Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2087Completed340 units

Dolphin Tower دولفين تاور Business Bay by T F G Real Estate L.L.CAll phases of Business Bay Completed 30 October 2020 (DLD) DLD end date Oct 2020 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Business Bay towers along the Dubai Water Canal from above
Area photo: Business Bay, not this project
Completed
Oct 2020
DLD end date Oct 2020
Build time
40 months
Jul 2017 → Oct 2020
Latest sales
—
Fewer than 5 recent sales
Developer
15 projects
15 completed · 7,039 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 8 December 2020 (inspections: 9).
Every DLD inspection and every change in the register %, newest first
Date % built Source
8 December 2020 100% DLD inspection
12 August 2020 97% DLD inspection
16 April 2020 90.3% DLD inspection
19 December 2019 84.8% DLD inspection
29 August 2019 73.5% DLD inspection
22 April 2019 60.3% DLD inspection
16 January 2019 50.2% DLD inspection
20 November 2018 41.9% DLD inspection
5 August 2018 30.3% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
40 monthsActual build
40 months
Start date
1 July 2017
DLD end date
30 October 2020
Completion date
30 October 2020
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Completed.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
189807
Issued
1 November 2016
Work start
1 November 2016
Completion
15 July 2020
Consultant · contractor
DXB DESIGN STUDIO · MODERN EXECUTIVE SYSTEMS CONTRACTING (MESC) (L.L.C)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Completed1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
2087
Escrow agent
Emirates Nbd Bank (P.J.S.C)
Zoning authority
Dubai Development Authority (DDA)
Master project
Business Bay
DLD area
Business Bay
Units · villas
340 · 0
Start → DLD end
Jul 2017 → Oct 2020
Registered unitsStudio 307 · 1 bed 20; sizes 418–529 sqft

Homes: hotel apartments and rooms 327.

Also registered: offices 3 · shops and showrooms 10.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Hotel rooms building 2B+G+3P+16 TYP+HC with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
19.98 AED/sqft a year
Business Bay: median of 71 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

LocationBusiness Bay · Dubai Municipality community

Al Reyhan Mini Mart · 360 mSupermarket · 390 mQ Mini Mart · 520 mPark · 580 mBayside Park 5 · 610 mBayside Park 3 · 660 mBIOS CLINIC · 1.2 kmBeach · 1.3 kmBeach · 1.5 kmSouk Al Bahar · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationBurj Khalifa/ Dubai Mall Metro Station · Red Metro line · 2.5 km
MallSouk Al Bahar · 1.5 km
SupermarketAl Reyhan Mini Mart · 360 m
HospitalBIOS CLINIC · 1.2 km
SchoolHartland International School · 2.1 km
ParkPark · 580 m
BeachBeach · 1.3 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 43, with 15,958 units and villas.

2023: 1452025: 1052026: 8,2342027: 4,7602028: 2922029: 4142030: 2182031: 484No end date: 1,306

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Business Bay: 53

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Skyrise 35.9% Dec 2026 3,040 3,281
Binghatti Aquarise 21% Oct 2026 2,621 1,348
Al Habtoor Tower 90% Dec 2026 2,771 779
Bayz 102 By Danube 6.5% Dec 2029 3,060 724
Binghatti Skyhall 31.1% Aug 2026 2,430 648
One by Binghatti 50.2% May 2026 2,921 574
Downtown Residences 1.3% Dec 2030 2,766 401
Onda By Kasco 61.1% Aug 2027 1,820 299
Tiger Sky Tower 10.2% — 2,142 296
Rove Home Marasi Drive 10% Aug 2027 3,299 283
One.B Tower 10.1% Dec 2028 2,725 180
One River Point 35.4% Jun 2027 2,643 175

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Business Bay

Developer in DLD data T F G Real Estate L.L.C · DLD developer no. 29

Projects registered
15
15 completed · 0 under construction · 0 not started
Units delivered
7,039
0 in the pipeline
Median build time
44 months
completed projects measured: 14

Completed a month or more after their DLD end date: 1 of 15 completed projects with both dates. In 13 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Business Bay

DLD lists 150 projects in the master project Business Bay.

Burj PacificUnder construction · 98.8% · Jan 2023
West Bay TowerUnder construction · 82.5% · Feb 2024
Luxury Family Residence IIIUnder construction · 50.6% · Jun 2025
Chic TowerUnder construction · 84% · Jul 2025
Bugatti Residences by BinghattiUnder construction · 65.6% · Dec 2025
The QuaysideUnder construction · 54.6% · Mar 2026
Eywa DubaiUnder construction · 65.7% · Apr 2026
One by BinghattiUnder construction · 50.2% · May 2026
Urban LifeUnder construction · 80% · Jun 2026
Burj Binghatti Jacob & Co. ResidencesUnder construction · 52.1% · Jun 2026
Binghatti SkyhallUnder construction · 31.1% · Aug 2026
Binghatti AquariseUnder construction · 21% · Oct 2026

Questions about Dolphin Tower

When was Dolphin Tower completed?

Dolphin Tower is recorded as completed on 30 October 2020 (DLD register of 1 November 2026).

Who is the developer of Dolphin Tower?

T F G Real Estate L.L.C, as registered with DLD.

What is the DLD project number of Dolphin Tower?

2087.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error