Dubai off-plan handovers in 2022 153 projects registered to end in 2022 · 147 completed · 6 under construction DLD projects register as of 1 November 2026 · sales to 5 November 2026
153 projects in the Dubai Land Department projects register have an end date in 2022. As of 1 November 2026, 147 are completed, 6 are under construction and 0 have not started. 6 of those under construction are past their DLD end date. These are the DLD end dates registered for each project, not handover forecasts.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end dates by month
153 projects| Month | Completed | Not yet completed | Past the DLD end date |
|---|---|---|---|
| January | 12 | 0 | 0 |
| February | 10 | 0 | 0 |
| March | 13 | 0 | 0 |
| April | 6 | 0 | 0 |
| May | 8 | 0 | 0 |
| June | 16 | 0 | 0 |
| July | 4 | 0 | 0 |
| August | 14 | 2 | 2 |
| September | 17 | 2 | 2 |
| October | 12 | 1 | 1 |
| November | 10 | 1 | 1 |
| December | 25 | 0 | 0 |
Columns link to their monthly pages. Source: DLD projects register, export of 1 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Not yet completed (6)6 projects with a 2022 DLD end date, by sales over 24 months
| Project | Area | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|
| Eden Garden | Al Hebiah Fourth | 96% | 31 Aug 2022 | 50 mo past | 394 |
| Sherena Residence 2 | Wadi Al Safa 3 | 82% | 31 Aug 2022 | 50 mo past | 120 |
| The Heart Of Europe 1 | World Islands | 86.2% | 30 Sep 2022 | 49 mo past | 32 |
| The Heart of Europe | World Islands | 82.3% | 30 Sep 2022 | 49 mo past | 10 |
| Palmarosa | Wadi Al Safa 7 | 97.8% | 31 Oct 2022 | 48 mo past | 296 |
| Aryene Greens | Al Barshaa South Third | 80.1% | 30 Nov 2022 | 47 mo past | 124 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Completed147 projects with a 2022 DLD end date, marked completed by DLD
| Project | Area | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|
| Shorooq Land 1 | Wadi Al Safa 5 | 4 Jan 2022 | 4 Jan 2022 | On the end date | 244 |
| Beach Vista | Marsa Dubai | 6 Jan 2022 | 6 Jan 2022 | On the end date | 466 |
| AR II Camelia | Wadi Al Safa 7 | 7 Jan 2022 | 7 Jan 2022 | On the end date | 258 |
| Azizi Star Hotel Apartments | Jabal Ali First | 10 Jan 2022 | 10 Jan 2022 | On the end date | 500 |
| Sobha Creek Vistas | Al Merkadh | 17 Jan 2022 | 31 Dec 2021 | 2 wk before | 784 |
| Binghatti Gate | Al Barsha South Fourth | 17 Jan 2022 | 17 Jan 2022 | On the end date | 132 |
| The Nook | Jabal Ali First | 22 Jan 2022 | 22 Jan 2022 | On the end date | 605 |
| Topaz Residences 2 | Nadd Hessa | 31 Jan 2022 | 31 Jan 2022 | On the end date | 202 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 1 | Al Merkadh | 31 Jan 2022 | 31 Jan 2022 | On the end date | 31 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 2 | Al Merkadh | 31 Jan 2022 | 31 Jan 2022 | On the end date | 31 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 | Al Merkadh | 31 Jan 2022 | 31 Jan 2022 | On the end date | 31 |
| The One at Jumeirah Village Triangle | Al Barsha South Fifth | 31 Jan 2022 | 31 Jan 2022 | On the end date | 593 |
| Lawnz Residence by Danube | Al Warsan First | 1 Feb 2022 | 1 Feb 2022 | On the end date | 1,063 |
| La Rosa 4 | Wadi Al Safa 5 | 1 Feb 2022 | 1 Feb 2022 | On the end date | 178 |
| Binghatti Point | Nadd Hessa | 3 Feb 2022 | 3 Feb 2022 | On the end date | 127 |
| Hera Tower | Al Hebiah Fourth | 7 Feb 2022 | 7 Feb 2022 | On the end date | 531 |
| Damac Hills (2) - Pacifica | Madinat Hind 4 | 10 Feb 2022 | 10 Feb 2022 | On the end date | — |
| Elite Downtown Residence | Burj Khalifa | 10 Feb 2022 | 10 Feb 2022 | On the end date | 469 |
| The Terraces | Al Merkadh | 15 Feb 2022 | 15 Feb 2022 | On the end date | 251 |
| Al Habtoor City | Business Bay | 17 Feb 2022 | 17 Feb 2022 | On the end date | 1,468 |
| Damac Hills (2) - Vardon | Madinat Hind 4 | 17 Feb 2022 | 9 Mar 2022 | 2 wk after | — |
| Damac Hills (2) - Acuna | Madinat Hind 4 | 21 Feb 2022 | 31 Dec 2017 | 49 mo before | — |
| Damac Hills (2) - Coursetia | Madinat Hind 4 | 16 Mar 2022 | 16 Mar 2022 | On the end date | — |
| Damac Hills (2) - Albizia | Madinat Hind 4 | 21 Mar 2022 | 21 Mar 2022 | On the end date | — |
| Damac Hills (2) - Basswood | Madinat Hind 4 | 21 Mar 2022 | 21 Mar 2022 | On the end date | — |
| Damac Hills (2) - Aster | Madinat Hind 4 | 21 Mar 2022 | 30 Oct 2021 | 4 mo before | — |
| Amaranta 2 | Wadi Al Safa 5 | 21 Mar 2022 | 21 Mar 2022 | On the end date | 352 |
| Damac Hills - Carson | Al Hebiah Third | 29 Mar 2022 | 29 Mar 2022 | On the end date | 1,575 |
| Paramount Tower Hotel & Residences | Business Bay | 29 Mar 2022 | 29 Mar 2022 | On the end date | 799 |
| Q Gardens Boutique Residences | Al Barshaa South Third | 30 Mar 2022 | 30 Mar 2022 | On the end date | 153 |
| Collective | Hadaeq Sheikh Mohammed Bin Rashid | 31 Mar 2022 | 31 Mar 2022 | On the end date | 477 |
| Collective 2.0 | Hadaeq Sheikh Mohammed Bin Rashid | 31 Mar 2022 | 31 Mar 2022 | On the end date | 495 |
| Vera Tower | Business Bay | 31 Mar 2022 | 31 Mar 2022 | On the end date | 526 |
| Lucky Residence | Al Barsha South Fourth | 31 Mar 2022 | 31 Mar 2022 | On the end date | 142 |
| Sun Point Dubai | Me'Aisem First | 31 Mar 2022 | 31 Mar 2022 | On the end date | 255 |
| Port De La Mer - La Voile | Jumeirah First | 3 Apr 2022 | 3 Apr 2022 | On the end date | 183 |
| The Haven Residences | Al Barsha South Fourth | 15 Apr 2022 | 15 Apr 2022 | On the end date | 161 |
| Damac Hills (2) - Centaury | Madinat Hind 4 | 19 Apr 2022 | 9 Mar 2022 | 1 mo before | — |
| Binghatti Avenue | Al Jadaf | 26 Apr 2022 | 26 Apr 2022 | On the end date | 639 |
| Binghatti Rose | Al Barsha South Fourth | 30 Apr 2022 | 30 Apr 2022 | On the end date | 171 |
| Azizi Riviera 13 | Al Merkadh | 30 Apr 2022 | 10 Nov 2022 | 6 mo after | 234 |
| Park Ridge | Hadaeq Sheikh Mohammed Bin Rashid | 8 May 2022 | 8 May 2022 | On the end date | 1,056 |
| Regina | Al Barsha South Fourth | 9 May 2022 | 23 Mar 2022 | 1 mo before | 328 |
| La Riviera Azure | Al Barsha South Fourth | 15 May 2022 | 15 May 2022 | On the end date | 88 |
| Villanova Amaranta | Wadi Al Safa 5 | 18 May 2022 | 18 May 2022 | On the end date | 561 |
| ELZ Residence | Al Barshaa South Third | 23 May 2022 | 31 May 2022 | 1 wk after | 275 |
| Parkside 3 | Madinat Al Mataar | 28 May 2022 | 28 May 2022 | On the end date | 365 |
| Cherrywoods | Al Yelayiss 1 | 31 May 2022 | 27 Jun 2021 | 11 mo before | 378 |
| Damac Hills (2) - Avencia | Madinat Hind 4 | 31 May 2022 | 31 May 2022 | On the end date | 230 |
| Dorchester Collection Dubai | Business Bay | 1 Jun 2022 | 1 Jun 2022 | On the end date | 57 |
| Damac Hills (2) - Zinnia | Madinat Hind 4 | 2 Jun 2022 | 2 Jun 2022 | On the end date | — |
| Samana Hills | Al Barshaa South Third | 9 Jun 2022 | 9 Jun 2022 | On the end date | 202 |
| Central Park at City Walk -Building 1 | Al Wasl | 13 Jun 2022 | 14 Oct 2021 | 7 mo before | 184 |
| Tabeer 1 | Al Warsan First | 15 Jun 2022 | 15 Jun 2022 | On the end date | 107 |
| The Estate - II | Jabal Ali First | 15 Jun 2022 | 15 Jun 2022 | On the end date | 40 |
| Binghatti Mirage | Al Barsha South Fourth | 19 Jun 2022 | 19 Jun 2022 | On the end date | 160 |
| ARAS Residence | Wadi Al Safa 3 | 22 Jun 2022 | 22 Jun 2022 | On the end date | 96 |
| Damac Hills - The Trump Estates 3 | Al Hebiah Third | 28 Jun 2022 | 28 Jun 2022 | On the end date | — |
| Damac Hills - The Trump Estates 2 | Al Hebiah Third | 28 Jun 2022 | 28 Jun 2022 | On the end date | — |
| Grande | Burj Khalifa | 30 Jun 2022 | 30 Jun 2022 | On the end date | 906 |
| Creek Rise | Al Khairan First | 30 Jun 2022 | 30 Jun 2022 | On the end date | 547 |
| Reva Residences | Business Bay | 30 Jun 2022 | 30 Jun 2022 | On the end date | 604 |
| Villanova Amaranta 3 | Wadi Al Safa 5 | 30 Jun 2022 | 30 Jun 2022 | On the end date | 322 |
| Stella Maris | Marsa Dubai | 30 Jun 2022 | 30 Jun 2022 | On the end date | 317 |
| Binghatti Gems | Al Barsha South Fourth | 30 Jun 2022 | 30 Jun 2022 | On the end date | 77 |
| ELYSEE II by PANTHEON | Al Barsha South Fourth | 6 Jul 2022 | 6 Jul 2022 | On the end date | 162 |
| Farhad Azizi Residence | Al Jadaf | 14 Jul 2022 | 14 Jul 2022 | On the end date | 662 |
| Orion Building | Al Barshaa South Third | 15 Jul 2022 | 1 Jun 2022 | 1 mo before | 196 |
| Port de La Mer - Le Pont | Jumeirah First | 20 Jul 2022 | 20 Jul 2022 | On the end date | 155 |
| Marbella Village | Al Hebiah Fourth | 1 Aug 2022 | 1 Aug 2022 | On the end date | — |
| V2 | Al Hebiah Fourth | 15 Aug 2022 | 15 Aug 2022 | On the end date | 160 |
| Azizi Riviera 7 | Al Merkadh | 23 Aug 2022 | 23 Aug 2022 | On the end date | 158 |
| Damac Hills (2) - Victoria | Madinat Hind 4 | 25 Aug 2022 | 25 Aug 2022 | On the end date | — |
| Damac Hills (2) - AVENCIA-2 | Madinat Hind 4 | 25 Aug 2022 | 25 Aug 2022 | On the end date | — |
| Damac Hills (2) - Viridis | Madinat Hind 4 | 26 Aug 2022 | 3 Apr 2023 | 7 mo after | 870 |
| Damac Hills (2) - Odora | Madinat Hind 4 | 29 Aug 2022 | 31 Oct 2021 | 9 mo before | — |
| Damac Hills (2) - Aquilegia | Madinat Hind 4 | 29 Aug 2022 | 29 Aug 2022 | On the end date | — |
| Harbour Gate | Al Khairan First | 30 Aug 2022 | 4 Jan 2022 | 7 mo before | 517 |
| Arabian Ranches III - JOY | Wadi Al Safa 5 | 30 Aug 2022 | 30 Aug 2022 | On the end date | 486 |
| Rukan2 | Wadi Al Safa 7 | 30 Aug 2022 | 30 Aug 2022 | On the end date | 49 |
| Downtown Views II | Zaabeel Second | 31 Aug 2022 | 31 Aug 2022 | On the end date | 1,515 |
| Midtown - Mesk | Me'Aisem First | 31 Aug 2022 | 31 Aug 2022 | On the end date | 282 |
| Cambridge Business Centre | Nadd Hessa | 31 Aug 2022 | 30 Apr 2015 | 88 mo before | 116 |
| Intima villas | Al Hebiah Fourth | 1 Sep 2022 | 1 Sep 2022 | On the end date | 21 |
| Joya Blanca Residences | Al Barshaa South Third | 12 Sep 2022 | 12 Sep 2022 | On the end date | 313 |
| Golden Wood Views -1 | Al Barsha South Fifth | 13 Sep 2022 | 13 Sep 2022 | On the end date | 59 |
| Serenity Lakes 5 | Al Barsha South Fourth | 20 Sep 2022 | 20 Sep 2022 | On the end date | 226 |
| 1 Residences | Al Kifaf | 28 Sep 2022 | 28 Sep 2022 | On the end date | 758 |
| Empire Residence | Al Barsha South Fourth | 30 Sep 2022 | 30 Sep 2022 | On the end date | 151 |
| Wavez Residence | Wadi Al Safa 2 | 30 Sep 2022 | 30 Sep 2022 | On the end date | 434 |
| Azizi Riviera 16 | Al Merkadh | 30 Sep 2022 | 30 Sep 2022 | On the end date | 262 |
| Azizi Riviera 14 | Al Merkadh | 30 Sep 2022 | 25 May 2023 | 7 mo after | 228 |
| Azizi Riviera 4 | Al Merkadh | 30 Sep 2022 | 31 Oct 2022 | 1 mo after | 212 |
| Azizi Riviera 17 | Al Merkadh | 30 Sep 2022 | 30 Sep 2022 | On the end date | 211 |
| Azizi Riviera 6 | Al Merkadh | 30 Sep 2022 | 30 Sep 2022 | On the end date | 160 |
| Azizi Riviera 12 | Al Merkadh | 30 Sep 2022 | 30 Sep 2022 | On the end date | 135 |
| Azizi Riviera 10 | Al Merkadh | 30 Sep 2022 | 23 Aug 2022 | 1 mo before | 131 |
| Azizi Riviera 11 | Al Merkadh | 30 Sep 2022 | 13 Sep 2022 | 2 wk before | 135 |
| Azizi Riviera 2 | Al Merkadh | 30 Sep 2022 | 30 Sep 2022 | On the end date | 62 |
| Prime Townhouses | Jabal Ali First | 30 Sep 2022 | 30 Sep 2022 | On the end date | 8 |
| Belvedere | Al Warsan First | 3 Oct 2022 | 31 Jan 2021 | 20 mo before | 141 |
| Creek Beach - Bayshore | Al Khairan First | 6 Oct 2022 | 6 Oct 2022 | On the end date | 305 |
| Creek Beach - Sunset | Al Khairan First | 6 Oct 2022 | 6 Oct 2022 | On the end date | 151 |
| Creek Beach - Breeze | Al Khairan First | 6 Oct 2022 | 6 Oct 2022 | On the end date | 202 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 5 | Al Merkadh | 6 Oct 2022 | 6 Oct 2022 | On the end date | 73 |
| La Rive | Jumeirah First | 19 Oct 2022 | 19 Oct 2022 | On the end date | 284 |
| The Grand | Al Khairan First | 30 Oct 2022 | 30 Oct 2022 | On the end date | 574 |
| Belgravia Heights I | Al Barsha South Fourth | 30 Oct 2022 | 30 Oct 2022 | On the end date | 156 |
| Arabian Ranches III - Spring | Wadi Al Safa 5 | 30 Oct 2022 | 30 Oct 2022 | On the end date | 154 |
| Seven Hotel and Apartments The Palm | Palm Jumeirah | 31 Oct 2022 | 31 Oct 2022 | On the end date | 1,124 |
| Burj Royale | Burj Khalifa | 31 Oct 2022 | 31 Oct 2022 | On the end date | 602 |
| Golf Grove | Hadaeq Sheikh Mohammed Bin Rashid | 31 Oct 2022 | 31 Oct 2022 | On the end date | 166 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 15 | Al Merkadh | 6 Nov 2022 | 6 Nov 2022 | On the end date | 95 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 16 | Al Merkadh | 6 Nov 2022 | 31 Dec 2019 | 34 mo before | 95 |
| Sur La Mer 2 | Jumeirah First | 7 Nov 2022 | 7 Nov 2022 | On the end date | 34 |
| Forte | Burj Khalifa | 29 Nov 2022 | 29 Nov 2022 | On the end date | 927 |
| VIDA Residences Dubai Marina | Marsa Dubai | 30 Nov 2022 | 1 Feb 2022 | 9 mo before | 364 |
| 17 Icon Bay | Al Khairan First | 30 Nov 2022 | 30 Nov 2022 | On the end date | 383 |
| Harrington House | Al Barsha South Fourth | 30 Nov 2022 | 30 Nov 2022 | On the end date | 92 |
| O10 | Al Jadaf | 30 Nov 2022 | 30 Nov 2022 | On the end date | 126 |
| Chaimaa Avenue 2 | Al Barsha South Fourth | 30 Nov 2022 | 30 Nov 2022 | On the end date | 92 |
| Jumeirah Living Marsa Al Arab | Um Suqaim Third | 30 Nov 2022 | 30 Nov 2022 | On the end date | 31 |
| Private Residences Dubai | Jumeirah Second | 8 Dec 2022 | 22 Sep 2022 | 2 mo before | 30 |
| DAMAC Hills (2) - Navitas | Madinat Hind 4 | 8 Dec 2022 | 8 Dec 2022 | On the end date | 304 |
| Il PRIMO | Burj Khalifa | 9 Dec 2022 | 9 Dec 2022 | On the end date | 137 |
| Golf Suites - Dubai Hills | Hadaeq Sheikh Mohammed Bin Rashid | 14 Dec 2022 | 14 Dec 2022 | On the end date | 216 |
| Arabian Ranches III - SUN | Wadi Al Safa 5 | 16 Dec 2022 | 16 Dec 2022 | On the end date | 432 |
| Madinat Jumeriah Living - Phase 2 | Um Suqaim Third | 20 Dec 2022 | 30 Jun 2021 | 17 mo before | 364 |
| Damac Hills (2) - Amargo | Madinat Hind 4 | 25 Dec 2022 | 25 Dec 2022 | On the end date | — |
| Act One | Act Two | Burj Khalifa | 26 Dec 2022 | 20 Jan 2022 | 11 mo before | 787 |
| Seventh Heaven - Ashjar | Wadi Al Safa 3 | 30 Dec 2022 | 30 Dec 2022 | On the end date | 302 |
| Vida Dubai Mall | Burj Khalifa | 30 Dec 2022 | 27 Feb 2022 | 10 mo before | 621 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 21 | Al Merkadh | 30 Dec 2022 | 30 Dec 2022 | On the end date | 31 |
| Edison House | Wadi Al Safa 5 | 30 Dec 2022 | 30 Dec 2022 | On the end date | 65 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 18 | Al Merkadh | 30 Dec 2022 | 30 Dec 2022 | On the end date | 31 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 19 | Al Merkadh | 30 Dec 2022 | 30 Dec 2022 | On the end date | 31 |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 31 | Al Merkadh | 30 Dec 2022 | 30 Dec 2022 | On the end date | 31 |
| Marsa Al Arab Villas | Um Suqaim Third | 30 Dec 2022 | 30 Dec 2021 | 12 mo before | — |
| Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17 | Al Merkadh | 30 Dec 2022 | 30 Dec 2022 | On the end date | 31 |
| Rukan 3 | Wadi Al Safa 7 | 31 Dec 2022 | 16 Jul 2026 | 42 mo after | 1,089 |
| Damac Hills (2) - Mulberry | Madinat Hind 4 | 31 Dec 2022 | 31 Oct 2021 | 14 mo before | — |
| Palace Residences - Dubai Creek Harbour | Al Khairan First | 31 Dec 2022 | 31 Dec 2022 | On the end date | 592 |
| Time 1 | Wadi Al Safa 5 | 31 Dec 2022 | 31 Dec 2022 | On the end date | 286 |
| Azizi Riviera 20 | Al Merkadh | 31 Dec 2022 | 31 Dec 2022 | On the end date | 250 |
| Azizi Riviera 23 | Al Merkadh | 31 Dec 2022 | 31 Dec 2022 | On the end date | 248 |
| Equiti Apartments | Warsan Fourth | 31 Dec 2022 | 31 Dec 2022 | On the end date | 135 |
| Equiti Residence | Jabal Ali First | 31 Dec 2022 | 31 Dec 2022 | On the end date | 90 |
Completed: the completion date DLD records for the project. Source: DLD projects register, export of 1 November 2026.
Months of 2022
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology