Dubai off-plan handovers in 2020 112 projects registered to end in 2020 · 111 completed · 1 under construction DLD projects register as of 1 November 2026 · sales to 5 November 2026
112 projects in the Dubai Land Department projects register have an end date in 2020. As of 1 November 2026, 111 are completed, 1 are under construction and 0 have not started. 1 of those under construction are past their DLD end date. These are the DLD end dates registered for each project, not handover forecasts.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
DLD end dates by month
112 projects| Month | Completed | Not yet completed | Past the DLD end date |
|---|---|---|---|
| January | 9 | 0 | 0 |
| February | 17 | 1 | 1 |
| March | 17 | 0 | 0 |
| April | 15 | 0 | 0 |
| May | 17 | 0 | 0 |
| June | 11 | 0 | 0 |
| July | 5 | 0 | 0 |
| August | 2 | 0 | 0 |
| September | 4 | 0 | 0 |
| October | 7 | 0 | 0 |
| November | 1 | 0 | 0 |
| December | 6 | 0 | 0 |
Columns link to their monthly pages. Source: DLD projects register, export of 1 November 2026.
DLD can change a project’s end date; the dates here are those in the latest export. In most completed projects the end date in the register equals the completion date, so a completed project counted here may have had a different end date before.
Not yet completed (1)1 projects with a 2020 DLD end date, by sales over 24 months
| Project | Area | Built | DLD end date | To DLD end date | Units |
|---|---|---|---|---|---|
| South Living | Madinat Al Mataar | 88.8% | 5 Feb 2020 | 80 mo past | 209 |
Months counted from the register date. Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Completed111 projects with a 2020 DLD end date, marked completed by DLD
| Project | Area | DLD end date | Completed | Against the end date | Units |
|---|---|---|---|---|---|
| Sobha Hartland Greens Phase Ii | Al Merkadh | 6 Jan 2020 | 6 Jan 2020 | On the end date | 354 |
| Azizi Samia Residence | Jabal Ali First | 9 Jan 2020 | 9 Jan 2020 | On the end date | 296 |
| Mirdif HILLS- Janayen Avenue | Mirdif | 12 Jan 2020 | 12 Jan 2020 | On the end date | 359 |
| AR II - Reem Community | Wadi Al Safa 7 | 13 Jan 2020 | 9 Dec 2019 | 1 mo before | 131 |
| The Pulse Residence Icon | Madinat Al Mataar | 14 Jan 2020 | 14 Jan 2020 | On the end date | 99 |
| Reem - Mira Oasis Community Phase 3 | Al Yelayiss 1 | 19 Jan 2020 | 30 Jul 2019 | 5 mo before | 483 |
| Acacia At Park Heights | Hadaeq Sheikh Mohammed Bin Rashid | 19 Jan 2020 | 1 Sep 2019 | 4 mo before | 551 |
| Topaz Residences 3 | Nadd Hessa | 20 Jan 2020 | 20 Jan 2020 | On the end date | 112 |
| Binghatti Stars | Nadd Hessa | 28 Jan 2020 | 1 Oct 2019 | 3 mo before | 362 |
| Resortz Residence | Al Barshaa South Third | 3 Feb 2020 | 30 Sep 2019 | 4 mo before | 444 |
| Mag 5 Boulevard | Madinat Al Mataar | 6 Feb 2020 | 6 Feb 2020 | On the end date | 1,452 |
| Dezire Residences | Al Barsha South Fourth | 6 Feb 2020 | 30 Aug 2019 | 5 mo before | 120 |
| Jumeirah Golf Estates - Hillside | Me'Aisem First | 9 Feb 2020 | 9 Feb 2020 | On the end date | — |
| Boulevard Point | Burj Khalifa | 10 Feb 2020 | 17 Dec 2019 | 1 mo before | 449 |
| Sol Bay | Business Bay | 11 Feb 2020 | 15 Jan 2015 | 60 mo before | 325 |
| Zhoug guo jia | Al Warsan First | 11 Feb 2020 | 11 Feb 2020 | On the end date | — |
| Burj Sabah | Al Barsha South Fourth | 12 Feb 2020 | 12 Feb 2020 | On the end date | — |
| The Pulse Residence | Madinat Al Mataar | 16 Feb 2020 | 16 Jun 2019 | 8 mo before | 239 |
| The Pulse Boulevard Apartments | Madinat Al Mataar | 16 Feb 2020 | 31 Dec 2019 | 1 mo before | 169 |
| Rawda Apartments | Al Yelayiss 2 | 20 Feb 2020 | 20 Feb 2020 | On the end date | 748 |
| Grand Views | Nad Al Shiba First | 24 Feb 2020 | 15 Nov 2019 | 3 mo before | 305 |
| Mudon Views | Al Hebiah Sixth | 25 Feb 2020 | 25 Feb 2020 | On the end date | 181 |
| Genesis | Al Barshaa South Third | 25 Feb 2020 | 25 Feb 2020 | On the end date | 200 |
| Merano Tower | Business Bay | 27 Feb 2020 | 27 Feb 2020 | On the end date | 581 |
| The Pulse Townhouses | Madinat Al Mataar | 27 Feb 2020 | 27 Feb 2020 | On the end date | 240 |
| Hayat Boulevard | Al Yelayiss 2 | 29 Feb 2020 | 29 Feb 2020 | On the end date | 678 |
| Midtown - Dania | Me'Aisem First | 1 Mar 2020 | 1 Mar 2020 | On the end date | 591 |
| Mirdif HILLS- Nasayem Avenue | Mirdif | 3 Mar 2020 | 3 Mar 2020 | On the end date | 407 |
| GardeniaTownHomes @ wasl gate | Jabal Ali First | 3 Mar 2020 | 3 Mar 2020 | On the end date | — |
| The One Jbr | Marsa Dubai | 6 Mar 2020 | 6 Mar 2020 | On the end date | 164 |
| Hyati Avenue | Al Barsha South Fourth | 9 Mar 2020 | 9 Mar 2020 | On the end date | 122 |
| Al Jawhara Tower | Al Barsha South Fifth | 12 Mar 2020 | 12 Mar 2020 | On the end date | 532 |
| Azizi Farishta Residence | Jabal Ali First | 16 Mar 2020 | 31 Mar 2020 | 2 wk after | 295 |
| Canal Residence West 2 | Al Hebiah Fourth | 18 Mar 2020 | 18 Mar 2020 | On the end date | 400 |
| The Pearl | Al Jadaf | 25 Mar 2020 | 31 Dec 2015 | 50 mo before | 61 |
| Urbana | Madinat Al Mataar | 26 Mar 2020 | 10 Sep 2019 | 6 mo before | 324 |
| Dt 1 | Burj Khalifa | 30 Mar 2020 | 30 Mar 2020 | On the end date | 133 |
| The Pulse Residence Park | Madinat Al Mataar | 30 Mar 2020 | 30 Mar 2020 | On the end date | 190 |
| Park Heights Ii | Hadaeq Sheikh Mohammed Bin Rashid | 31 Mar 2020 | 31 Mar 2020 | On the end date | 557 |
| Park Heights I | Hadaeq Sheikh Mohammed Bin Rashid | 31 Mar 2020 | 31 Mar 2020 | On the end date | 275 |
| Mohammed Bin Rashid Al Maktoum CITY-DISTRICT One Phase Ii Villas | Al Merkadh | 31 Mar 2020 | 31 Mar 2020 | On the end date | — |
| Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1 | Al Merkadh | 31 Mar 2020 | 31 Mar 2020 | On the end date | — |
| Dar Al Jawhara | Al Barsha South Fourth | 31 Mar 2020 | 31 Mar 2020 | On the end date | 117 |
| Liv Residence | Marsa Dubai | 1 Apr 2020 | 1 Apr 2020 | On the end date | 190 |
| Qpoint LIWAN-PLOT R081 | Wadi Al Safa 2 | 2 Apr 2020 | 15 Dec 2014 | 63 mo before | 95 |
| ALandalus Building D | Me'Aisem First | 4 Apr 2020 | 4 Apr 2020 | On the end date | 136 |
| Hameni | Al Barsha South Fourth | 5 Apr 2020 | 5 Apr 2020 | On the end date | 504 |
| Damac Hills - The Trump Estates | Al Hebiah Third | 11 Apr 2020 | 30 Jun 2016 | 45 mo before | — |
| Q-Zone (Qpoint - Phase III), MU005&6 | Wadi Al Safa 2 | 14 Apr 2020 | 14 Apr 2020 | On the end date | 328 |
| Rp Heights | Burj Khalifa | 15 Apr 2020 | 15 Apr 2020 | On the end date | 296 |
| Oxford Residence 2 | Al Barsha South Fourth | 27 Apr 2020 | 10 Mar 2020 | 1 mo before | 147 |
| Blvd Heights | Burj Khalifa | 30 Apr 2020 | 30 Apr 2020 | On the end date | 558 |
| Park Point | Hadaeq Sheikh Mohammed Bin Rashid | 30 Apr 2020 | 30 Apr 2020 | On the end date | 338 |
| Prime Views | Nad Al Shiba First | 30 Apr 2020 | 2 Mar 2021 | 10 mo after | 153 |
| Urbana Ii | Madinat Al Mataar | 30 Apr 2020 | 30 Apr 2020 | On the end date | 236 |
| Villanova Amaranta A | Wadi Al Safa 5 | 30 Apr 2020 | 30 Apr 2020 | On the end date | 154 |
| Al Haseen Residence | Saih Shuaib 2 | 30 Apr 2020 | 30 Apr 2020 | On the end date | 138 |
| Shorooq Land 2 | Wadi Al Safa 5 | 30 Apr 2020 | 30 Apr 2020 | On the end date | 253 |
| Serena Casa Dora | Wadi Al Safa 7 | 12 May 2020 | 12 May 2020 | On the end date | 578 |
| Arabella 2 - Townhouses At Mudon | Al Hebiah Sixth | 14 May 2020 | 14 May 2020 | On the end date | — |
| Oasis Tower One | Al Hebiah Fourth | 14 May 2020 | 14 May 2020 | On the end date | 221 |
| Golf Views | Madinat Al Mataar | 15 May 2020 | 15 May 2020 | On the end date | 291 |
| Banyan Tree Residences Hillside Dubai | Al Thanyah Fifth | 15 May 2020 | 15 May 2020 | On the end date | 236 |
| Maple III | Hadaeq Sheikh Mohammed Bin Rashid | 17 May 2020 | 17 May 2020 | On the end date | 562 |
| Ag Tower | Business Bay | 22 May 2020 | 6 Jul 2021 | 13 mo after | 590 |
| Golf Links | Madinat Al Mataar | 30 May 2020 | 30 May 2020 | On the end date | 1 |
| Sol Avenue | Business Bay | 30 May 2020 | 15 Feb 2017 | 39 mo before | 324 |
| Azizi Aura Residences | Jabal Ali Industrial Second | 31 May 2020 | 20 Dec 2020 | 6 mo after | 487 |
| Creekside 18 | Al Khairan First | 31 May 2020 | 31 May 2020 | On the end date | 506 |
| Urbana Iii | Madinat Al Mataar | 31 May 2020 | 31 May 2020 | On the end date | 372 |
| Eagle Heights | Al Hebiah Fourth | 31 May 2020 | 31 Dec 2013 | 77 mo before | 291 |
| Beverly Residence | Al Barsha South Fourth | 31 May 2020 | 11 Feb 2021 | 8 mo after | 195 |
| 2020 Marquis | Al Barshaa South Third | 31 May 2020 | 31 May 2020 | On the end date | 150 |
| Azizi Plaza Hotel Apartments | Jabal Ali First | 31 May 2020 | 3 Nov 2021 | 17 mo after | 448 |
| The One Hotel | Business Bay | 31 May 2020 | 30 Sep 2019 | 8 mo before | 504 |
| Jumeirah Living Marina Gate | Marsa Dubai | 7 Jun 2020 | 7 Jun 2020 | On the end date | 418 |
| Golden Wood Views | Al Barsha South Fifth | 11 Jun 2020 | 11 Jun 2020 | On the end date | 60 |
| Chaimaa Avenue | Al Barsha South Fourth | 12 Jun 2020 | 12 Jun 2020 | On the end date | 89 |
| Wadi Tower | Wadi Al Safa 4 | 14 Jun 2020 | 14 Jun 2020 | On the end date | 202 |
| Plazzo Heights | Al Barsha South Fourth | 15 Jun 2020 | 15 Jun 2020 | On the end date | 116 |
| Noor Townhouses | Al Yelayiss 2 | 30 Jun 2020 | 30 Jun 2020 | On the end date | 764 |
| Sidra 3 | Hadaeq Sheikh Mohammed Bin Rashid | 30 Jun 2020 | 30 Jun 2020 | On the end date | 1 |
| W Residences Dubai - The Palm | Palm Jumeirah | 30 Jun 2020 | 30 Jun 2020 | On the end date | 106 |
| Sobha Hartland VILLAS-PHASE 1 | Al Merkadh | 30 Jun 2020 | 30 Jun 2020 | On the end date | — |
| Avalon Tower | Al Barsha South Fourth | 30 Jun 2020 | 30 Jun 2020 | On the end date | 362 |
| The One | Al Barsha South Fourth | 30 Jun 2020 | 30 Jun 2020 | On the end date | 501 |
| Uniestate Prime Tower | Al Barsha South Fourth | 2 Jul 2020 | 22 Sep 2012 | 93 mo before | 138 |
| Laya Mansion | Al Barsha South Fourth | 6 Jul 2020 | 6 Jul 2020 | On the end date | 239 |
| Bellevue Towers | Burj Khalifa | 30 Jul 2020 | 30 Jul 2020 | On the end date | 365 |
| Arabella 3 | Al Hebiah Sixth | 31 Jul 2020 | 31 Jul 2020 | On the end date | — |
| The 50 | Wadi Al Safa 3 | 31 Jul 2020 | 31 Jul 2020 | On the end date | 60 |
| Bloom Towers | Al Barsha South Fourth | 7 Aug 2020 | 16 Feb 2021 | 6 mo after | 944 |
| Alandalus Building E | Me'Aisem First | 31 Aug 2020 | 31 Aug 2020 | On the end date | 89 |
| 5242 | Marsa Dubai | 5 Sep 2020 | 5 Sep 2020 | On the end date | 493 |
| Seventh Heaven | Wadi Al Safa 3 | 8 Sep 2020 | 8 Sep 2020 | On the end date | 223 |
| Royal Park | Al Thanyah Fifth | 14 Sep 2020 | 14 Sep 2020 | On the end date | 40 |
| Creek Horizon | Al Khairan First | 19 Sep 2020 | 19 Sep 2020 | On the end date | 559 |
| Arabian Gate | Nadd Hessa | 1 Oct 2020 | 1 Oct 2020 | On the end date | 716 |
| ALandalus Townhouse | Me'Aisem First | 5 Oct 2020 | 30 Apr 2020 | 5 mo before | — |
| Vincitore Boulevard | Al Barshaa South Third | 8 Oct 2020 | 8 Oct 2020 | On the end date | 248 |
| The Pad | Business Bay | 14 Oct 2020 | 1 Jul 2020 | 3 mo before | 265 |
| Park Gate Residences | Al Kifaf | 15 Oct 2020 | 15 Oct 2020 | On the end date | 764 |
| Glamz Residence | Jabal Ali First | 22 Oct 2020 | 22 Oct 2020 | On the end date | 426 |
| Dolphin Tower | Business Bay | 30 Oct 2020 | 30 Oct 2020 | On the end date | 340 |
| Harbour Views | Al Khairan First | 5 Nov 2020 | 24 Apr 2020 | 6 mo before | 784 |
| Mag 318 | Business Bay | 6 Dec 2020 | 6 Dec 2020 | On the end date | 451 |
| Samana Green | Al Barshaa South Third | 14 Dec 2020 | 14 Dec 2020 | On the end date | 122 |
| Naseem Townhouses | Al Yelayiss 2 | 21 Dec 2020 | 1 Dec 2020 | 2 wk before | 322 |
| Bella Rose | Al Barshaa South Second | 27 Dec 2020 | 27 Dec 2020 | On the end date | 490 |
| The Pulse Boulevard Apartments - C3 | Madinat Al Mataar | 30 Dec 2020 | 30 Mar 2020 | 9 mo before | 157 |
| The Square | Al Barsha South Fourth | 31 Dec 2020 | 31 Dec 2020 | On the end date | 370 |
Completed: the completion date DLD records for the project. Source: DLD projects register, export of 1 November 2026.