DLD master projectBusiness Bay
Business Bay 43 of 151 phases not yet completed · 16,462 units · 14,045 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Business Bay has 151 projects in the Dubai Land Department projects register as of 1 November 2026: 43 not yet completed, with 16,462 units and villas. By DLD status: Under construction 33 · Completed 108 · Not started 7 · Conditionally activating 1 · Pending 2. Under construction and past the DLD end date: 11.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 150 of the 151 phases: those with a map pin. Pins mark approximate locations.
Business Bay (DM community)
Phases (151)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Binghatti Skyrise | Under construction | 35.9% | Dec 2026 1 month to go | 1 month to go | 3,358 | 3,281 | +33.8% |
| Binghatti Aquarise | Under construction | 21% | Oct 2026 This month | This month | 1,592 | 1,348 | +7.2% |
| Binghatti Skyhall | Under construction | 31.1% | Aug 2026 2 months past it | 2 months past it | 728 | 648 | +0.4% |
| One by Binghatti | Under construction | 50.2% | May 2026 5 months past it | 5 months past it | 755 | 574 | +25.1% |
| Peninsula Four | Completed | 100% | Jun 2026 | — | 1,038 | 333 | +7.7% |
| Peninsula Three | Completed | 100% | Dec 2025 | — | 859 | 303 | +26% |
| Onda By Kasco | Under construction | 61.1% | Aug 2027 9 months to go | 9 months to go | 352 | 299 | -16% |
| Tiger Sky Tower | Under construction | 10.2% | — | — | 849 | 296 | — |
| Rove Home Marasi Drive | Under construction | 10% | Aug 2027 9 months to go | 9 months to go | 811 | 283 | +11.9% |
| The EDGE | Completed | 100% | Aug 2026 | — | 1,030 | 259 | +8.8% |
| Damac Towers By Paramount | Completed | 100% | Oct 2018 | — | 2,041 | 253 | — |
| Regalia | Completed | 100% | Apr 2026 | — | 913 | 207 | +26.6% |
| Prive By Damac | Completed | 100% | Sep 2019 | — | 1,056 | 202 | — |
| Nobles | Completed | 100% | Aug 2024 | — | 562 | 194 | — |
| Peninsula One | Completed | 100% | Apr 2024 | — | 525 | 192 | +49.6% |
| Peninsula Two | Completed | 100% | Feb 2026 | — | 462 | 179 | +48% |
| One River Point | Under construction | 35.4% | Jun 2027 7 months to go | 7 months to go | 298 | 175 | +2.2% |
| UPSIDE Living | Completed | 100% | Feb 2023 | — | 527 | 171 | — |
| Peninsula Five | Completed | 100% | Dec 2024 | — | 383 | 165 | +34.1% |
| Avarra by Palace | Not started | 0.1% | Jun 2031 55 months to go | 55 months to go | 694 | 159 | — |
| Zada Tower | Completed | 100% | Jun 2023 | — | 703 | 151 | — |
| Royal Regency Suites | Under construction | 56.2% | Dec 2026 1 month to go | 1 month to go | 238 | 130 | +34.3% |
| Urban Oasis | Completed | 100% | Jun 2024 | — | 467 | 117 | — |
| Urban Life | Under construction | 80% | Jun 2026 4 months past it | 4 months past it | 147 | 115 | — |
| Reva Residences | Completed | 100% | Jun 2022 | — | 604 | 110 | — |
| Sls Dubai | Completed | 100% | Jan 2021 | — | 894 | 109 | — |
| Canal Heights | Under construction | 36.3% | Dec 2026 1 month to go | 1 month to go | 415 | 102 | +0.8% |
| Merano Tower | Completed | 100% | Feb 2020 | — | 581 | 101 | — |
| 15 Northside | Completed | 100% | Apr 2023 | — | 358 | 96 | +45.7% |
| Burj Binghatti Jacob & Co. Residences | Under construction | 52.1% | Jun 2026 4 months past it | 4 months past it | 325 | 95 | — |
| Bugatti Residences by Binghatti | Under construction | 65.6% | Dec 2025 10 months past it | 10 months past it | 187 | 94 | — |
| Ag Tower | Completed | 100% | Jul 2021 | — | 590 | 92 | — |
| Bay Square | Completed | 100% | Aug 2014 | — | 1,023 | 89 | — |
| Trillionaire Residences by Binghatti | Completed | 100% | Jun 2024 | — | 369 | 85 | -10.8% |
| The Crestmark | Under construction | 61.2% | — | — | 191 | 84 | -3.8% |
| Canal Heights 2 | Under construction | 36.4% | Mar 2027 4 months to go | 4 months to go | 505 | 83 | -0.2% |
| Canal Crown | Under construction | 42.2% | Feb 2027 3 months to go | 3 months to go | 327 | 82 | — |
| Churchill Tower | Completed | 100% | Feb 2009 | — | 1,168 | 82 | — |
| Elite Business Bay Residence | Completed | 100% | Jan 2021 | — | 540 | 82 | — |
| Royal Regency | Completed | 100% | Nov 2025 | — | 165 | 81 | — |
| The Paragon By IGO | Completed | 100% | May 2025 | — | 328 | 80 | +36.7% |
| Marquise Square Tower | Completed | 100% | Mar 2019 | — | 428 | 78 | — |
| Bayz Tower | Completed | 100% | May 2021 | — | 463 | 78 | — |
| Vera Tower | Completed | 100% | Mar 2022 | — | 526 | 75 | — |
| Majestine | Completed | 100% | Jul 2018 | — | 506 | 72 | — |
| Mag 318 | Completed | 100% | Dec 2020 | — | 451 | 71 | — |
| The Cosmopolitan | Completed | 100% | Mar 2014 | — | 368 | 70 | — |
| Scala Tower | Completed | 100% | Sep 2010 | — | 188 | 69 | — |
| Ontario Tower | Completed | 100% | Aug 2010 | — | 300 | 68 | — |
| Chic Tower | Under construction | 84% | Jul 2025 15 months past it | 15 months past it | 467 | 67 | +3% |
| Vyb | Completed | 100% | Jun 2026 | — | 181 | 66 | +3.9% |
| DG1 Living | Under construction | 65% | Apr 2027 5 months to go | 5 months to go | 249 | 64 | — |
| The Sterling East House | Completed | 100% | Aug 2023 | — | 222 | 63 | — |
| West Bay Tower | Under construction | 82.5% | Feb 2024 32 months past it | 32 months past it | 253 | 62 | — |
| Binghatti Canal | Completed | 100% | Jun 2023 | — | 306 | 62 | +28.2% |
| The Pad | Completed | 100% | Jul 2020 | — | 265 | 59 | — |
| Canal Crown 2 | Under construction | 32.5% | Mar 2027 4 months to go | 4 months to go | 351 | 58 | — |
| The Sterling West House | Completed | 100% | May 2023 | — | 187 | 56 | — |
| U-BORA Towers | Completed | 100% | Jan 2011 | — | 305 | 55 | — |
| Century | Completed | 100% | Feb 2026 | — | 214 | 53 | -0.9% |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
43 phases| DLD end year | Projects | Units |
|---|---|---|
| 2023 | 1 | 145 |
| 2024 | 1 | 253 |
| 2025 | 3 | 726 |
| 2026 | 11 | 8,114 |
| 2027 | 11 | 3,155 |
| 2028 | 6 | 1,094 |
| 2029 | 3 | 690 |
| 2030 | 1 | 99 |
| 2031 | 2 | 880 |
| No end date | 4 | 1,306 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Business Bay
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology