Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1366Completed

Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1 محمد بن راشد ال مكتوم سيتي- ديسترك ون، فيس ون Al Merkadh by District One - FZ Completed 31 March 2020 (DLD) DLD end date Mar 2020 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Mar 2020
DLD end date Mar 2020
Build time
83 months
May 2013 → Mar 2020
Latest sales
2,356 AED/sqft
7 sales
4 BR rent
820,000 AED/yr
12 leases, 12 months
Developer
38 projects
36 completed · 1,752 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 24 September 2020 (inspections: 17).
Every DLD inspection and every change in the register %, newest first
Date % built Source
24 September 2020 100% DLD inspection
12 March 2019 95% DLD inspection
17 April 2018 90.1% DLD inspection
13 February 2018 88.2% DLD inspection
8 November 2017 87% DLD inspection
19 July 2017 85.3% DLD inspection
14 May 2017 80.2% DLD inspection
12 January 2017 75.1% DLD inspection
24 October 2016 66.1% DLD inspection
21 August 2016 61.1% DLD inspection
20 July 2016 60% DLD inspection
15 June 2016 55.4% DLD inspection
25 April 2016 50.2% DLD inspection
17 February 2016 39.3% DLD inspection
11 November 2015 27.8% DLD inspection
11 August 2015 17.5% DLD inspection
12 February 2015 10.3% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
83 monthsActual build
83 months
Start date
1 May 2013
DLD end date
31 March 2020
Completion date
31 March 2020
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

11 of 11 buildings

Buildings on the project’s plots: 11, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Final works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
11
1 on construction permits
Permit status
Open
226802
Issued
17 August 2014
Work start
17 August 2014
Expected completion
31 January 2014
Consultant · contractor
AE SEVEN MORSE ARCHITECTURE & ENGINEERING CONSULTANCIES CO L.L.C · SOBHA ENGINEERING & CONTRACTING L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Final works11

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1366
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Municipality
DLD area
Al Merkadh
Units · villas
0 · 0
Start → DLD end
May 2013 → Mar 2020
Registered units4 bed 116 · 5+ bed 187; sizes 6,625–9,090 sqft

Homes: villas 303.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: The project contains 303villas, the villas are fully detached G+1 with sizes varying from 4,5, 6, 7, 7+ &8 bedrooms of 3 different design styles Contemporary, Miditerranean & Modern Arabic with external and internal finishes

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over villas and townhouses, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Merkadh, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
4 BR AED 820,000 12 -13.7%
5 BR AED 1,050,000 14 -19.2%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 13; registered amount AED 189.2M.

Since the first registration in 2015-Q2: 289 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
26.22 AED/sqft a year
Meydan: median of 83 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 15 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
2 November 2026readyVilla 7,725 21,000,000 2,718
29 October 2026readyVilla 8,622 20,000,000 2,320
24 August 2026readyVilla 8,490 20,000,000 2,356
22 July 2026readyVilla 7,878 16,800,000 2,133
30 June 2026readyVilla 7,535 14,000,000 1,858
12 June 2026readyVilla 9,761 26,000,000 2,664
8 May 2026readyVilla 7,725 21,000,000 2,718
24 April 2026readyVilla 8,353 31,700,000 3,795
22 April 2026readyVilla 15,790 50,000,000 3,167
5 March 2026readyVilla 7,878 19,515,000 2,477

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Merkadh · Dubai Municipality community

Beach · 460 mBeach · 510 mPark · 650 mallday · 680 mAl Quoz Pond Park · 820 mDubai International School · 850 mBayside Park 4 · 900 mKHAMIS BIN HOABA GROCERY · 990 mDubai International School · 1.1 kmBarsha Hills Mini Mart · 1.1 kmGEMS Our Indian School · 1.2 kmMall · 1.3 kmSafa Private School · 1.4 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Approximate project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationBusiness Bay Metro Station · Red Metro line · 2.7 km
MallMall · 1.3 km
Supermarketallday · 680 m
HospitalNexx Home Healthcare Services · 2.1 km
SchoolDubai International School · 850 m
ParkPark · 650 m
BeachBeach · 460 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 14, with 8,213 units and villas.

2026: 6,2352027: 1,1632028: 588No end date: 227

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Merkadh: 17

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Sobha Creek Vista Heights 91.5% — 2,076 224
Azizi Riviera Reve 76.6% Feb 2025 — 144
Azizi Riviera 50 60.9% Mar 2027 2,294 79
Azizi Riviera 68 74.6% May 2027 1,971 79
Azizi Riviera 49 54.4% Mar 2027 2,316 75
The Highbury 80% — 2,196 69
Azizi Riviera 66 91% May 2027 1,352 41
ِِAzizi Riviera 60 97.1% Mar 2027 2,125 40
Naya at District One 68.5% Sep 2027 2,106 33
Casa Serene 74% Dec 2024 — 2
Project 3532, Al Merkadh 0% Sep 2025 — 0
Azizi Riviera 53 63.2% Mar 2027 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Merkadh

Developer in DLD data District One - FZ · DLD developer no. 956

Projects registered
38
36 completed · 1 under construction · 1 not started
Units delivered
1,752
456 in the pipeline
Median build time
26 months
completed projects measured: 36
Past the DLD end date
0
of 1 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 36 completed projects with both dates. In 35 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1

When was Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1 completed?

Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1 is recorded as completed on 31 March 2020 (DLD register of 1 November 2026).

Who is the developer of Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1?

District One - FZ, as registered with DLD.

What is the DLD project number of Mohammed Bin Rashid Al Maktoum CITY- District One, Phase 1?

1366.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error