Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2161Completed

Marsa Al Arab Villas فلل مرسى العرب Um Suqaim Third by Marsa Al Arab Residences L.L.C Completed 30 December 2021 (DLD) DLD end date Dec 2022 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Madinat Jumeirah waterways with the Burj Al Arab, Umm Suqeim
Area photo: Umm Suqeim, not this project
Completed
Dec 2021
DLD end date Dec 2022
Build time
30 months
Jun 2019 → Dec 2021
Latest sales
—
Fewer than 5 recent sales
Developer
2 projects
2 completed · 31 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 12 June 2023 (inspections: 11).
Every DLD inspection and every change in the register %, newest first
Date % built Source
12 June 2023 100% DLD inspection
2 February 2023 97.1% DLD inspection
31 August 2022 70.7% DLD inspection
5 August 2022 50% DLD register, archived export
29 March 2022 50.1% DLD inspection
7 February 2022 43.7% DLD inspection
26 August 2021 24.1% DLD inspection
21 March 2021 13.4% DLD inspection
5 November 2020 9.8% DLD inspection
20 July 2020 6.2% DLD inspection
8 March 2020 4.8% DLD inspection
24 October 2019 0.3% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
42 monthsActual build
30 months
Start date
24 June 2019
DLD end date
30 December 2022
Completion date
30 December 2021
Completion vs DLD end date
12 months before

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2161
Escrow agent
Emirates Nbd Bank (P.J.S.C)
Zoning authority
Dubai Development Authority (DDA)
DLD area
Um Suqaim Third
Units · villas
0 · 0
Start → DLD end
Jun 2019 → Dec 2022
Registered units5+ bed 9; sizes 16,929–16,976 sqft

Homes: villas 9.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Nine (9) Residential Villas of G+3 with internal and external finishes

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

LocationUmm Suqeim Third · Dubai Municipality community

Jumeirah Public Beach · 550 mUmm Suqeim Park · 680 mThe Mall · 830 mGetchecked Clinic · 830 mMeyan Mall · 1 kmRaffles World Academy · 1.1 kmAl Basher Grocery · 1.2 kmThe Emirates Academy Of Hospitality Management · 1.2 kmBeach · 1.2 kmAl Gazal Alajabali Grocery · 1.3 kmRaffles International School · 1.3 kmBilal Abdul Grocery · 1.4 kmDubai London Clinic & Specialty Hospital · 1.4 kmKings' Dubai · 1.5 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Approximate project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationFirst Abu Dhabi Bank Metro Station · Red Metro line · 3 km
MallThe Mall · 830 m
SupermarketAl Basher Grocery · 1.2 km
HospitalGetchecked Clinic · 830 m
SchoolRaffles World Academy · 1.1 km
ParkUmm Suqeim Park · 680 m
BeachJumeirah Public Beach · 550 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 0, with 0 units and villas.

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Umm Suqeim Third: 3

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Nourelle 4% Mar 2029 4,204 220
Riwa 12.5% — — 28
Elara 64.3% Nov 2026 2,570 13

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Umm Suqeim Third

Developer in DLD data Marsa Al Arab Residences L.L.C · DLD developer no. 1271

Projects registered
2
2 completed · 0 under construction · 0 not started
Units delivered
31
0 in the pipeline

Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Marsa Al Arab Villas

When was Marsa Al Arab Villas completed?

Marsa Al Arab Villas is recorded as completed on 30 December 2021 (DLD register of 1 November 2026).

Who is the developer of Marsa Al Arab Villas?

Marsa Al Arab Residences L.L.C, as registered with DLD.

What is the DLD project number of Marsa Al Arab Villas?

2161.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error