DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2277Completed92 units

Harrington House هارينغتون هاوس Al Barsha South Fourth · Jumeirah Village Circle by Ellington Properties Development L.L.CAll phases of Jumeirah Village Circle Completed 30 November 2022 (DLD) DLD end date Nov 2022 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Nov 2022
DLD end date Nov 2022
Build time
23 months
Jan 2021 → Nov 2022
Launch → resale
1,550 AED/sqft
+64.9% on launch Launch 1,018 · 8 sales since completion
1 BR rent
80,000 AED/yr
21 leases, 12 months
Developer
34 projects
16 completed · 2,686 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 20 October 2022 (inspections: 5).
Every DLD inspection and every change in the register %, newest first
Date % built Source
20 October 2022 100% DLD inspection
5 August 2022 85% DLD register, archived export
15 July 2022 85.1% DLD inspection
24 March 2022 53.4% DLD inspection
20 January 2022 42.6% DLD inspection
15 August 2021 20.1% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
23 monthsActual build
23 months
Start date
5 January 2021
DLD end date
30 November 2022
Completion date
30 November 2022
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2277
Escrow agent
Abu Dhabi Islamic Bank
Zoning authority
Trakhees
Master project
Jumeirah Village Circle
DLD area
Al Barsha South Fourth
Units · villas
92 · 0
Start → DLD end
Jan 2021 → Nov 2022
Registered unitsStudio 10 · 1 bed 53 · 2 bed 29; sizes 700–1,003 sqft

Also registered: other units 3.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: (B+G+4+R) Residential Building.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,018 AED/sqft
Median of 33 off-plan sales in the 90 days from the first one (Jan 2022)
Latest registered sales
1,550 AED/sqft
Median of 8 home sales in the last 12 months, ready and off-plan
Change
+64.9%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2022-Q1 to 2026-Q2: +36.9%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
1 BR 995 (19) 1,641 (5) +64.9%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 18 1,641 (5) Nov 2025 – Nov 2026
2 BR 6 — —

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2022-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Barsha South Fourth, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
1,018 AED/sqft
Median of 33 off-plan sales, Jan 2022 – Apr 2022
Resales after completion
1,550 AED/sqft
Median of 8 ready sales, Nov 2025 – Nov 2026
Change
+64.9%
Same home types, weighted by the resales

Over the same span, ready homes in DLD area Al Barsha South Fourth changed +49.8% (same home types).

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 50,000 10 -16.7%
1 BR AED 80,000 21 -2.4%
2 BR AED 100,000 8 -23.1%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 3; the amount shows from 5 registrations.

Since the first registration in 2022-Q4: 32 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.31 AED/sqft a year
Jumeirah Village Circle: median of 112 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 8 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
27 October 2026readyApartment · 2 BR 998 1,350,000 1,353
13 July 2026readyApartment · 1 BR 559 780,000 1,395
13 July 2026readyApartment · 1 BR 484 750,000 1,550
6 March 2026readyApartment · 2 BR 998 1,500,000 1,503
15 January 2026readyApartment · 1 BR 724 1,250,000 1,727
13 January 2026readyApartment · 1 BR 760 1,270,000 1,671
28 November 2025readyApartment · Studio 384 750,000 1,953
12 November 2025readyApartment · 1 BR 774 1,270,000 1,641
24 October 2025readyApartment · 2 BR 1,027 1,800,000 1,753
16 October 2025readyApartment · 2 BR 1,068 1,580,000 1,479

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Barsha South Fourth · Dubai Municipality community

Star Mart Supermarket · 250 mHalfa · 280 mAl Nakhla · 330 mShooa · 330 mSupermarket · 490 mAwadia Grocery · 680 mKinderopvang smallsteps leidsche rijn · 1.1 kmMe'aisem City Center · 1.3 kmCity Centre Meaisem · 1.3 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationJumeirah Golf Estates Metro Station · Red Metro line · 5.3 km
MallMe'aisem City Center · 1.3 km
SupermarketStar Mart Supermarket · 250 m
HospitalMediclinic Springs · 3.1 km
SchoolKinderopvang smallsteps leidsche rijn · 1.1 km
ParkHalfa · 280 m
BeachBeach · 7.4 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 114, with 29,397 units and villas.

2010: 02013: 1652024: 2292025: 1,7482026: 6,6102027: 7,0762028: 6,8902029: 2,6342030: 0No end date: 4,045

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Barsha South Fourth: 153

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Circle 22.1% May 2027 1,611 779
Serenz by Danube 0.1% Dec 2029 2,302 673
Binghatti Amberhall 70% Feb 2026 1,696 623
Binghatti Ruby 65% Feb 2026 1,967 552
One Sky Park By Iman 21.7% Mar 2028 1,650 549
Auresta Tower 4.4% Dec 2028 1,609 523
Skyhills II by HRE 96% Jun 2026 1,531 481
Skyhills III by HRE 75.7% Jun 2026 1,598 418
Legado By Prescott 23.3% Aug 2027 1,748 342
Violet Tower 90.2% Jun 2026 1,345 285
The AUTOGRAPH-I Series 4% Aug 2028 1,691 269
Maison Elysee Iii By Pantheon 4.4% Oct 2027 1,679 260

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Barsha South Fourth

Developer in DLD data Ellington Properties Development L.L.C · DLD developer no. 1117

Projects registered
34
16 completed · 16 under construction · 2 not started
Units delivered
2,686
3,938 in the pipeline
Median build time
33 months
completed projects measured: 16
Past the DLD end date
6
of 12 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 15 completed projects with both dates. In 14 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Ellington Properties Development L.L.C is one of 10 DLD-registered developers we list together as Ellington. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Jumeirah Village Circle

DLD lists 410 projects in the master project Jumeirah Village Circle.

Luxury Family ResidenceUnder construction · 76% · Dec 2023
North Forty Three Serviced ResidencesUnder construction · 94.7% · Jul 2024
7 Park Central By MeteoraUnder construction · 90.2% · Apr 2025
The PortmanUnder construction · 78.7% · Sep 2025
Serenity Lakes 2Under construction · 50.5% · Nov 2025
Levanto By ORO24Under construction · 66% · Dec 2025
Sky Suites by Peace HomesUnder construction · 55.5% · Dec 2025
Ashton Park Residences The SecondUnder construction · 70.1% · Dec 2025
Maimoon GardensUnder construction · 78% · Dec 2025
99 Park PlaceUnder construction · 90% · Dec 2025
Elitz By DanubeUnder construction · 91.8% · Dec 2025
Q Gardens LoftsUnder construction · 90.7% · Dec 2025

Questions about Harrington House

When was Harrington House completed?

Harrington House is recorded as completed on 30 November 2022 (DLD register of 1 November 2026).

Who is the developer of Harrington House?

Ellington Properties Development L.L.C, as registered with DLD.

What is the DLD project number of Harrington House?

2277.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error