DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan handovers in 2021 79 projects registered to end in 2021 · 78 completed · 1 under construction DLD projects register as of 1 November 2026 · sales to 5 November 2026

79 projects in the Dubai Land Department projects register have an end date in 2021. As of 1 November 2026, 78 are completed, 1 are under construction and 0 have not started. 1 of those under construction are past their DLD end date. These are the DLD end dates registered for each project, not handover forecasts.

Registered to end in 2021
79
projects · 343 units not yet completed
Completed
78
marked completed by DLD
Under construction
1
0 with the end date to come
Not started
0
Not yet active on the DLD register
Under construction, past end date
1
of 1 under construction

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

DLD end dates by month

79 projects

Columns link to their monthly pages. Source: DLD projects register, export of 1 November 2026.

DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.

Not yet completed (1)1 projects with a 2021 DLD end date, by sales over 24 months

1 projects with a 2021 DLD end date, by sales over 24 months
ProjectArea Built DLD end dateTo DLD end date Units
Living Legends Phase 7Wadi Al Safa 3 91.9% 30 Sep 2021 61 mo past 343

Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Completed78 projects with a 2021 DLD end date, marked completed by DLD

78 projects with a 2021 DLD end date, marked completed by DLD
ProjectAreaDLD end dateCompletedAgainst the end date Units
Pantheon ElyseeAl Barsha South Fourth 4 Jan 2021 4 Jan 2021 On the end date 272
Damac Hills - ArtesiaAl Hebiah Third 10 Jan 2021 10 Jan 2021 On the end date 1,246
Sobha Hartland Greens - Phase IIIAl Merkadh 11 Jan 2021 11 Jan 2021 On the end date 507
The Pulse Boulevard Apartments-C1Madinat Al Mataar 11 Jan 2021 2 Apr 2020 9 mo before 147
Azizi MinaPalm Jumeirah 14 Jan 2021 7 Apr 2021 2 mo after 184
Sls DubaiBusiness Bay 17 Jan 2021 17 Jan 2021 On the end date 894
Elite Business Bay ResidenceBusiness Bay 31 Jan 2021 31 Jan 2021 On the end date 540
Royal AmwajPalm Jumeirah 3 Feb 2021 10 Jan 2013 96 mo before 560
Damac Hills (2) - PrimroseMadinat Hind 4 10 Feb 2021 30 Sep 2020 4 mo before —
Damac Hills (2) - AmazoniaMadinat Hind 4 10 Feb 2021 10 Feb 2021 On the end date —
Bloom HeightsAl Barsha South Fourth 28 Feb 2021 28 Feb 2021 On the end date 692
Suncity HomesWarsan Fourth 28 Feb 2021 28 Feb 2021 On the end date 69
Madinat Jumeirah LivingUm Suqaim Third 1 Mar 2021 1 Mar 2021 On the end date 161
Sky Bay HotelBusiness Bay 1 Mar 2021 1 Mar 2021 On the end date 449
AriaAl Barsha South Fourth 10 Mar 2021 10 Mar 2021 On the end date 125
Damac Hills - Golf VitaAl Hebiah Third 15 Mar 2021 15 Mar 2021 On the end date 510
The Pulse Residence PlazaMadinat Al Mataar 15 Mar 2021 15 Mar 2021 On the end date 193
Azizi Shaista ResidenceJabal Ali First 17 Mar 2021 17 Mar 2021 On the end date 297
Mbl ResidenceAl Thanyah Fifth 22 Mar 2021 22 Mar 2021 On the end date 487
Jumeirah GateMarsa Dubai 28 Mar 2021 28 Mar 2021 On the end date 910
Signature LivingsAl Barsha South Fourth 28 Mar 2021 28 Mar 2021 On the end date 276
UnaAl Yelayiss 2 30 Mar 2021 30 Mar 2021 On the end date 480
RigelAl Barsha South Fourth 30 Mar 2021 30 Mar 2021 On the end date 219
The CourtBusiness Bay 31 Mar 2021 31 Mar 2021 On the end date 271
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 4Al Merkadh 31 Mar 2021 31 Mar 2021 On the end date 73
Miraclz TowerAl Barshaa South Third 5 Apr 2021 14 Jul 2019 20 mo before 599
Alandalus Building GMe'Aisem First 28 Apr 2021 28 Apr 2021 On the end date 29
Bayz TowerBusiness Bay 3 May 2021 3 May 2021 On the end date 463
Murano Residence 5Jabal Ali First 16 May 2021 16 May 2021 On the end date —
Living Garden IIAl Barsha South Fourth 19 May 2021 19 May 2021 On the end date 123
Edmonton ElmAl Barsha South Fifth 20 May 2021 20 May 2021 On the end date 65
Damac Hills (2) - JanusiaMadinat Hind 4 30 May 2021 16 Feb 2020 15 mo before —
Serena - Casa VivaWadi Al Safa 7 31 May 2021 31 May 2021 On the end date 494
One At Palm JumeirahPalm Jumeirah 20 Jun 2021 20 Jun 2021 On the end date 94
Downtown ViewsZaabeel Second 21 Jun 2021 21 Jun 2021 On the end date 479
O 2Al Barsha South Fourth 30 Jun 2021 30 Jun 2021 On the end date 323
Jumeirah LuxuryMe'Aisem First 30 Jun 2021 30 Jun 2021 On the end date 165
Binghatti GatewayAl Jadaf 30 Jun 2021 30 Jun 2021 On the end date 182
Millennium Binghatti Residences Business BayBusiness Bay 15 Jul 2021 31 Mar 2021 3 mo before 246
Mohammad Aqil Ali & Ahmad Ali AlzarooniMarsa Dubai 28 Jul 2021 31 Dec 2012 102 mo before —
Sunset GardensAl Barsha South Fourth 28 Jul 2021 30 Jun 2014 84 mo before 12
Villanova Amaranta BWadi Al Safa 5 30 Jul 2021 30 Jul 2021 On the end date 422
La QuintaWadi Al Safa 5 30 Jul 2021 30 Jul 2021 On the end date —
Grenland Residence By arloidWadi Al Safa 3 10 Aug 2021 10 Aug 2021 On the end date 60
Sur La MerJumeirah First 14 Aug 2021 14 Aug 2021 On the end date 113
Mirdif HILLS- Al Multaqa AvenueMirdif 18 Aug 2021 18 Aug 2021 On the end date 489
Damac Hills (2) - AMAZONIA-EXMadinat Hind 4 18 Aug 2021 30 Jun 2021 1 mo before —
Sunrise LegendAl Barshaa South Third 19 Aug 2021 19 Aug 2021 On the end date 112
Damac Hills (2) - MimosaMadinat Hind 4 23 Aug 2021 23 Aug 2021 On the end date —
Damac Hills (2) - TrixisMadinat Hind 4 23 Aug 2021 28 Feb 2021 5 mo before —
Damac Hills (2) - SycamoreMadinat Hind 4 26 Aug 2021 31 Oct 2017 45 mo before —
Sobha Hartland Estates - TownhousesAl Merkadh 8 Sep 2021 8 Sep 2021 On the end date 27
Sama TownhousesAl Yelayiss 2 15 Sep 2021 30 Apr 2021 4 mo before 264
Port de La Mer - La CoteJumeirah First 30 Sep 2021 30 Sep 2021 On the end date 429
Rove City WalkAl Wasl 30 Sep 2021 30 Sep 2021 On the end date 517
Oxford BoulevardAl Barsha South Fourth 6 Oct 2021 6 Oct 2021 On the end date 131
Sunrise BayMarsa Dubai 31 Oct 2021 31 Oct 2021 On the end date 461
Club Villas at Dubai HillsHadaeq Sheikh Mohammed Bin Rashid 31 Oct 2021 31 Oct 2021 On the end date 150
K1Wadi Al Safa 5 14 Nov 2021 14 Nov 2021 On the end date 144
The CoveAl Khairan First 17 Nov 2021 17 Nov 2021 On the end date 291
Park View TowerAl Barsha South Fourth 17 Nov 2021 17 Nov 2021 On the end date 280
AR II Camelia 2Wadi Al Safa 7 17 Nov 2021 17 Nov 2021 On the end date 168
Creek GateAl Khairan First 18 Nov 2021 18 Nov 2021 On the end date 498
Majestique Residence 2Madinat Al Mataar 21 Nov 2021 21 Nov 2021 On the end date 60
Terhab Hotel & Towers At Jumeirah Village TriangleAl Barsha South Fifth 25 Nov 2021 25 Nov 2021 On the end date 943
The Palm TowerPalm Jumeirah 30 Nov 2021 30 Nov 2021 On the end date 442
Opera GrandBurj Khalifa 9 Dec 2021 9 Dec 2021 On the end date 306
The Anwa By OmniyatMadinat Dubai Almelaheyah 13 Dec 2021 15 Nov 2021 4 wk before 233
Villa AmalfiIsland 2 15 Dec 2021 15 Dec 2021 On the end date 68
Remraam - Al RamthAl Hebiah Fifth 16 Dec 2021 16 Dec 2021 On the end date 946
J OneBusiness Bay 28 Dec 2021 28 Dec 2021 On the end date 353
Belgravia IiiAl Barsha South Fourth 29 Dec 2021 29 Dec 2021 On the end date 260
Park VistaAl Barsha South Fourth 30 Dec 2021 30 Dec 2021 On the end date 73
ZaZEN OneAl Barsha South Fifth 30 Dec 2021 30 Dec 2021 On the end date 86
ParksideMadinat Al Mataar 31 Dec 2021 31 Dec 2021 On the end date 371
Wilton TerracesAl Merkadh 31 Dec 2021 5 Jan 2022 5 d after 283
Majestique Residence 1Madinat Al Mataar 31 Dec 2021 31 Dec 2021 On the end date 124
Sobha Hartland Villas - Phase IIAl Merkadh 31 Dec 2021 31 Dec 2021 On the end date —

Completed: the completion date DLD records for the project. Source: DLD projects register, export of 1 November 2026.

Months of 2021

Other years: 2020 · 2022

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. The DLD end date is the date registered with DLD; your SPA may give another. Methodology