023 On the end date 308
Marina StarMarsa Dubai 9 Oct 2023 9 Oct 2023 On the end date 211
Tranquil Wellness TowerAl Barsha South Fifth 10 Oct 2023 29 Sep 2025 23 mo after 252
Aykon City 2Business Bay 12 Oct 2023 12 Oct 2023 On the end date 986
Azizi Riviera 19Al Merkadh 16 Oct 2023 16 Oct 2023 On the end date 207
Prive ResidenceHadaeq Sheikh Mohammed Bin Rashid 18 Oct 2023 18 Oct 2023 On the end date 231
La RosaWadi Al Safa 5 18 Oct 2023 18 Oct 2023 On the end date 154
Binghatti CrescentAl Barsha South Fourth 26 Oct 2023 26 Oct 2023 On the end date 170
Imperial AvenueBurj Khalifa 30 Oct 2023 9 Jun 2025 19 mo after 431
Jewelz ResidenceAl Barshaa South Third 30 Oct 2023 30 Oct 2023 On the end date 463
Boutique XllAl Jadaf 30 Oct 2023 30 Oct 2023 On the end date 129
Sobha Hartland Waves GrandeAl Merkadh 31 Oct 2023 31 Oct 2024 12 mo after 440
Binghatti NovaAl Barsha South Fourth 31 Oct 2023 31 Oct 2023 On the end date 211
La Rosa Phase 2Wadi Al Safa 5 31 Oct 2023 31 Oct 2023 On the end date 276
Binghatti CrestAl Barsha South Fourth 31 Oct 2023 31 Oct 2023 On the end date 171
Binghatti LunaAl Barsha South Fourth 31 Oct 2023 31 Oct 2023 On the end date 212
AvanosAl Barsha South Fourth 1 Nov 2023 1 Nov 2023 On the end date 96
ElanAl Hebiah Fourth 3 Nov 2023 3 Nov 2023 On the end date 916
La Belle VueAl Barsha South Fourth 6 Nov 2023 1 May 2010 162 mo before 10
Belgravia SquareAl Barsha South Fourth 8 Nov 2023 8 Nov 2023 On the end date 225
Profile ResidenceAl Hebiah Fourth 9 Nov 2023 31 Dec 2021 22 mo before 138
Westwood By ImtiazJabal Ali First 27 Nov 2023 27 Nov 2023 On the end date 188
Laya HeightsAl Hebiah Second 30 Nov 2023 30 Nov 2023 On the end date 396
Reem TownhousesAl Yelayiss 2 30 Nov 2023 30 Nov 2023 On the end date 364
Azizi GardensNad Al Shiba First 11 Dec 2023 11 Dec 2023 On the end date 82
One Za'abeelZaabeel First 29 Dec 2023 29 Dec 2023 On the end date 484
Luxury Family Residence IIBusiness Bay 30 Dec 2023 30 Dec 2023 On the end date 205
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 11Al Merkadh 30 Dec 2023 30 Dec 2023 On the end date 130
Mohammed Bin Rashid Al Maktoum City , District One Phase III , A VillasAl Merkadh 30 Dec 2023 30 Dec 2023 On the end date —
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 8Al Merkadh 30 Dec 2023 30 Dec 2023 On the end date 73
Oakley Square ResidencesAl Barsha South Fourth 31 Dec 2023 31 Dec 2023 On the end date 269
Bali ResidencesAl Barsha South Fifth 31 Dec 2023 31 Dec 2023 On the end date 121
Mas TowerNadd Hessa 31 Dec 2023 31 Dec 2023 On the end date 96
Equiti ArcadeJabal Ali First 31 Dec 2023 31 Dec 2023 On the end date 83
Aras HeightsWadi Al Safa 3 31 Dec 2023 12 Mar 2026 26 mo after 73
Marquis SignatureAl Barshaa South Third 31 Dec 2023 31 Dec 2023 On the end date 91

Completed: the completion date DLD records for the project. Source: DLD projects register, export of 1 November 2026.

Months of 2023

Other years: 2022 · 2024

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology